On March 13, 2015, at 0919 hours0.0106 days <br />0.255 hours <br />0.00152 weeks <br />3.496795e-4 months <br />, Secondary Containment became inoperable requiring a Technical Specification (TS) 3.6.4.1, Condition A, entry for failure to meet Surveillance Requirement 3.6.4.1.1 for Susquehanna Steam Electric Station ( SSES) Unit 1 and Unit 2. The Reactor Building ( RB) Zone 2 differential pressure fell below the TS limit of 0.25 inches water column (wc) vacuum, when an air handling plenum door was open for approximately one minute. The LCO was exited at 0930 hours0.0108 days <br />0.258 hours <br />0.00154 weeks <br />3.53865e-4 months <br /> when the differential pressure returned to 0.34 inches wc vacuum. On March 13, 2015, at 1256 hours0.0145 days <br />0.349 hours <br />0.00208 weeks <br />4.77908e-4 months <br />, this condition was determined to be reportable as an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> ENS (#50885) in accordance with 10 CFR 50.72(b)(3)(v)(C) for any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to control the release of radioactive material. SSES has no redundant Secondary Containment system.
The direct cause of the event was due to plant personnel holding the RB plenum door open for approximately one minute while performing radiation surveys.
Key Completed Actions: 1) Signs were added to the affected Unit 1 and Unit 2 exhaust fan plenum doors warning of the Secondary Containment implications, and 2) Plant personnel were coached regarding the use of the RB plenum doors.
Key Planned Action: Install signs on all major Reactor Building fan plenum doors to alert plant personnel of the Secondary Containment impacts.
There were no actual consequences to the health and safety of the public as a result of this event. An Engineering evaluation concluded that Secondary Containment could have performed its safety function of isolating as assumed in the SSES accident analysis and also of re-establishing 0.25 inches wc vacuum (i.e., drawdown time) within the assumed accident analysis time of 10 minutes. |
the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Susquehanna Steam Electric Station, Unit 2 05000388
CONDITIONS PRIOR TO THE EVENT
Unit 1 — Mode 1, 100 percent Rated Thermal Power Unit 2 — Mode 1, 100 percent Rated Thermal Power There were no systems, structures, or components that were inoperable at the start of the event and contributed to the event.
EVENT DESCRIPTION
On March 13, 2015, at 0919 hours0.0106 days <br />0.255 hours <br />0.00152 weeks <br />3.496795e-4 months <br />, Secondary Containment became inoperable requiring a Technical Specification (TS) 3.6.4.1, Condition A, entry for failure to meet Surveillance Requirement 3.6.4.1.1 for Susquehanna Steam Electric Station (SSES) Unit 1 and Unit 2. The Reactor Building (RB) Zone 2 differential pressure fell below the TS limit of 0.25 inches water column (wc) vacuum when an air handling plenum door was opened for approximately one minute. TS 3.6.4.1, Condition A, was exited at 0930 hours0.0108 days <br />0.258 hours <br />0.00154 weeks <br />3.53865e-4 months <br /> when the differential pressure returned to 0.34 inches wc vacuum. On March 13, 2015, at 1256 hours0.0145 days <br />0.349 hours <br />0.00208 weeks <br />4.77908e-4 months <br />, this condition was determined to be reportable as an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> ENS (#50885) in accordance with 10 CFR 50.72(b)(3)(v)(C) for any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to control the release of radioactive material. SSES has no redundant Secondary Containment system.
In accordance with 10 CFR 50.73(a)(2)(v)(C), this LER is being submitted for an event or condition that at the time of discovery, could have prevented the fulfillment of the safety function of Secondary Containment to control the release of radioactive material.
CAUSE OF THE EVENT
The direct cause of the event was due to plant personnel holding the RB plenum door open for approximately one minute during the performance of radiation surveys.
The apparent causes of the event were due to: 1) an insufficient questioning attitude by plant personnel.
Plenum doors are only intended to allow momentary passage. SSES's site generic plant access training instructs personnel not to prop open plant doors, and 2) the plenum access doors were not marked with signs that notified personnel of the potential impacts/consequences to Secondary Containment by opening the door.
ANALYSIS/SAFETY SIGNIFICANCE
The actual consequence of this event was a degradation of the Secondary Containment vacuum which led to an unplanned entry into TS 3.6.4.1, Condition A, for Unit 1 and Unit 2. An Engineering evaluation was performed which concluded that Secondary Containment could have performed its safety function of isolating as assumed in the SSES accident analysis and also of re-establishing 0.25 inches wc vacuum (i.e., drawdown time) within the assumed accident analysis time of 10 minutes. Therefore, the safety function of the Secondary Containment boundary and Standby Gas Treatment systems were unaffected and remained operable during this event. As such, there were no actual consequences to the health and safety of the public.
ANALYSIS/SAFETY SIGNIFICANCE (cont.) Additionally, this event will not be counted as a safety system functional failure (SSFF) for the NRC performance indicator based on the engineering evaluation that concluded there was no loss of Secondary Containment's ability to fulfill its safety function.
CORRECTIVE ACTIONS
Key Completed Actions —
- Signs were added to the affected Unit 1 and Unit 2 exhaust fan plenum doors warning of the Secondary Containment implications.
- Plant personnel were coached regarding the use of the RB plenum doors.
Key Planned Action —
- Install signs on all major Reactor Building fan plenum doors to alert plant personnel of the Secondary Containment impacts.
PREVIOUS SIMILAR EVENTS
|
---|
|
|
| | Reporting criterion |
---|
05000387/LER-2015-001 | Inoperability of the 'B' Emergency Diesel Generator due to Fuel Oil Leakage LER 15-001-01 for Susquehanna, Unit 1, Regarding Condition Prohibited by Technical Specifications Due to Drift of Reactor Pressure Steam Dome - Low Switches | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2015-001 | Condition Prohibited by Technical Specifications Due to Drift of Reactor Pressure Steam Dome - Low Switches | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System | 05000387/LER-2015-002 | Secondary Containment Inoperability Due to Failure to Meet Technical Specification Surveillance Requirement 3.6.4.1.1 | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000388/LER-2015-002 | Secondary Containment Inoperability Due To Failure to Meet Technical Specification Surveillance Requirement 3.6.4.1.1 | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000387/LER-2015-003 | Secondary Containment Inoperability Due to Failure to Meet Technical Specification Surveillance Requirement 3.6.4.1.1 LER 15-003-01 for Susquehanna, Unit 1, Regarding Secondary Containment Inoperability Due to Failure to Meet Technical Specification Surveillance Requirement 3.6.4.1.1 | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000388/LER-2015-003 | Unit 2 Automatic Reactor Scram Caused by Main Turbine Trip Due to Loss of Main Condenser Vacuum | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000387/LER-2015-004 | Secondary Containment Inoperable due to Secondary Containment Boundary Door Found Ajar | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000388/LER-2015-004 | Degraded Condition Due to Reactor Coolant Pressure Boundary Leakage Caused by Vibration and Stiff Pipe Connection | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000388/LER-2015-005 | Condition Prohibited by Technical Specifications Due to Implementation of Enforcement Guidance Memorandum (EGM) 11-003 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000387/LER-2015-006 | Loss of Safety Function due to Inoperability of Both Trains of the Standby Gas Treatment System and a Loss of Safety Function of the Control Room Emergency Outside Air Supply System due to Air Flow Controller found in Manual LER 15-006-01 for Susquehanna, Unit 1, Regarding Loss of Safety Function due to Inoperability of Both Trains of the Standby Gas Treatment System and a Loss of Safety Function of the Control Room Emergency Outside Air Supply System due to Air Flow... | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000388/LER-2015-006 | Secondary Containment Declared Inoperable Due to Secondary Containment Boundary Door 104-R Breached. | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material | 05000387/LER-2015-007 | Unit 1 'B' Inboard Main Steam Isolation Valve, HV141F022B closed during surveillance test which caused a SCRAM on Unit 1 LER 15-007-00 for Susquehanna, Unit 1, Regarding 'B' Inboard Main Steam Isolation Valve, HV141 F022B Closed During Surveillance Test Which Caused a SCRAM | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000388/LER-2015-007 | 1 of 3 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000387/LER-2015-008 | 1 of 4 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000387/LER-2015-009 | Pressure Boundary Leakage From an Inadequate Weld Repair in Small Bore Pump Seal Vent Piping LER 15-009-00 for Susquehanna, Unit 1, Regarding Pressure Boundary Leakage From an Inadequate Weld Repair in Small Bore Pump Seal Vent Piping | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded |
|