| Q | CCA | Title |
---|
05000282/FIN-2016004-02 | 2016Q4 | H.4 | Failure to Properly Implement a Post-Maintenance Test Procedure during Safety Injection System Valve Testing |
05000282/FIN-2016004-03 | 2016Q4 | H.11 | Failure to Adequately Calibrate an Electrometer |
05000282/FIN-2016004-01 | 2016Q4 | | Baffle Former Bolting Acceptance Criteria |
05000282/FIN-2017001-01 | 2017Q1 | | Failure to Evaluate Changes to NRC Approved Methodology |
05000282/FIN-2017002-03 | 2017Q2 | | Failure to Make an 8Hour Report Required by05000306/201700203 10 CFR 50.72(b)(3)(ii)(B) |
05000282/FIN-2017002-01 | 2017Q2 | H.4 | Failure to Properly Implement the Minor Maintenance Process During Door 225 Transom Maintenance |
05000282/FIN-2017002-02 | 2017Q2 | H.8 | Failure to Implement the Emergency Plan |
05000282/FIN-2017201-01 | 2017Q2 | | Security |
05000282/FIN-2017201-02 | 2017Q2 | | Security |