05000251/LER-2003-002, Regarding As-Found Cycle 20 Main Steam Safety Valve Setpoint Outside Technical Specification Limits

From kanterella
(Redirected from 05000251/LER-2003-002)
Jump to navigation Jump to search
Regarding As-Found Cycle 20 Main Steam Safety Valve Setpoint Outside Technical Specification Limits
ML033460386
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 12/03/2003
From: Jones T
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-2003-295 LER 03-002-00
Download: ML033460386 (6)


LER-2003-002, Regarding As-Found Cycle 20 Main Steam Safety Valve Setpoint Outside Technical Specification Limits
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
2512003002R00 - NRC Website

text

FPL DEC 0 3 2003 L-2003-295 10 CFR § 50.73 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:

Turkey Point Unit 4 Docket No. 50-251 Reportable Event: 2003-002-00 Date of Event: October 2, 2003 As-Found Cycle 20 Main Steam Safety Valve Setpoint Outside Technical Specification Limits The attached Licensee Event Report 251/2003-002-00 is being submitted pursuant to the requirements of 10 CFR § 50.73(a)(2)(i)(B) to provide notification of the subject event.

Very truly yours, Terry 0. Jones Vice President Turkey Point Nuclear Plant WJP Attachment cc:

Regional Administrator, USNRC, Region II Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant zj

an FPL Group company

Abstract

On October 2, 2003, Turkey Point Unit 4 was in Mode 1 and holding at approximately 49 percent (%) reactor power, while performing Technical Specification (TS) surveillance testing of the Main Steam Safety Valves (MSSV) setpoints, just prior to the Unit 4 Cycle 21 Refueling Outage. The Unit 4 "A" Steam Generator (SG) MSSV, RV-4-1400, as-found lift pressure was 1128.5 psig, which was greater than the TS allowable setpoint pressure of +/-3% of 1085 psig (1052.5 psig -

1117.5 psig). RV-4-1400 was declared inoperable and the plant entered TS action statement 3.7.1.1.b. Reactor power was at 49%, which is below the 53% reactor power required per TS 3.7.1.1.b.

RV-4-1400 was subsequently tested at 1097.9 psig, or 1.19% above the setpoint. Per ASME Operation and Maintenance (OM), Part 1, Section 1.3.4.1(e)(2), RV-4-1400 remained out of service, pending cause and corrective action determination. The cause of the high lift pressure for RV-4-1400 was determined to be micro-bonding of the nozzle and disc.

An adjustment was made of 1 flat of the adjusting nut to restore the valve to within 1%

of the setpoint pressure and the plant exited TS action statement 3.7.1.1.b. The valve was subsequently overhauled and tested twice more, with the results within 1% of the required setpoint pressure the valve was placed back in service.

Operation of the facility with the as-found setting was within analytical bounds; therefore, this event had no impact on the health and safety of the public.

NRC FORM 366 (7-2001)U.S. NUCLEAR REGULATORY COMMISSION (7-2W1)

LICENSEE EVENT REPORT (LER)

TEXT CONTINUATION FACILITY NAME (1)

DOCKET LER NUMBER (6)

PAGE (3)

YEAR SEQUENTIAL REVISION Turkey Point Unit 4 05000251 N

.U.

R Page 2 of 5 2003 002 00 TEXT (If more space is required use additional copies of NRC Form 366A) (17)

Description of the Event On October 2, 2003, Turkey Point Unit 4 was in Mode 1 and holding at approximately 49 percent (%) reactor power during the downpower for the PTN 4 Cycle 21 refueling outage.

Technical Specification (TS) surveillance testing of the Main Steam Safety Valves (MSSVs) [EIIS:SB:RV] was performed at this power level.

The TS surveillance testing was performed in accordance with procedure 4-OSP-072.5, "Main Steam Safety Valve Setpoint Verification Test".

The Unit 4 "A" Steam Generator (SG) MSSV, RV-4-1400, as-found lift pressure tested at 1128.5 psig, or 4.01% above the setpoint pressure.

This is greater than the TS allowable setpoint pressure range of +/-3% of 1085 psig (1052.5 psig to 1117.5 psig).

RV-4-1400 was declared inoperable and the plant entered TS Action Statement 3.7.1.1.b.

Since reactor power was at 49%, no reactivity changes were required in order to comply with TS 3.7.1.1.b.

RV-4-1400 was subsequently tested at 1097.9 psig, or 1.19% above the setpoint.

An adjustment was made of 1 flat of the adjusting nut to restore the valve to within 1% of the setpoint pressure and the plant exited TS action statement 3.7.1.1.b. The valve was tested twice more, with results within 1% of the required setpoint pressure.

Although the valve had been adjusted and tested within 1% of the required setpoint pressure, based on the requirements of ASME OM, Part 1, Section 1.3.3.1(e)(2), the valve was not returned to service until the cause was determined and corrected.

RV-4-1400 was subsequently overhauled, tested and returned to service.

As a result of the RV-4-1400 failed test, the Inservice Testing (IST) program required test expansion for an additional 2 relief valves over the planned testing requirement of 4 relief valves for this Unit 4 outage.

All other MSSVs tested were within the +/-3% range of the required setpoint pressure.

Cause of the Event

Based on inspection of valve internals, the cause of the high as-found lift setpoint for RV-4-1400 was determined to be micro-bonding of the nozzle and disc.

Lift pressure test results that exhibit a moderate to large reduction following the as-found test (typically 30 psig) are symptomatic of this phenomenon.

Micro-bonding of the nozzle and disc can occur when the harder disc (410 stainless steel) causes microscopic galling of the softer nozzle (316 stainless steel) during plant heatup, due to the differential thermal expansion between the contact surfaces.

These small gall beads cause the disc and nozzle to fuse to a limited degree.U.S. NUCLEAR REGULATORY COMMISSION (7-2W1)

LICENSEE EVENT REPORT (LER)

TEXT CONTINUATION FACILIlY NAME (1)

DOCKET LER NUMBER (6)

PAGE (3)

YCEAR SEQUENTIAL I NUMBER Turkey Point Unit 4 05000251 E VUSE Page 3 of 5 2003 002 00 TEXT (if more space Is required use additional copies of NRC Form 366A) (17)

Under these conditions, the first as-found lift pressure is often significantly higher than subsequent lifts.

Investigations performed by Altran Corporation for PG&E support this theory as a potential reason why the first as-found lift pressure is often significantly higher than subsequent lifts.

The high initial lift pressure, followed by the subsequent test acceptable lift pressure, is consistent with the phenomenon of micro-bonding.

The traditional corrective action for micro-bonding has been to resurface the nozzle and disc (disc is usually replaced) during the safety valve overhaul.

However, it was noted that there had been an apparent increasing trend in occurrences of micro-bonding, which is apparently related to seating surface finish.

The overhaul procedure had been recently revised to minimize the contribution to micro-bonding of seat finish.

RV-4-1400 was overhauled to lap the seating surfaces to eliminate the micro-galling associated with this phenomena; however, a rougher surface finish was specified to an L4-L8 profile (i.e., Lapped to a 4-8 l-in finish) in order to reduce the likelihood of future micro-bonding occurrences.

Additionally, different disc materials will be evaluated to further improve minimizing the occurrence of micro-bonding in the MSSVs.

Analysis of the Event

The existence of micro-bonding in RV-4-1400 is an indication that the condition may well have developed during the operating cycle and that the condition existed prior to the surveillance testing.

Based on this past operability assessment, the condition could have existed during Unit 4 Cycle 20 operation; this event is reportable under 10 CFR 50.73(a)(2)(i)(B).

Analysis of Safety Significance The MSSVs were designed and constructed in accordance with the requirements of the ASME Code,Section III (ref. UFSAR Table 10.1-1).

The function of the MSSVs is to provide overpressure protection for the shell side of the SGs (also ASME III components; ref. UFSAR table 4.1-9).

The MSSVs are classified as safety related, Quality Group B components.

Unit 4 was in Mode 1 at approximately 49 percent reactor power, when RV-4-1400 on the "A" steam generator failed its lift pressure surveillance test.

The unit entered TS 3.7.1.1.b action statement and complied with the action statement by remaining at approximately 49 percent reactor power (less than 53 percent as required TS Table 3.7-1).U.S. NUCLEAR REGULATORY COMMISSION (7-2001)

LICENSEE EVENT REPORT (LER)

TEXT CONTINUATION FACILITY NAME (1)

DCNUMBER 2

LER NUMBER (6)

PAGE (3)

YEAR SEQUNTIAL I REVISION I~~~~~~

YEAR lSENQUMEl l NUMBER Turkey Point Unit 4 05000251 N

Page 4 of 5 2003 002 00 TEXT (If more space Is required use additional copies of NRC Form 366A) (17)

This is the maximum allowable power level with one MSSV inoperable on any steam generator.

All other MSSVs tested were within +/-3% of the required setpoint pressure.

A review of the Turkey Point safety analyses was performed to assess the impact of RV-4-1400 "as found" condition on Unit 4 Cycle 20 operation.

The analyses where the MSSVs are modeled include:

- Uncontrolled Rod Withdrawal At Power
- Feedwater System Malfunction
- Increase in Steam Flow
- Loss of Flow
- Locked Rotor
- Loss of External Electrical Load/Turbine Trip
- Loss of Normal Feedwater With/Without Loss of Non-Emergency AC Power
- Small Break LOCA The review indicated that only the events that are susceptible to overpressure conditions might be impacted by the "as found" condition of the subject MSSVs.

These include:

Loss of External Electrical Load (LOL)/Turbine Trip (Limiting Event)

Rod Withdrawal From Power (RWFP)

Loss of Normal Feedwater (LONF) With/Without Loss of Non-Emergency AC Power Safety significance was evaluated on a system-wide basis for the MSSVs. The limiting overpressurization event is the Loss of External Electrical Load (LOL)/Turbine Trip. Based on the dynamics of the LOL safety analysis it is concluded that the "as found" MSSV condition does not result in the LOL design basis analysis being adversely impacted.

This is because the "as found" opening setpoints of the second and third MSSV banks are lower than +3% above the setpoint assumed in the LOL safety analysis.

This lower "as found" opening setpoints compensate the higher "as found" opening setpoint for the first bank.

Based on the above discussion it is concluded that the overpressure design basis criteria for the LOL event were not exceeded during Cycle 20 as a result of the "as found" MSSV opening setpoints.U.S. NUCLEAR REGULATORY COMMISSION (7-2W1)

LICENSEE EVENT REPORT (LER)

TEXT CONTINUATION FACILITY NAME (1)

DONUMERT LER NUMBER (6)

PAGE (3)

B E

NUMBER 2 NUMBER Turkey Point Unit 4 05000251 Page 5 of 5 2003 -

002 00 TEXT (If more space Is required, use additional copies of NRC Form 366A) (17)

Operation of the facility with the as-found setting was within analytical bounds; therefore, this event is evaluated as low safety significance and had no impact on the health and safety of the public.

Corrective Actions

(1) RV-4-1400 was disassembled and overhauled, with the seating surfaces lapped to an L4 -

L8 l-in finish acceptance criteria.

Additional Information

Failed Components Identified Manufacturer:

Crosby Model Number:

Style HA-55-FN, size 6R10, direct acting, spring loaded, open bonnet valves Component:

Main Steam Safety Relief Valve

Similar Events

Turkey Point Unit 3, Docket No. 50-250, Reportable Event: 2003-004-00, dated February 27, 2003, "As-Found Cycle 19 Main Steam Safety Valve Setpoints Outside Technical Specification Limits", Letter L-2003-087, dated April 25, 2003.