Technical Specification (TS) 5.4, Procedures, requires that the applicable procedures recommended in
Regulatory Guide 1.33 be established, implemented, and maintained.
Regulatory Guide 1.33 states that maintenance that could affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with procedures appropriate to the circumstances. Contrary to this requirement, procedure 12EHP4030056218, Automatic Operation of
Auxiliary Feedwater Pumps, was not performed as written in the procedure. Specifically, pages were skipped which resulted in the 2CD
EDG inadvertently starting during the surveillance. Screening: The issue resulted in momentary loss of the T21C and T21D vital busses until the 2CD
EDG reached rated speed and connected to the busses. The reactor was defueled at the time. One train of spent fuel pool cooling was lost for several minutes, but the other train stayed in service and there was no apparent change in spent fuel pool temperature. The issue screened as minor based on the guidance in
IMC 0612 Appendix E because there were no safety consequences and there was no
transient of any significance. Violation: This failure to comply with
TS 5.4 constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs
Enforcement Policy.