IR 05000213/1998005 | 21 December 1998 | Insp Rept 50-213/98-05 on 980720-1102.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support |
ML20133A503 | 24 December 1996 | Insp Rept 50-213/96-11 on 960921-1115.Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant Support |
ML20133B659 | 7 June 1996 | Forwards Briefing Package on Status of Plants as Background for Visit by Northeast Utilities on 960611 |
ML20134B493 | 16 February 1994 | Forwards Updated Briefing Package for Visit by Util Officials W/Nrc Chairman,Commission,Edo,Director OI & Director Oe.Requests Replacement of Encls 1 & 2 in 940215 Package,Retaining Supporting Attachment 1 Documentation |
ML20127J539 | 30 November 1992 | Connecticut Yankee Structural Reevaluation of Plant Structures to Address SEP Topic III-7.B Load Combinations Code Changes |
NRC Generic Letter 1989-18 | 6 September 1989 | NRC Generic Letter 1989-018: Resolution of Unresolved Safety Issue A-17, Systems Interactions in Nuclear Power Plants. |
A07693, Outlines General Approach Which Util Intends to Utilize in Responding to Generic Ltr 88-20, Individual Plant Exams for Severe Accident Vulnerabilities & Summarizes Key Points of Past Involvement in Field of PRA & Accident Mgt | 27 July 1989 | Outlines General Approach Which Util Intends to Utilize in Responding to Generic Ltr 88-20, Individual Plant Exams for Severe Accident Vulnerabilities & Summarizes Key Points of Past Involvement in Field of PRA & Accident Mgt |
B13019, Forwards Update on Isap Topic Reviews Discussed in Util ,Description of New Topics Being Added to Isap, Updated Integrated Implementation Schedule & Summary Table of Isap ARM Scores & Installation man-rem for Each Project | 2 March 1989 | Forwards Update on Isap Topic Reviews Discussed in Util ,Description of New Topics Being Added to Isap, Updated Integrated Implementation Schedule & Summary Table of Isap ARM Scores & Installation man-rem for Each Project |
A06748, Forwards Response to NRC Topic Evaluations Status of Integrated Safety Assessment Program Topics & Review of Draft NUREG-1185.Attachment a Provides Discussion on Scope, Evaluation & Prioritization of Each Topic | 13 November 1987 | Forwards Response to NRC Topic Evaluations Status of Integrated Safety Assessment Program Topics & Review of Draft NUREG-1185.Attachment a Provides Discussion on Scope, Evaluation & Prioritization of Each Topic |
ML20237J100 | 31 July 1987 | Integrated Safety Assessment Report.Integrated Safety Assessment Program.Haddam Neck Plant.Docket No. 50-213. (Connecticut Yankee Atomic Power Company) |
ML20209C716 | 31 December 1986 | Vols 1 & 2 to Isap,Haddam Neck Plant,Final Rept |
B12121, Forwards Reviews for Isap Topic 1.05, Seismic Structural Mods, Topic 1.09, Design Codes,Design Criteria,Load Combinations & Topic 1.57, Flooding of Compartments by Backflow, Per 850517 Commitment | 30 July 1986 | Forwards Reviews for Isap Topic 1.05, Seismic Structural Mods, Topic 1.09, Design Codes,Design Criteria,Load Combinations & Topic 1.57, Flooding of Compartments by Backflow, Per 850517 Commitment |