| Q | CCA | Title |
---|
05000382/FIN-2016001-01 | 2016Q1 | H.8 | Failure to Assess and Manage the Increase in Risk from Emergent Maintenance Activities |
05000382/FIN-2015407-01 | 2016Q1 | | Security |
05000382/FIN-2015407-02 | 2016Q1 | | Security |
05000382/FIN-2016002-02 | 2016Q2 | H.8 | Failure to Properly Assess and Manage Risk When Performing Dry Cooling Tower Maintenance |
05000382/FIN-2016002-03 | 2016Q2 | H.5 | Failure to Perform Drills Required by the Site Emergency Plan |
05000382/FIN-2016002-01 | 2016Q2 | P.1 | Failure to Properly Pre-Plan and Perform Maintenance on the Cable Vault and Switchgear Ventilation System |
05000382/FIN-2016002-04 | 2016Q2 | P.2 | Failure to Account for Starting Air Design Features in Emergency Diesel Operating Procedures |
05000382/FIN-2016403-01 | 2016Q4 | H.1 | Security |
05000382/FIN-2016403-02 | 2016Q4 | H.12 | Security |
05000382/FIN-2016008-01 | 2016Q4 | H.14 | Failure to Control Nonconforming Parts |
05000382/FIN-2016004-01 | 2016Q4 | H.4 | Failure to Ensure Appropriate Post-Maintenance Testing on Essential Chiller B |
05000382/FIN-2016008-02 | 2016Q4 | P.1 | Failure to Perform Operability Determinations for Nonconforming Conditions |
05000382/FIN-2016008-03 | 2016Q4 | P.3 | Failure to Include Appropriate Quantitative Acceptance Criteria for the Reconstituted Feedwater/Emergency Feedwater Monitoring Plan Associated with Steam Generator Replacement Induced Vibration |
05000382/FIN-2016008-04 | 2016Q4 | | Departure from Approved Method to Determine Steam Generator Internal Loads During Main Steam Line Break |