2010/01/21-Memorandum and Order (Scheduling Initial Prehearing Conference)
ML100210793
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 01/21/2010
From: Bollwerk G P
Atomic Safety and Licensing Board Panel
To:
SECY RAS
References
50-438-CP, 50-439-CP, ASLBP 10-896-01-CP-BD01, RAS 17008
Download: ML100210793 (5)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD PANEL Before the Licensing Board:

G. Paul Bollwerk, III, Chairman Dr. Anthony J. Baratta Dr. William W. Sager In the Matter of TENNESSEE VALLEY AUTHORITY (Bellefonte Nuclear Plant Units 1 and 2)

Docket Nos. 50-438-CP and 50-439-CP

ASLBP No. 10-896-01-CP-BD01

January 21, 2010 MEMORANDUM AND ORDER (Scheduling Initial Prehearing Conference)

After reviewing (1) applicant Tennessee Valley Authority's (TVA) August 26, 2008 request that the Nuclear Regulatory Commission (NRC) reinstate the 10 C.F.R. Part 50

construction permits (CP) for two pressurized water reactors TVA had been in the process of

building at its Bellefonte site near Scottsboro, Alabama, see Letter from Ashok S. Bhatnager, Senior Vice President, TVA, to NRC Document Control Desk at 1 (Aug. 26, 2008) (ADAMS

Accession No. ML082410087); and (2) Joint Petitioners 1 May 8, 2009 hearing petition contesting the TVA reinstatement request, see Petition for Intervention and Request for Hearing by [Joint Petitioners] (May 8, 2009), the Licensing Board has tentatively concluded that it would

be beneficial to conduct an initial prehearing conference during which it will entertain oral

argument regarding the admissibility of the hearing petition. Certain of the administrative details

associated with that argument are set forth below:

1 Joint Petitioners include the Blue Ridge Environmental Defense League (BREDL) and its Bellefonte Efficiency and Sustainability Team chapter and the Southern Alliance for Clean Energy. A.Initial Prehearing Conference Venue The Board intends to conduct the argument from the Licensing Board Panel's Rockville, Maryland hearing room, with the proceeding being webstreamed so that members of the public in the vicinity of the Bellefonte facility can view/listen to the argument via the internet. To

minimize travel time and expenses, as an alternative to all participants appearing in Rockville, the Board has made arrangements with the agency's Region II office to make available a

conference room in its office space in the Sam Nunn Atlanta Federal Center, 61 Forsyth Street, SW, Atlanta, Georgia, from which representatives of Joint Petitioners or TVA (if they wish to do

so) can participate in the argument by videoconference.

2 In the joint scheduling report requested in section B below, Joint Petitioners and applicant TVA should indicate whether they

wish to avail themselves of this opportunity, as opposed to participating by teleconference or in person from the Licensing Board Panel's Rockville hearing room.

3 B.Date and Time for the Oral Argument The Board is available on the following days to conduct the oral argument, which would begin at 9:00 a.m. Eastern Time (ET):

2 Absent some indication to the contrary in the joint scheduling report requested in section B below, the Board presumes that NRC staff representatives would prefer to participate from Rockville. Also, representatives for the participants should anticipate that any individual

with whom they wish to consult on technical or other questions that may arise during the

argument would need to be present in the same location from which they are participating, absent some other arrangement (e.g., consultation by cell phone during a recess), which

should be described in the joint scheduling report and approved by the Board prior to the

conference.

3 If one or more of the participants decides to take part in the argument from the Region II conference room via videoconference, because that room is publicly accessible, it

also will be available to those members of the public that wish to view the proceeding. Monday, February 22, 2010 Friday, February 26, 2010 Monday, March 1, 2010 Friday, March 5, 2010 The Board requests that on or before Tuesday, January 26, 2010 , TVA, the NRC staff, and Joint Petitioners provide the Board with a joint report that, among other things, specifies a date or dates when all the participants are available for an oral argument and indicates from

which location their representatives intend to participate. Thereafter, the Board will notify the

participants regarding the date of the argument, which the Board anticipates should last no

more than one day.

It is so ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING BOARD

G. Paul Bollwerk, III CHAIRMAN Rockville, Maryland January 21, 2010 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-438-CP

) and 50-439 CP (Bellefonte Nuclear Power Plant - ) Units 1 and 2) ) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LB MEMORANDUM AND ORDER (SCHEDULING INITIAL PREHEARING CONFERENCE) have been served upon the following persons by the Electronic Information Exchange (EIE) with additional service by email on persons marked with*. U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel

Mail Stop: T-3F23 Washington, DC 20555-0001 G. Paul Bollwerk, III, Chair

Administrative Judge

E-mail: paul.bollwerk@nrc.gov Dr. Anthony J. Baratta Administrative Judge

E-mail: ajb5@nrc.gov

Dr. William W. Sager

Administrative Judge E-mail: william.sager@nrc.gov

Ann Hove, Law Clerk

E-mail: ann.hove@nrc.gov U.S. Nuclear Regulatory Commission Office of the General Counsel

Mail Stop: O-15D21 Washington, DC 20555-0001 Edward Williamson, Esq.

E-mail: elw2@nrc.gov Andrea' Jones, Esq.

E-mail: axj4@nrc.gov Brian Newell, Paralegal E-mail: bpn1@nrc.gov David E. Roth, Esq.

E-mail: david.roth@nrc.gov Jeremy Suttenberg, Esq.

E-mail: Jeremy.suttenberg@nrc.gov OGC Mail Center

E-mail: OGCMailCenter@nrc.gov

U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Mail Stop: O-16C1 Washington, DC 20555-0001

OCAA Mail Center E-mail: ocaamail@nrc.gov U.S. Nuclear Regulatory Commission Office of the Secretary of the Commission Mail Stop: O-16C1 Washington, DC 20555-0001

Hearing Docket E-mail: hearingdocket@nrc.gov

Docket Nos. 50-438 and 50-439-CP LB MEMORANDUM AND ORDER (SCHEDULING INITIAL PREHEARING CONFERENCE) 2 Morgan, Lewis & Bockius, LLP Counsel for Tennessee Valley Authority

1111 Pennsylvania Ave., N.W.

Washington, DC 20004

Kathryn M. Sutton, Esq.

ksutton@morganlewis.com Martin J. O'Neill, Esq.

E-mail: martin.oneill@morganlewis.com Lawrence Chandler, Esq.

E-mail: lchandler@morganlewis.com Mary L. Freeze, Legal Secretary E-mail: mfreeze@morganlewis.com Angela Perry Angela.perry@morganlewis.com Tennessee Valley Authority Office of the General Counsel

400 W. Summit Hill Drive, WT 6A-K

Knoxville, TN 37902

Edward J. Vigluicci, Esq.

E-mail: ejvigluicci@tva.gov Scott A. Vance, Esq.

E-mail: savance@tva.gov Maureen H. Dunn, Esq.

E-mail: mhdunn@tva.gov Maria V. Gillen, Esq.

mvgillen@tva.gov Christopher Chandler, Esq.

E-mail: ccchandler0@tva.gov Blue Ridge Environmental Defense League, Inc. (BREDL)

Bellefonte Efficiency & Sustainability Team

(BEST)

P.O. Box 88

Glendale Springs, NC 28629 Louis A. Zeller E-mail: bredl@skybest.com

Eckert Seamans Cherin & Mellott, LLC Counsel for Westinghouse Electric Company

600 Grant Street, 44 th Floor Pittsburgh, PA 15219

Barton Z. Cowan, Esq.

E-mail: teribart61@aol.com Southern Alliance for Clean Energy 428 Bull Street Savannah, GA 31401 Sara Barczak*

E-mail: sara@cleanenergy.org

[Original signed by Evangeline S. Ngbea]

Office of the Secretary of the Commission

Dated at Rockville, Maryland

this 21 st day of January 2010.