UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2010
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF THE MAY 11, 2010, PUBLIC MEETING TO DISCUSS THE 2009 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT
On May 11, 2010, the Nuclear Regulatory Commission (NRC) held a public meeting at the Holiday Inn Express Conference Room in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representativ es to discuss the NRC's assessment of the safety performance of Palisades Nuclear Plant for the period from January 1, 2009, through December 31, 2009. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML101040711 and ML101300433, respectively.
The NRC began the meeting with an overview of the NRC's Mission, the Reactor Oversight Process (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC's assessment of Palisades performance in 2009, which was documented in the March 3, 2010, End-Of-Cycle assessment letter (ML100610274).
The licensee then provided a response to the NRC's assessment. The licensee presentation can be found in the ADAMS as ML101330508. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Several members of the public asked questions that covered the emergency plan, ground water monitoring, spent fuel, reactor head and steam generator replacements, and license renewal. A list of principal meeting attendees can be found in the attached enclosure.
/RA/
John B. Giessner, Chief Branch 4 Division of Reactor Projects
Docket No. 50-255;72-007 License No. DPR-20
Enclosure:
As Stated
cc w/encl: Distribution via ListServ
PUBLIC MEETING PRINCIPAL ATTENDEES May 11, 2010
Nuclear Regulatory Commission
S. West, Director, Division of Reactor Projects, RIII J. Giessner, Branch Chief, Division of Reactor Projects, RIII J. Ellegood, Senior Resident Inspector, Palisades T. Taylor, Resident Inspector, Palisades E. Duncan, Chief, Plant Support Branch, Division of Reactor Safety, RIII
C. Lipa, Chief, Materials Control, ISFSI, and Decommissioning Branch, Division of Nuclear Materials Safety, RIII J. Cassidy, Senior Health Physicist, Division of Reactor Safety, RIII F. Tran, Reactor Engineer, Division of Reactor Projects, RIII M. Chawla, Project Manager, Office of Nuclear Reactor Regulation V. Mitlyng, Senior Public Affairs Officer, RIII C. Hernandez, Resident Office Assistant, Palisades
Entergy Nuclear Operations, Inc.
C. Schwarz, Site Vice President T. Kirwin, Plant Manager A. Blind, Entergy D. Hamilton, Entergy M. Savage, Entergy K. Madden, Entergy
Other Attendees
T. Davis, Public
D. Rozanski, Public J. Bredeweg, Don't Waste Michigan C. Lowe, IGE - Don't Waste Michigan F. Jason, Don't Waste Michigan M. Merla B. Burr, City of South Haven
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2010
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF THE MAY 11, 2010, PUBLIC MEETING TO DISCUSS THE 2009 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT
On May 11, 2010, the Nuclear Regulatory Commission (NRC) held a public meeting at the Holiday Inn Express Conference Room in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representativ es to discuss the NRC's assessment of the safety performance of Palisades Nuclear Plant for the period from January 1, 2009, through December 31, 2009. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML101040711 and ML101300433, respectively.
The NRC began the meeting with an overview of the NRC's Mission, the Reactor Oversight Process (ROP), national ROP results, and the Action Matrix in general. This was followed by a
discussion of the NRC's assessment of Palisades performance in 2009, which was documented in the March 3, 2010, End-Of-Cycle assessment letter (ML100610274).
The licensee then provided a response to the NRC's assessment. The licensee presentation can be found in the ADAMS as ML101330508. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Several members of the public asked questions that covered the emergency plan, ground water monitoring, spent fuel, reactor head and steam generator replacements, and license renewal. A list of principal meeting attendees can be found in the attached enclosure.
/RA/ John B. Giessner, Chief Branch 4 Division of Reactor Projects Docket No. 50-255;72-007 License No. DPR-20
Enclosure:
As Stated
cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2009\EOC Letters\EOC Meeting Summaries\Palisades EOC 09 Public Meeting Summary.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME FTran:dpt JGiessner DATE 05/19/2010 05/21/2010 OFFICIAL RECORD COPY Letter to Entergy Nuclear Operations, Inc. from J. Giessner dated May 21, 2010.
SUBJECT:
SUMMARY
OF THE MAY 11, 2010, PUBLIC MEETING TO DISCUSS THE 2009 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT
DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-1 RidsNrrPMPalisades Resource
RidsNrrDirsIpab Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource