Post Fukushima Order Status - 06-29-2018
ML18180A226
Person / Time
Issue date: 06/29/2018
From: Bernardo R J
Beyond-Design-Basis Management Branch
To:
Bernardo R J, NRR/DLP, 415-2621
References
EA-12-049, EA-12-051, EA-12-109
Download: ML18180A226 (2)


Text

June 29, 2018 Post Fukushima Order Implementation Status Mitigating Strategies (MS) Order (EA-12-049) Compliance Status

- As of June 18 , 2018, all operating power reactor units are in compliance with Order EA-12-049. - The NRC staff perform s inspections in accordance with NRC Inspection Manual Temporary Instruction 2515/191 (TI

-191) after all units at a site are in compliance to verify that required FLEX equipment and connections are in place.

- The staff has completed TI

-191 inspections at 51 sites. Spent Fuel Pool Instrumentation (SFPI) Order (EA-12-051) Compliance Status

- As of June 30, 2017, all operating power reactor units are in compliance with Order EA-12-0 51. - The NRC staff inspect s for compliance with the SFPI Order in conjunction with the inspection s for Order EA-12-049. Severe Accident Capable Hardened Containment Vent System (HCVS) Order (EA-13-109) Compliance Status

- Order EA-13-109 established a schedule for 30 applicable licensees (boiling water reactors with Mark I or Mark II containments) to achieve full compliance with Phase 1 (wetwell vent) by June 30, 2018 and full compliance with Phase 2 (drywell vent or a strategy that makes drywell venting unlikely) by June 30, 2019. - Two units have been granted extensions to the required compliance dates until after their planned final shutdown dates. These units have operable hardened vents in place providing compensatory measures.

- As of June 29 , 2018, 2 8 applicable reactor units are in compliance with Phase 1, and 1 5 applicable reactor units are in compliance with Phase 2. - The NRC staff will perform inspections for compliance with the HCVS Order in accordance with NRC Inspection Manual Temporary Instruction 2515/19 3 (TI-19 3) after all units at a site are in compliance

. - A pilot TI

-193 inspection is planned for summer of 2018

. A table with the Order Compliance Status is provided on the following page. Site names that are highlighted in dark green have completed all post-Fukushima activities and the NRC has issued a completion letter.

June 29, 2018 Order Implementation Status for Operating Reactors

- By Region