ML17103A185

From kanterella
Revision as of 21:30, 18 May 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Dresden Nuclear Power Station, Unit 3 - Notification of Readiness for NRC 95001 Inspection
ML17103A185
Person / Time
Site: Dresden Constellation icon.png
Issue date: 04/11/2017
From: Karaba P J
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
17-0013
Download: ML17103A185 (1)


Text

April 11, 2017 SVPL TR: #17-0013 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001

Subject:

Dresden Nuclear Power Station, Unit 3 Renewed Facility Operating License No. DPR-25 NRC Docket No. 50-249 Notification of Readiness for NRC 95001 Inspection

References:

Dresden Nuclear Power Station 6500 North Dresden Road Morris, IL 60450 1) Letter from Cynthia Pederson (NRC) to Bryan Hanson, "Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation Letter for Dresden Unit 3", dated February 27, 2017. In the referenced letter, Exelon Generation Company, LLC (EGC) was informed that based on the Unit 3 HPCI Auxiliary Oil Pump failure, the NRC determined that Dresden Nuclear Power Station (DNPS) is in the Regulatory Response Column of the Reactor Oversight Process Action Matrix. As a result of the White finding, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001. Based on discussions with the NRC staff, EGC requests that the NRC begin the inspection in June 2017. There are no regulatory commitments contained in this submittal. Should you have any questions concerning this letter, please contact Mr. Bruce Franzen, Regulatory Assurance Manager, at (815) 416-2800. __ Peter J. Karaba Site Vice President Dresden Nuclear Power Station