Fort Calhoun Station, Unit 1, and Independent Spent Fuel Storage Installation - 2024 Decommissioning Funding Plan Required 72.30(c) Updated Financial Information
ML24325A092
Person / Time
Site: Fort Calhoun  
Issue date: 11/19/2024
From: Uehling T
Omaha Public Power District
To:
Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk
References
LIC-24-0016
Download: ML24325A092 (1)


Text

10 CFR 72.30 November 19, 2024 LIC-24-0016 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285 Fort Calhoun Station Independent Spent Fuel Storage Installation NRC Docket No.72-054

Subject:

Fort Calhoun Station, Unit No. 1, 2024 Omaha Public Power District (OPPD) Nuclear Decommissioning Funding Plan Required 72.30(c) Updated Financial Information for the Fort Calhoun Station Independent Spent Fuel Storage Installation (ISFSI)

References:

1. Letter from OPPD (B. Pearson) to USNRC (Document Control Desk) Fort Calhoun Station, Unit No. 1, 2018, 2021, and 2024 Triennial Omaha Public Power District (OPPD) Nuclear Decommissioning Funding Plan Required Supplement for the Fort Calhoun Station Independent Spent Fuel Storage Installation (ISFSI), dated August 12, 2024 (LIC-24-0010)

(ML24276A214)

2. Letter from OPPD (B. Pearson) to USNRC (Document Control Desk) Intent to Submit a Supplement to Fort Calhoun Station, Unit No. 1, 2021, and 2024 Omaha Public Power District (OPPD) Nuclear Decommissioning Funding Plan Required 72.30(c) Update, dated October 10, 2024 (LIC-24-0013)
3. Letter from OPPD (T. Uehling) to USNRC (Document Control Desk) Supplement to Fort Calhoun Station, Unit No. 1, 2021, and 2024 Omaha Public Power District (OPPD) Nuclear Decommissioning Funding Plan Required 72.30(c) Update for the Fort Calhoun Station Independent Spent Fuel Storage Installation (ISFSI), dated October 10, 2024 (LIC 0014)

In Reference 1, OPPD submitted a letter stating that Fort Calhoun Station identified omissions of regulatory requirements in their original submittal (Reference 2). Fort Calhoun Station notified the NRC of the issue with the submittal and Fort Calhoun Stations intent to provide a supplement to the submittal (Reference 2) that fully addresses the requirements of 10 CFR 72.30(c). A supplemental submission was provided in Reference 3 to provide an updated Decommissioning Funding Plan for 2021 and 2024. provides the financial information for the year 2024, specifically in accordance with 10 CFR 72.30(c).

No commitments to the NRC are made in this letter.

If you should have any questions about the enclosed reports, please contact Mr. Ben Pearson, Manager

- Regulatory Assurance & Emergency Planning, at 531-226-7249.

Respectfully, Timothy S. Uehling Sr. Director of Nuclear Decommissioning TSU/bpp

Enclosures:

1. Part 72.30(c) 2024 Financial information for Fort Calhoun Station, Unit. No. 1.

c:

T. Liu, NRC Senior Project Manager J. D. Parrott, NRC Senior Project Manager

U.S. Nuclear Regulatory Commission LIC-24-0016 Page 1 ENCLOSURE 1 FORT CALHOUN STATION UNIT NO. 1 2024 OMAHA PUBLIC POWER DISTRICT NUCLEAR DECOMMISSIONING FUND PLAN FINANCIAL INFORMATION FORT CALHOUN STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

U.S. Nuclear Regulatory Commission LIC-24-0016 Page 2 OMAHA PUBLIC POWER DISTRICT ISFSI Decommissioning Cost Estimate Attachment A (thousands of 2023 dollars)

Activity Description Removal Costs Packaging Costs Transport Costs LLRW Disposal Costs Other Costs Total Costs Burial Volume Class A (cubic feet)

Craft Manhours Oversight and Contractor Manhours Decommissioning Contractor Planning (characterization, specs and procedures) 159 $

159 793 Decontamination (activated disposition) 2,743 $

2,743 15,884 License Termination (radiological surveys) 618 $

618 4,224 Subtotal 2,743 $

777 $

3,520 20,901 Supporting Costs NRC and NRC Contractor Fees and Costs 297 $

297 560 Insurance 551 $

551 Property Taxes Corporate A&G 1,282 $

1,282 non-Labor Overhead 51 $

51 Security Staff Costs 451 $

451 8,320 Oversight Staff Costs 689 $

689 8,320 Subtotal 3,320 $

3,320 17,200 Total (w/o contingency) 2,743 $

4,097 $

6,840 38,101 Total (w/25% contingency) 3,429 $

5,121 $

8,550