Audit Plan for the Staff Review of the NuScale Power, LLC Supplement 1 to TR-1015-18653-P-A, Design of the Highly Integrated Protection System Platform, TR-147121, Revision 0
ML25199A072
Person / Time
Site: 99902078
Issue date: 07/22/2025
From: Getachew Tesfaye
NRC/NRR/DNRL/NRLB
To: Jardaneh M
NRC/NRR/DNRL/NRLB
References
TR-1015-18653-P-A, TR-147121, Rev. 0
Download: ML25199A072 (5)


Text

July 22, 2025 MEMORANDUM TO:

Mahmoud Jardaneh, Chief New Reactor Licensing Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation FROM:

Getachew Tesfaye, Senior Project Manager /RA/

New Reactor Licensing Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation

SUBJECT:

AUDIT PLAN FOR THE STAFF REVIEW OF THE NUSCALE POWER, LLC SUPPLEMENT 1 TO TR-1015-18653-P-A, "DESIGN OF THE HIGHLY INTEGRATED PROTECTION SYSTEM PLATFORM," TR-147121, REVISION 0 By letter dated February 25, 2025, NuScale Power, LLC (NuScale) submitted Supplement 1 to TR-1015-18653-P-A,"Design of the Highly Integrated Protection System Platform," TR-147121, Revision 0. (Agencywide Documents Access and Management System Accession No. ML25056A296). The purpose of this audit is to review documents that support the staff review this supplement.

The audit will begin on July 22, 2025, with an Entrance meeting. The audit is being conducted primarily via the established NuScale Electronic Reading Room and at NuScale s offices in Rockville, Maryland and Corvallis, Oregon. The U.S. Nuclear Regulatory Commission (NRC) headquarters offices can also be used for hybrid (virtual/in-person) audit meetings, as appropriate. The contents of the audit plan are provided as an enclosure to this memorandum.

Docket No. 99902078

Enclosure:

Audit Plan cc w/encl.: NuScale Power, LLC Listserv CONTACT: Getachew Tesfaye, NRR/DNRL 301-415-8013

ML25199A072

  • via email NRR-106 OFFICE DNRL/NRLB: PM DNRL/NLIB: LA DNRL/NRLB: BC DNRL/NRLB: PM NAME GTesfaye SGreen*

MJardaneh

  • GTesfaye DATE 07/16/2025 07/21/2025 07/18 /2025 07/22/2025 Enclosure UNITED STATES NUCLEAR REGULATORY COMMISSION AUDIT PLAN FOR THE STAFF REVIEW OF THE NUSCALE POWER, LLC SUPPLEMENT 1 TO TR-1015-18653-P-A, "DESIGN OF THE HIGHLY INTEGRATED PROTECTION SYSTEM PLATFORM," TR-147121, REVISION 0 DOCKET NO. 99902078 AUDIT PLAN APPLICANT:

NuScale Power, LLC (NuScale)

CONTACTS:

Licensing Supervisor: Amanda Bode DURATION:

July 22, 2025 - December 31, 2025 LOCATION:

U.S. Nuclear Regulatory Commission (NRC) Headquarters (via NuScale Electronic Reading Room (eRR) and hybrid (virtual/in-person))

One White Flint North 11545 Rockville Pike Rockville, Maryland 20852-2738 NuScale 11333 Woodglen Drive, Suite 205 Rockville, Maryland 20852 NuScale 1100 NE Circle Blvd Corvallis, Oregon 97330 NRC AUDIT TEAM:

Mahmoud Jardaneh Branch Chief, DNRL/NRLB Getachew Tesfaye Senior Project Manager, DNRL/NRLB Fanta Sacko Branch Chief, DEX/EICB Dinesh Taneja Senior Electronics Engineer, DEX/EICB Jaison Monachan Electronics Engineer, DEX/EICB

I.

BACKGROUND AND OBJECTIVES By letter dated February 25, 2025, NuScale Power, LLC (NuScale) submitted Supplement 1 to TR-1015-18653-P-A,"Design of the Highly Integrated Protection System Platform," TR-147121, Revision 0. (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25056A296). The purpose of this audit is to review documents that support the staff review this supplement. The staff audits material that may be needed to make a reasonable assurance finding that the design protects public health and safety. If the U.S. Nuclear Regulatory Commission (NRC) staff identifies information that is needed to support a finding, NuScale submits that information on the application docket.

II.

REGULATORY AUDIT BASIS In Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(h), the Office of the Federal Register approved for incorporation by reference into 10 CFR 50.55a the 1991 version of IEEE Std. 603-1991, including the correction sheet dated January 30, 1995.

III.

REGULATORY AUDIT SCOPE The audit covers Supplement 1 to TR-1015-18653-P-A,"Design of the Highly Integrated Protection System Platform," TR-147121, Revision 0, (ML25056A296).

IV.

INFORMATION AND OTHER MATERIAL NECCSSARY FOR THE REGULATORY AUDIT NuScale should be prepared to provide documents, reports, calculations, computer code verification, and other material, as applicable, supporting the analyses documented in the Supplement 1 to TR-1015-18653-P-A,"Design of the Highly Integrated Protection System Platform," TR-147121, Revision 0. The NRC staff may request that NuScale make these additional materials available in the eRR and/or as a computer disc to be submitted on the docket.

V SPECIAL REQUESTS NuScale and NRC have discussed and agreed upon the following audit logistics:

NuScale creates Certrec eRR portal for document viewing.

o NuScale to set up access for NRC participants once the staff emails are communicated.

The request for additional information (RAI) process will be used when:

o completion of the response will extend past the audit close date o requested by NuScale or NRC NRC will send formal RAI to NuScale via email RAI clock starts on the day the question is sent NuScale will respond to RAI questions:

o Does the RAI contain proprietary, export control, or security related information?

o Is clarification needed?

o Is the 30-day response timeline achievable?

NuScale responses to RAIs will be submitted electronically to the NRC docket.

VI DELIVERABLES The NRC audit team is expected to be composed of the above-listed project manager and technical reviewers. The NRC staff acknowledges the proprietary nature of the information requested and will handle it in accordance with agency policies and procedures throughout the audit. While the NRC staff will take notes, the NRC staff will not remove hard copies or electronic files from the audit site(s).

The audit started on July 22, 2025, and will end on December 31, 2025.

The NRC will inform NuScale of emerging information needs as well as documents that can be removed from eRR.

The NRC will generate an audit report at the completion of the audit. The audit report will include a link for all docketed materials requested by the staff during the audit.

The NRC point of contact for communicating questions or comments related to the conduct of the audit is Mr. Getachew Tesfaye, who can be reached at 301-415-8013 or via email at Getachew.tesfaye@nrc.gov.