FOF - Request for Schedule Date Change
ML25066A148
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 03/07/2025
From: Oesterle R
FirstEnergy Nuclear Operating Co, Vistra Corp
To: Joshua Berry
Office of Nuclear Security and Incident Response
References
Download: ML25066A148 (1)


Text

From:

Oesterle, Robert To:

Joshua Berry

Subject:

[External_Sender] PY and BV FOF - request for schedule date change Date:

Friday, March 7, 2025 6:36:58 AM Attachments:

image001.png VISTRA requests the schedule weeks for the Beaver Valley and Perry Nuclear Power Plant Force on Force Inspection to be revised to separate the inherent impacts of the Inspection activities from the refueling outage mobilization/de-mobilization activities at the respective site based on current schedule. The requested change is effectively a swap in locations; the change is summarized as follows:

Beaver Valley New Dates:

Planning Week: May 19-23, 2025 Exercise Week: June 9-13, 2025

Perry New Dates:

Planning Week: August 4-8, 2025 Exercise Week: August 25-29, 2025

Please contact me should any additional information be required.

Thank you,

Rob

Robert W. Oesterle Manager, Regulatory Compliance Mobile: 419-607-0948 Office: 419-321-7462