November 2004 Monthly Operating Report for Limerick Generating Station, Units 1 and 2
ML043500517
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 12/15/2004
From: Bryan Hanson
Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002
Download: ML043500517 (3)


Text

T.S. 6.9.1.6 December 15, 2004 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353

Subject:

Monthly Operating Report for November 2004 Attached is the monthly operating report for Limerick Units 1 and 2 for the month of November 2004 forwarded pursuant to Technical Specification 6.9.1.6 and the guidance of NRC Generic Letter 97-02. The attached monthly operating report data has also been entered into the INPO Consolidated Database for the month of November 2004 for Units 1 and 2.

If you have any questions or require additional information, please do not hesitate to contact us.

Sincerely, Original signed by Edward Callan for Bryan C. Hanson Plant Manager-LGS Attachments cc:

S. Collins, Administrator, Region I, USNRC S. Hansell, LGS USNRC Senior Resident Inspector

Unit:

Limerick 1 Docket No:

50-352 Date:

12/15/04 Completed by: Greg Lee Telephone:

(610) 718-3707 A.

OPERATING DATA REPORT REPORTING PERIOD-November 2004 Design Electrical Rating (MWe-Net) 1191.00 Maximum Dependable Capacity (MWe-Net) 1134.00 Month Year to Date Cumulative Hours Reactor Critical (Hours) 720.0 7,645.17 146,211.64 Hours Generator On-Line (Hours) 720.0 7,601.38 144,182.58 Unit Reserve Shutdown Hours (Hours) 0.00 0.00 0.00 Net Electrical Energy (MWh) 842,244.00 8,663,961.00 150,490,250.00 B.

UNIT SHUTDOWN No.

Date (yymmdd)

Type Generator Off-line Duration (hrs)

Reason Method Corrective Actions/Comments None during November 2004

SUMMARY

Unit 1 began the month of November 2004 at 99.3% of rated thermal power (RTP).

There were no power changes during the month of November 2004.

Unit 1 ended the month of November 2004 at 99.2% RTP.

Type Reason Method F-Forced A-Equipment Failure (Explain) 1-Manual S-Scheduled B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other(Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

C.

SAFETY/RELIEF VALVE OPERATION Date Valves Actuated No. & Type of Actuation Plant Condition Description of Event None During November 2004

Unit:

Limerick 2 Docket No:

50-353 Date:

12/15/04 Completed by: Greg Lee Telephone:

(610) 718-3707 A. OPERATING DATA REPORT REPORTING PERIOD-November 2004 Design Electrical Rating (MWe-Net) 1191.00 Maximum Dependable Capacity (MWe-Net) 1134.00 Month Year to Date Cumulative Hours Reactor Critical (Hours) 720.00 8,009.13 122,459.23 Hours Generator On-Line (Hours) 720.00 7,990.02 120,677.74 Unit Reserve Shutdown Hours (Hours) 0.00 0.00 0.00 Net Electrical Energy (MWh) 830,951.00 9,096,216.00 130,117,582.00 B. UNIT SHUTDOWN No.

Date (yymmdd)

Type Generator Off-line Duration (hrs)

Reason Method Corrective Actions/Comments None During November 2004

SUMMARY

Unit 2 began the month of November 2004 at 99.9% of rated thermal power (RTP).

On November 13th at 22:00 hours, reactor power was reduced from 99.9% to 90.0% RTP for rod pattern adjustment.

On November 14th at 02:00 hours, reactor power was restored to 99.7% RTP.

Unit 2 ended the month of November 2004 at 99.8% RTP.

Type Reason Method F-Forced A-Equipment Failure (Explain) 1-Manual S-Scheduled B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

C. SAFETY/RELIEF VALVE OPERATION Date Valves Actuated No. & Type of Actuation Plant Condition Description of Event None During November 2004