Amends 126 & 120 to Licenses DPR-31 & 41,incorporating License Conditions Which Require Implementation of Util Plan for Integrated Scheduling of Plant Mods
ML17347A625
Person / Time
Site: Turkey Point  
Issue date: 11/23/1987
From: Berkow H
Office of Nuclear Reactor Regulation
To:
Shared Package
ML17347A626 List:
References
NUDOCS 8712030004
Download: ML17347A625 (6)


Text

1

~p,q REOII, (4

Mp0~i i~

nO Vi 0

Cy

~ ~y/p 0

++**~

UNITEDSTATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 FLORIDA POWER AND LIGHT COMPANY DOCKET NO. 50"250 TURKEY POINT PLANT UNIT NO.

3 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 126 License No.

DPR-31 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Florida Power and Light Company (the licensee) dated December 19,

1986, as supplemented June 22, 1987 and November 16,
1987, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission'.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safetv of the public; and The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by adding a new license condition 3.K. to read as follows:

87i2030004 87ii23 PDR ADOCK 05000250 P

'PDR

3.K. Inte rated Schedule 1.

The Plan for Integrated Scheduling of Plant Modifications for Turkey Point Units 3

E 4 (the Plan),

submitted on December 19, 1986, is approved.

a.

The Plan shall be followed by the licensee from and after the effective date of this amendment.

b.

Changes to dates for completion of items identified in Schedule 8 do not require a license amendment.

Dates specified in Schedule A shall be changed only in accordance with applicable NRC procedures.

2.

This license condition shall be effective until December 31, 1990, subject to renewal upon application by the licensee.

3.

This license amendment is effective as oF the date of issuance and shall be implemented within 60 days.

FOR THE NUCLEAR REGULATORY COMMISSION Herbert N. Berkow, Dir tor Project Directorate II 2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation Date of Issuance:

November 23, 1987

~S eaeI (4

tp0 Op

~c C

O IA rp 0

Co Cy JP ++*++

UNITED STATES NUCLEAR REGULATORY COMMISSION'ASHINGTON, D. C. 20555 FLORIDA POWER AND LIGHT COMPANY DOCKET NO. 50-251 TURKEY POINT PLANT UNIT NO. 4 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 120 License No.

DPR-41 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Florida Power and Light Company (the licensee) dated December 19,

1986, as supplemented June 22, 1987 and November 16, 1987, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the actfvfties authorized by this amendment can be conducted without endangering the health and safety of the public, and (fi) that such activities will be conducted in compliance with the Commfssfon's regulations; D,

The issuance of this amendment will not be inimical to the common defense and security o} to the health and safety of the public; and E.

The issuance of this amendment is fn accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license fs amended by adding a new license condition 3.K. to read as follows:

3.K. Inte rated Schedule 1.

The Plan for Integrated Scheduling of Plant Modifications for Turkey Point Units 3 8 4 (the Plan),

submitted on December 19, 1986, is approved.

a.

The Plan shall be followed by the licensee from and after the effective date of this amendment.

b.

Changes to dates for completion of items identified in Schedule B do not require a license amendment.

Dates specified in Schedule A shall be changed only in accordance with applicable NRC procedures.

2.

This license condition shall be effective until December 31, 1990, subject to renewal upon application by the licensee.

3.

This license amendment is effective as of the date of issuance and shall be implemented within 60 days.

FOR THE NUCLEAR REGULATORY COMMISSION f~

Herbert N. Berkow, Dir tor Project Directorate I -2 Division of Reactor Projects-I/II Office of Nuclear Reactor Regulation Date of Issuance:

November 23, 1987

C t