Forwards Final SALP 10 Rept 50-255/91-01 for Sept 1989 - Dec 1990,per 910322 Meeting Re Initial SALP Rept . No Changes to Initial SALP Necessary & as Such Considered to Be Final SALP Rept
ML18057A872
Person / Time
Site: Palisades Entergy icon.png
Issue date: 04/23/1991
From: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Slade G
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18057A873 List:
References
NUDOCS 9105020022
Download: ML18057A872 (4)


See also: IR 05000255/1991001

Text

~.

  • I\\_,

Docket No. 50-255

Consumers Power Company *

ATTN:

Gerald 8. Slade

General Manager

Palisades Nuclear Generating Plant

27780 Blue Star Memorial Highway

Covert, MI

49043

Gentlemen:

This refers to the NRC 1 s Systematic Assessment of Licensee Performance (SALP) 10

Report for the Palisades Nuclear Plant, and our meeting of March 22, 1991,

which discussed in detail the contents of the report and your written comments

dated April 16, 1991, relat1ve to the report.

Based on our in-depth discussions during the meeting and our thorough review

and evaluation of your letter of response, we have reached the conclusion that

no changes to the Ini.tial SALP Report are necessary.

As such, the Initial

SALP Report dated March 7, 1991 is considered to be the Final SALP Report .

We note your concern with the category 2, declining rating in the emergency

preparedness area.

This concern was discussed in your letter and at the SALP

meeting.

I have reconsidered this rating and have decided it is proper.

The

training, staff qualifications, Operations Support Center command and control

and untimely activation of the EDF concerns discussed in the SALP report

certainly establish that your performance has declined from the previous

category 1 rating.

It was the opinion of the,SALP Board that your performance in this area was

declining primarily due to lack of management involvement, and that your

performance would have continued to decline without NRC intervention.

Your

corrective actions, although they appeared adequate, had riot been tested in a

dri 11 or exercise by the end of the SALP period.

Based on your performance as -

discussed above and in the SALP report, I believe the SALP Board rating is

appropriate.

We will be pleased to discuss the matter further as you

requested-.

In accordance with Section 2.790 of the NRC's

11 Rules of Practice,

11 Part 2,

Title 10, Code of Federal Regulations, a copy of this letter with the

referenced enclosures, will be placed in the NRC's Public Document Room .

APR 2 3 1S81 *

Consumers Power Company

2

No reply to this letter is required; however, should you have questions

regarding the Final SALP Report, please let us know ~nd we will be pleased to

discuss them with you.

Sincerely,

A. Bert Davis

Regional Administrator

Enclosures: *

1.

Final SALP 10 Report

No. 50-255/91001

(Meeting Summary)

2.

Licensee Response Ltr,

dtd April 16, 1991

Distribution

cc w/enclosures:

David P. Hoffman, Vice President

Nuclear Operations

Mr. P. M. Donnelly, Safety and

Licensing Director

DCD/DCB (RIDS)~

OC/LFDCB

Resident Inspector, RIII

James R. Padgett, Michigan Public

Service Commission

Michigan Department of

Public Health

J. H. Sniezek, DEDR

T. E. Murley, NRR

K. M. Carr, Chairman

K. C. Rogers, Commissioner

J. R. Curtiss, Commissioner

F. J. Remick, Commissioner

L. R. Plisco, NRR

8.- E. Holian, NRR Project Manager

Distribution Continued

69_

@

RIII

RIIl

RIII

~I

~

~~n

~ '\\,\\O*\\\\

.&~c~i bi nz/da

J

nse~" as e

RI I I

'1'"\\.\\

.

~ "-'"t.\\I\\\\

RIIC!f

RIII

"~~'l\\ us :;:

.0

ptl~M11'

Davis

7,'liqt*

'-f) 2-'1

Y~

i/v~

RIII'2 c

Riii *~

zt r~

Clayton

Green *an

4/'i..l/p I

111~!11

RIII

.~~~.

APR 2 3 '1891

Consumers Power Company

3

L. B. Marsh, ~RR Direct6r, Project Directorate III-1

J. Lieberman, Director, Office of

Enforcement

E. w. 'Brach, NRR

M. L. Dapas, NRR

C. F. Holden, NRR

R. L. Wharton, .NRR

RI II PRR

State Li~ison Officer, State

of Michigan

INPO

L. R. Greger, RIII

M. J. Pearson, RIII

. L.

~- Cox, RIII

.

TSS, RIII

Riil Files

Consumers Power Company

3

Distribution

L. B. Marsh, NRR Director, Project Directorate III-1.

J. Lieberman, Director, Office of

Enforcement

E. W. Brach, NRR

M. L. Dapas, NRR

C. F. Holden, NRR

R. L. Wharton, NRR

RIII PRR

-

State Liaison Officer; State

of Michigan

INPO

L. R. Greger, RIII

M. J. Pearson, RIII

L. L. Cox, RIII

TSS, RIII

RI! I Files