TXX-6460, Final Deficiency Rept CP-85-54 Re Seismic Qualification of HVAC Supports.Initally Reported on 860926.Project Organization & Responsibilities for HVAC Activities Realigned & Field Verification Effort Expanded

From kanterella
Revision as of 02:56, 4 December 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Final Deficiency Rept CP-85-54 Re Seismic Qualification of HVAC Supports.Initally Reported on 860926.Project Organization & Responsibilities for HVAC Activities Realigned & Field Verification Effort Expanded
ML20214H984
Person / Time
Site: Comanche Peak  
Issue date: 05/22/1987
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-85-54, TXX-6460, NUDOCS 8705270576
Download: ML20214H984 (2)


Text

'

Log # TXX-6460 File # 10110 903.7

=

=

Ref: # 10CFR50.55(e) 1UELECTRIC "j,'l*,"j@,",,"'

May 22, 1987 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 SEISMIC QUALIFICATION OF HVAC SUPPORTS SDAR: CP-85-54 (FINAL REPORT)

Gentlemen:

On September 26, 1986, we notified you by letter TXX-5043 that a deficiency involving discrepancies in supplier provided HVAC support documents was reportable under the provisions of 10CFR50.55(e). Our last interim report logged was TXX-6106 dated November 20, 1986.

This is a final report to status the following corrective measures:

1.

The Project organization and responsibilities for Units 1 and 2 HVAC activities have been realigned.

Engineering and QC activities previously performed by Bahnson have been assumed by Ebasco and TV Electric, respectively.

2.

The field verification effort has been expanded to encompass all Unit 1 and 2 Seismic Category I duct and duct supports.

Ebasco's progress to date, for this effort, is as follows:

O Collection of existing documents is complete for Units 1 and 2.

O The as-built inspection of duct supports in Unit 1 and Common has been completed with the exception of areas which will be verified.

The as-built inspection of ductwork in Unit 1 and Common is currently in progress and is being performed in accordance with TU Electric Procedure CPE-FVM-CS-029, " Procedure for Seismic HVAC Duct and Duct Hangers As-Built Verification in Unit I and Common Areas."

3.

Engineering evaluations are being performed to ensure compliance with FSAR i

commitments.

4.

Construction re-work was initiated on May 4, 1987, as deemed necessary by the engineering evaluations of field verified information, to ensure compliance with FSAR criteria for the affected supports.

870527057b 870522 0

{DR ADOCK 05000445 h

PDR 1

400 North Olise Street L B. 81 Dallas, Texas 75201 8 D

TXX-6460 May 22, 1987 Page 2 of 2 5.

QC inspections of the Seismic Category I duct and duct supports will be performed after an engineering review of the construction re-work.

6.

An as-built and design verification effort, and QC inspection will be performed on Seismic Category I duct and duct supports in Unit 2.

This program will be performed in the same manner as the one utilized in Unit 1.

Unit I activities are scheduled for completion by March,1988.

Unit 2 activities are scheduled for completion in July,1988.

4 Very truly yours, W. G. Counsil RWH/gj c - Mr. R. D. Martin - Region IV CPSES Resident Inspector - 3 copies l