TXX-6663, Interim Deficiency Rept CP-87-27 Re Galvanic Corrosion in Component Cooling Water & Svc Water Sys.Initially Reported on 870629.Evaluation of Issue Continuing.Next Rept to Be Submitted by 871124

From kanterella
Revision as of 07:20, 2 December 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Interim Deficiency Rept CP-87-27 Re Galvanic Corrosion in Component Cooling Water & Svc Water Sys.Initially Reported on 870629.Evaluation of Issue Continuing.Next Rept to Be Submitted by 871124
ML20237H226
Person / Time
Site: Comanche Peak  
Issue date: 08/20/1987
From: Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-87-27, TXX-6663, NUDOCS 8708240398
Download: ML20237H226 (1)


Text

. - _ _ _

j M==

Log # TXX-6663 File # 10110 E

=

909.2-

~~

~1UELECTRIC William G. Omnsil ano,,, vw anue,,'

August 20, 1987 V. S. Nuclear Regulatory Commission Attn: Document Control Desk

. Washington, D. C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET N05.'50-445 AND 50-446 GALVANIC CORR 0SION IN CCW AND SW SYSTEMS SDAR:

CP-87-27 (INTERIM REPORT)

Gentlemen:

On June 29, 1987, we verbally notified your Mr. Shannon Phillips of a potentially reportable item involving galvanic corrosion in Component' Cooling Water (CCW) and Service Water (SW) systems.

This is an interim report under the provisions of 10CFR50.55(e). Our last interim report was logged as TXX-6583, dated July 28, 1987.

Our evaluation of this issue is continuing. We expect to submit our next report by November 24, 1987.

Very truly yours, W. G. Counsil

)

By:

[

G. S. Keeley _

Manager, Nuclear i ensing MCP/gj c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) 8708240398 B70020 PDR ADDCK 0500 5

O S

Y &

400 North Olive Street LB 81 Dallas, Texas 75201 l