Supplemental Deficiency Rept CP-86-07 Re Svc Water Sys Leakage.Initially Reported on 860411.Design Mods Being Implemented on Train a to Be Completed by 861107. Evaluation of Corrective Action & Rept Scheduled for 870130
ML20210R129
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/19/1986
From: Counsil G, Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CP-86-07, CP-86-7, TXX-5026, NUDOCS 8610070128
Download: ML20210R129 (1)


Text

Log # TXX-5026 File # 10110 909.2 TEXAS UTILITIES GENERATING COMPANY SKYWAY TOWER . 400 NORTH OLIVE STREET. L.H. N B . DAELAN. TEXAS 78201 September 19, 1986 022N?2?L% $ $ b 5 b.

Mr. Eric H. Johnson, Director SEP 2 5 i986 Division of Reactor Safety and Projects y U.S. Nuclear Regulatory Commission -

611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET N0S. 50-445 AND 50-446 SERVICE WATER SYSTEM LEAKAGE SDAR: CP-86-07 (SUPPLEMENTAL REPORT)

Dear Mr. Johnson:

On April 11, 1986 we verbally notified you of a reportable item involving weld failure and coating degradation in the Service Water System (see TXX-4762).

This is a follow-up supplemental report on a reportable item under the provisions of 10CFR50.55(e).

Our inspections of the Train "A" Service Water Piping have been completed revealing no generic failures of the Plasite coatings. Several pitted areas were identified for which repair was warranted. Other areas containing minor defects, not warranting repair, were identified and will be used as baseline data fcr future inspections.

Several design modifications are currently being implemented on Train "A" which are currently scheduled for completion by November 7,1986. Train "A" will be held out of service until these actions are complete. The inspection of Train "B" will not be started until Train "A" is returned to service. This inspection will require two months to complete. Therefore, corrective measures which may be required for Train "B" are scheduled for completion by January 15, 1987.

l We anticipate completing our evaluation of the corrective action and submitting our next report by January 30, 1987.

l Very truly yours, f

W. G. Co sil

/

8610370128 060919 B:

Y PDR ADOCK 03000445 G. S. Keele p /-

N Manager,Licensi(g' l

JCH/amb q

\ Q i

Y an,v,s,osorre m ur,ur,ese, m mccm,,4~r h-Id%