Responds to NRC Re Noncompliance Noted in Insp Repts 50-456/84-13 & 50-457/84-13.Corrective Actions: Importance of Including Required Statements,Per 10CFR21,on Procurement Orders Reemphasized
ML20093M360
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 09/21/1984
From: Farrar D
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20093M355 List:
References
9213N, NUDOCS 8410220087
Download: ML20093M360 (5)


Text

..

u' '

=.

j t Commonwealth Edison s ) one First National Plaza. Chicago, III.nois kO j Chicago, Illinois 60690

-\

~7 Address Reply to: Post Office Box 767 September 21, 1984

'Mr. James G. Keppler Regional Administrator U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen-Ellyn, Il 60137

- Sub jec t: Braidwood Station Units 1 and 2 Response to Inspection Report Nos.

50-456/84-13 and 50-457/84-13 NRC Docket Nos. 50-456 and 50-457 Reference (a): R. F. Warnick letter to Cordell Reed dated August 7, 1984.

Dea'r Mr. Keppler:

This letter is provided in response to the inspection conducted by Messrs. L. G. McGregor and R. D. Schulz on June 5 through July 6, 1984 of. activities at Braidwood Station. Reference (a) indicated that certain activities appeared to be in noncompliance with NRC requirements. The Commonwealth Edison Company response to the Notice of Violation as appended to Reference (a) is provided in the enclosure.

. Our delay in submittal of this thirty-day report until September 21, 1984, was discussed with Mr. R. F. Warnick of your office.on September 5, 1984.

Very uly your ,

De nis L. Farrar Director of Nuclear Licensing Enclosure cc: NRC Resident Inspector -

Braidwood gg,p 'l 4 8410220007 841017 PDR ADOCK 05000456 G PDR t

req -

') . :. j '

ENCLOSURE-COMMONWEALTH EDISON COMPANY RESPONSE T0' INSPECTION REPORT-50-456/84-13-AND 50-457/84-13 456-457/84-13-08

. ITEM OF' NONCOMPLIANCE

~

lf. :10 CFR-21.31 states,L"Each individual, corporation, partnership or other entity-- subject to the regulations in this part shall

^

. assure that each procurement document for a facility, or a basic component issued by him, her or it on or after January 6, 1978 specifies,--when. applicable, that the provisions of 10 CFR Part 21 apply."

Contrary: to1the above, procurement documents, numbers 252162,

-254434, 259782,-262155, 265347, and 270934 did not specify that

'the provisions of 10 CFR Part 21 apply for heat shrink tubing 1 required to be in compliance with IEEE 383-1974 for aging, Sr radiation,'and LOCA environments.

RESPONSE:.

a-

. Commonwealth Edison Company agrees that the procurement documents identified were not_ stamped with the appropriate stamp. However, documentation received with the subject heat shrink tubing did

contain 10 CFR.Part 21 reporting re_quirements.

~ CORRECTIVE ACTION TAKEN AND RESULTS ACHIEVED:

All-procurement 1 documents for_the vendor in question have been reviewed for the applicability of 10 CFR Part 21. o Change orders have been issued to the appropriate procurement documents to_ include the 10.CFR Part 21 provisions.

CORRECTIVE ACTION-TAKEN TO AVOID FURTHER NONCOMPLIANCE:

The importance of including the required statements on

. procurement orders has been re-emphasized to review personnel.

Also, Quality Assurance Supervisory Personnel are providing an additional-review of procurement orders.

.m ? +-tym y- m p rm 7wy+8--*T'PT=v rF- errrPWe n- t y-F -'

I DATE 0F FULL COMPLIANCE:

Full compliance has been' achieved.

ll - . _ - - . . . - - __

m de i .,.,

COMMONWEALTH EDISON COMPANY t

RESPONSE TO INSPECTION REPORT 50-456/84-13 AND 50-457/84-13

'456-457/84-13-09 ITEM OF NONCOMPLIANCE:

2. . 10 CFR 50, Appendix.8, Criterion IX, states in part, " Measures shall be established to assure that special processes, including welding... are controlled and accomplished...using qualified procedures in accordance with applicable codes, standards, specifications, criteria, and other special requirements."

Sargent and Lundy drawing 20E-0-3251, Revision AC and L. K.

Comstock. Procedure 4.3.3 dated January 29, 1982, require the use of E60 series weld rod for cable pan welds.

Contrary to the above, nine L. K. Comstock filler metal withdrawal. authorization forms documented the release of E7018 weld rod'for cable pan welds between May 25, 1932, and July 28, 1982.

RESPONSE

Commonwealth Edison agrees that a procedure violation occurred.

However, our review indicates that the welds made with either E60 or E70 series weldrod are technically acceptable and will not result in any hardware problems in the field for the following reasons:

1. The heat numbers identified are acceptable heat numbers traceable to valid certification papers.
2. The welds made utilizing either of these electrodes meets or exceeds the strength requirements specified by AWS Dl.1-1975.
3. The welders making these welds were qualified to use either filler metal.
4. Welding always required a 100% visual inspection and any unacceptable welds would have been identified.

CORRECTIVE ACTION TAKEN AND RESULTS ACHIEVED:

LKC NCR #3275 has been issued to identify and disposition the procedure violation.

i-

y_._ ..

  • ~~

...y .--._

_4_

' CORRECTIVE ACTION TAKEN TO AVOIO FURTHER NONCOMPLIANCE:

L. K. Comstock Procedure 4.3.10, Storage, Issue and Control of Welding Material, has been revised lto amplify and clarify the

. control of weld filler metal. Personnel responsible for weld rod control.have.been trained in this procedure revision.

DATE OF FULL COMPLIANCE:

Disposition of NCR #3275 is expected by November 16, 1984.

9213N A_,.____._______________