Forwards Revised Background Info for AP600 Emergency Response Guidelines,Including Rev 1A to AE-1,Rev 1A to AES-1.1,Rev 1A to AES-1.2 & Rev 1A to AE-2
ML20117J098
Person / Time
Site: 05200003
Issue date: 08/30/1996
From: Mcintyre B
WESTINGHOUSE ELECTRIC COMPANY, DIV OF CBS CORP.
To: Quay T
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20117J100 List:
References
NSD-NRC-96-4805, NUDOCS 9609100162
Download: ML20117J098 (2)


Text

'

x e  :

Westinghouse Energy Systems Box 355 Electric Corporation Pmsburgh Pennsylvania 15230-0355 NSD-NRC-96-4805 DCP/NRC0589 Docket No.: STN-52-003 August 30,1996 Document Control Desk U.S. Nuclear Regulatory Commission l Washington, D.C. 20555 l ATTENTION: T.R. QUAY l

SUBJECT:

SUBMITTAL OF AP600 AT-POWER ERG BACKGROUND DOCUMENTS

References:

1. Letter DCP/NRC0376 from N. J. Liparulo to T. R. Quay, dated 8/9/95.

l

2. Letter DCP/NRC0574, from B. A. McIntyre To T. R. Quay, dated

! 8/8/96.

Dear Mr. Quay:

! Please find attached the following four " Background Information for AP600 Emergency Response Guidelines" documents, revised to include a Section 2.0

Description:

AE-1, Rev. l A, 8/96 AP600 Loss of Reactor or Secondary Coolant AES-1.1, Rev. l A, 8/96 AP600 Passive Safety Systems Termination

, AES-1.2, Rev. l A, 8/96 AP600 Post LOCA Cooldown and Depressurization -

AE-2, Rev. l A, 8/96 AP600 Faulted Steam Generator Isolation To complete Westinghouse activities related to the AP600 ERGS and Background Documents, the at-power ERGS will be updated to reflect the AP600 as described in the SSAR, including design changes incorporated since issuance of Reference 1 as well as PRA insights. Upon completion of the at-power ERGS revision, the at-power ERGS and Background Information will be issued as Revision

2. You are requested to review the attached documents assuming minimal technical changes will result from revision of the at-power ERGS.

\

l l

l t

- 06005s 40W 9609100162 960830 PDR ADOCK 05200003 l

F PDR l

l t

m NSD-NRC-96-4805 l l_ DCP/NRC0589 August 30,1996 While this submittal does not affect the status of any DSER/Open Item Tracking System open items, completion of the at-power ERGS revision will close the following DSER/OITS open items. i l

l DSER OITS l 13.3.5 1222 18.9.3-3 1365 18.9.3-4 1366 18.9.3-6 1368 18.9.3-7 1369 18.9.3-8 1370 18.9.3-9 1371 ,

18, 2043 13.5 2304 l 13.5 2305 l

Please contact Robin K. Nydes on (412) 374-4125 if you have any questions regarding this transmittal ,

or the AP600 Emergency Response Guidelines.

h .:v Brian A. McIntyre, Manager L Advanced Plant Safety and Licensing

/nja Enclosures l

l cc: D. Jackson, NRC (llE)

J. Bongarra, NRC (IE)

G. Galletti, NRC (IE)

T. Collins, NRC (IE)

A. Levin, NRC (IE)

W. Iluffman, NRC (IE)

11. Li, NRC (IE)

N. Liparulo, Westinghouse (w/o Enclosures) i l 2WIA l I l

l