July 21, 2020, Summary of Public Meeting with Nuclear Energy Institute Regarding 10 CFR 50.69 License Amendment Requests
ML20217L361
Person / Time
Issue date: 08/12/2020
From: Geoffrey Miller
Plant Licensing Branch II
To: Markley M
Plant Licensing Branch II
Miller G
References
Download: ML20217L361 (4)


Text

August 12. 2020 MEMORANDUM TO: Michael T. Markley, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: G. Edward Miller, Project Manager /RA/

Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF JULY 21, 2020, PUBLIC MEETING WITH NUCLEAR ENERGY INSTITUTE REGARDING 10 CFR 50.69 LICENSE AMENDMENT REQUESTS On July 21, 2020, a Category 2 public meeting1 was held between representatives of the U.S. Nuclear Regulatory Commission (NRC), Nuclear Energy Institute (NEI), Electric Power Research Institute (EPRI), and licensees. The purpose of this meeting was to discuss NRC staffs information needs with regard to treatment of seismic risk when reviewing license amendment requests (LARs) to adopt a risk-informed program for categorization and treatment of structures, systems, and components (SSCs) for nuclear power reactors in accordance with Section 50.69, Risk-informed categorization and treatment of structures, systems, and components for nuclear power reactors, of Title 10 of the Code of Federal Regulations (10 CFR 50.69).

Specifically, this meeting focused on NRC staffs information needs when licensees for sites with a relatively low seismic hazard propose to use an alternative approach to consider seismic risk for categorization of SSCs during implementation of 10 CFR 50.69 and cite EPRI 30020129882 to support the proposed approach.

During the meeting, the NRC staff discussed the purpose of the information needed by the staff to make a positive regulatory finding in these reviews. The NRC staff and NEI discussed alternatives to the quantification of seismic risk for sites with a relatively low seismic hazard.

During the discussion, the NRC staff expressed an openness to consider semi-quantitative and qualitative justifications by licensees to demonstrate a low seismic risk in comparison with the total plant risk. The NRC staff discussed potential options for such justifications and provided feedback on comments from NEI and EPRI.

1 The meeting notice is available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML20189A538.

2 The EPRI report is available by searching the report number at www.epri.com.

M. Markley The NRC staff plans future meetings with NEI and to schedule a pre-submittal public meeting for focused feedback on the semi-quantitative or qualitative justifications proposed in an LAR.

No regulatory decisions were made during the meeting. Following the discussion, an opportunity was afforded to any other participants who wished to ask questions or make comments. No questions or comments were received.

The list of attendees is enclosed to this summary.

Enclosure:

List of Attendees

LIST OF ATTENDEES

SUMMARY

OF JULY 21, 2020 PUBLIC MEETING WITH NUCLEAR ENERGY INSTITUTE REGARDING 10 CFR 50.69 LICENSE AMENDMENT REQUESTS Name Organization Ed Miller NRC/NRR Greg Bowman NRC/NRR Michael Marshall NRC/NRR Mihaela Biro NRC/NRR Shilp Vasavada NRC/NRR John Richards EPRI Victoroia Anderson NEI John Conly Certrec Timothy Sande Enercon Rob Burg EPM Shannon Refferty-Czincila Exelon Luke McSweeney Nuscale Mark Brossart Xcel Energy Jana Bergman Curtiss-Wright Sunwoo Park NRC/NRR John Schrage Entergy Owen Scott SNC Stephen Flickinger Exelon Phil Tarpinian Exelon Richard Rolland Westinghouse Enclosure

ML20217L361 *via e-mail OFFICE NRR/DORL/LPL2-1/PM NRR/DORL/LPL2-1/LA NRR/DRA/APLC/BC NRR/DORL/LPL2-1/BC NAME GEMiller* KGoldstein* SRosenberg* MMarkley*

DATE 08/12/2020 08/12/2020 08/5/2020 08/12/2020