2 to Procedure Work Plan 1903.065, Emergency Response Facility Technical Support Center (Tsc)
ML20141C542
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 06/17/1997
From:
ENTERGY OPERATIONS, INC.
To:
References
1903.065, NUDOCS 9706250286
Download: ML20141C542 (5)


Text

_ _ . _ . . . _ .____ _ --_._ ._ _ _ _ . _ . _ _ _ _ _ . - - _ . _ . _ _ _ _ _

j l .

.. ENTERGY OPERATIONS INCORPORATED 4

ARKANSAS NUCLEAR ONE PROC / WORK PLAN NO. REV.

TITLE: EMERGENCY RESPONSE FACILITY TECHNICAL l' SUPPORT CENTER (TSC) 1903.065 12 I

EXP.DATE SAFETY-RELATED l i

2 N/A SYES []NO

" Da  !

PAOe , Og 4 l

CONTROLLED COPY # )g 93- @NO PAGE CHO PAGE CHG PAGE CHG PAGE CHG Self Check.

37 gc., 33 gc.,

1 19

' 38 56 l 2 20 i

3 PC-1 21 -

to 39 57 j

) 40 58 Th.m k-

~

4 22

~ PC-2 41 59 5 23 Ck 42 60 6 24 PC-1 43 61 7 25 44 8 26 i

45 9 27

.. eCause Nobody's perfe TIME 46 PC-1 10 28 VERIFIED BY DATE 47 11 29 48 12 30 PC 10 A 49

. 13 31 50 PC-1 14 32 51 PC-1 15 33 52 16 34 35 e C 17 ggW)llll!ElBil h9g3 i pj 18 36 PC-1 .

~

I V

FORM TITLE:

h NO. REV.

LIST OF AFFECTED PAGL.s idt0.006A 45

[ 9706250286 970617 '

PDR ADOCK 05000313 F PPR s

, . \

j .

CNTERGY OPERATIONS INCORPORATED l

- ARKANSAS NUCLEAR ONE l 1

l -

TITLE: EMERGENCY RESPONSE FACILITY TECHNICAL PROC /WORKPLAN NO. REV. CHG.

! SUPPORT CENTER (TSC) 1903.065 12 PC-2 )

TEMPORARY CHANGE O PERMANENT AFFECTED UNIT SATETY-RELATED PAGE 1 OF 2 RA ON CHANGE @

. D @1 @2 EYES ONO 1 REASON FOR CHANGE:

{ Add checklist for " release source" and " plant release" DESCRIPTION OF CHANGE:

See attached l

r j Does This Change Require a 10CFR50.59 Review Per 1000.131, Step 6.3.27 @ YES O NO 4

DOES THIS CHANGE: Yes No Does this change alter or delete an existing Yes No Regula% CommRmed (If yes, coodnate Chango the Procedure purpose? O E with licensing before implemeriting.) O 2 l; Was MEF used as source document? Yes No j

Change the Procedure scope? O 2 E O Degrade the controls prescribed in O g STANDARD APPROVAL PROCESS the Admin. Procedures? (Required for Intent Changes or Changes Requiring a 50.59 Evaluation)

Reduce the level of nuclear safety? O g ORIGINATOR: EVIEW 3)  :

Degrade acceptance criteria? O 2 INDEPEND RE R DA :

If the response to any of the above is YES, or a 50.59 ENGINEERING'- # 9 #

DATE'-

Evaluation is required,.the change must be approved using the Standard Approval Pro:ess. M (/9 INTERIM APPROVAL PROCFSS QUALITY: DATE:

(Non-intent Changes and changes not requiring a 50.59 Evaluation that are stopping work in progress) Md j i

ORIGINATOR:(INCLUDES REVIEW AGAINST ATT.13) DATE: UNIT SURVEILLANCE COO INATOR: DATE. l Ub N4 SUPERVISOR APPROVAL:* DATE: S TlOf L DATE:

U ER:h 14% folIL,l91 SRO UNIT TWO;"

SRO UNIT ONE:"

a DATE:

DATE:

QUALITY ASSU%CE: uls OTHER SECTION LEADER (S): (Required for assignment of DATE:

responsibility outside of responsible section letder's section)

DATE:

  • 1f the change is not required to support work in /

progress, the Department Head must sign. y "If both units are affected by this change, then both SRO signatures are requised.

FINAL APPRGVAL(Required within 14 days of SRO signt;ture)

FI APPROVAL- DATE:

- 2 &ar~ a/n/e, FtEQUIRED EFFECTIVE DATE: PSC CHAIR /TEC DATE:

CAL RplEWER:'

4 /~7 IhWfY FORM TITLE. f0RKNO. REV.

CHANGE REQUEST / 1000.006C 45 PC-1

'(OCNA128509) 3(OCNA049312)

V ENTERGY OPERATIONS INCORPORATED m ARKANSAS NUCLEAR ONE

. PROC /WORKPLAN NO.

4 1903.065 TITLE: EMERGENCY RESPONSE FACILITY TECHNICAL SUPPORT REV. CHG. NO CENTER (TSC) 12 PC-2 PAGE 2 OF 2 CONTINUATION PAGE REASON AND DESCRIPTION OF CHANGE:

1. Added checks for " release source" and " plant release" to RP&RM and TSC Director update list page 59 of 61.
2. Added
  • outlet and return line" and removed "RMS" from step F Position Guide D.

4 (D

U i

1 O

v FORM NO. REV.

FORM TITLE:

1000.006C 45 CHANGE REQUEST

. PROC./ WORK PLAN No. PROCEDURE / WORK PLAN TITLE:

PAGE: 31 cf 61 REV: 12

  • 1903.065 EMERGENCY RESPONSE FACILITY CHANGE: PC-1,2

! TECHNICAL SUPPORT CENTER (TSC)

(

k\l / POSITION GUIDE D Page 3 of 4 RADIATION PROTECTION AND RADWASTE MANAGER

e. If the emergency event has dictated the use of reactor sump recire, then inform the H.P. Supervisor in the OSC to begin

((' monitoring the BWST and/or RWT outlet and return lines for di radioactivity.

f. Monitor radiation levels in the TSC/OSC and, using the guidelines on Attachment 1 of Procedure 1903.030, recommend any protective i

actions to the TSC Director,

g. Using Form 1903.065D, "TSC Director Status Update Guide", provide current updates to the TSC Director.
h. Using Procedure 1903.035, assess the need for the administration of Potassium Iodide and advise the TSC Director of any such recommendations,
i. Develop plans, procedures, and methods for keeping radiation exposure of recovery personnel as low as reasonably achievable (ALARA).
j. Coordinata with Dosimetry to ensure personnel TLDs are read and updated camputer listings are provided.
k. Ensure that the TSC RDhCS Operator monitors the status of any O, offsite radiological release.
1. Coordinate with the Health Physics staff to develop decontamination plans to support the recovery effort.

l m. Provide information and recommer dations to the TSC Director concerning future operations that could affect the plant or the l

environment.

n. Coordinate with collocated NRC of ficials and ensure that an open communications dialogue is maintained throughout the event.

l i o. Recommend equipment needed for use in accomplishing radwaste processing and monitoring activities,

p. Advise the Plant Modifications group as necessary concerning f

radwaste system additions and modifications. >

) q. Coordinate with the TSC Support Superintendent to request services that may be needed from offsite sources.

i l

1

$[ i j r. Coordinate with the TSC Support Superintendent to obtain f f Technical Assistants, as necessary.

\

! s. Monitor consultant activities whero outside assistance is being provided,

t. Ensure that documentation of all Radiation Protection activities is maintained using the ERO Chronological Logs, f* )

%./

1

.I

Pag 3 59 of 61 Page 2 of 3 fg

( )

's#' 5. Radiation Protection and Radwaste Manager Update Items (check as reviewed):

A. Radiological release data available.

ng 1. Is release source secure?

e 2. Is release from plant secure?

9( 3. Update TSCD if one or both have been secured.

B. Control Room \OSC\TSC habitability.

C. On-site radiological conditions affecting repair \ recovery effort.

D. Personnel exposure status, overexposure, contamination, etc.

E. Plans for keeping radiation exposure of repair \ recovery personnel as low as reasonably achievable.

F. Decontamination work necessary to support the recovery effort.

G. Radwaste processing and monitoring in progress.

H. Planned evolutions that could' affect the plant environment.

I. Problem areas needing resolution.

Notes:

6. TSC Support Superintendent Update Items (check as reviewed):

A. Status of technical and/or administrative support requested by the TSC, OSC, or Control Room.

B. Offsite communications (transmissions in progress) from the TSC.

C. Status of initial \ continuous accountability (if plant evacuation has occurred).

/

D. Security activities in support of emergency response.

\s_, E. Problem areas needing resolution.

Notes:

7. TSC Director Update Items (check as reviewed):

A. Current Emergency Class declared and the basis.

B. On-site protective measures in effect (or planned).

C. Overall accident mitigation objectives and their priorities.

D. Significant items from the EOF Director.

E. Significant items from the OSC Director.

F. Problem areas needing resolution.

,g G. Is release source secure?

61 H. Is release from plant secure?

Notes:

l i S/

FORM NO. REV.

FORM TITLE:

1903.065D 12, PC-2 TSC DIRECTOR STA1US UPDATE GUIDE