Submittal of 2019 Annual Radioactive Effluent Release Report, 2019 Annual Radiological Environmental Operating Report, and 2019 Annual Environmental Operating Report (Non-Radiological)
ML20125A184
Person / Time
Site: Beaver Valley
Issue date: 04/27/2020
From: Penfield R
Energy Harbor Nuclear Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML20125A185 List:
References
L-20-137
Download: ML20125A184 (4)


Text

- ~

lf6l energy Beaver Valley Power Station P.O. Box 4

  • ~ harbor Shippingport, PA 15077 Rod L. Penfield 724-682-5234 Site Vice President Fax: 724-643-8069 April 27, 2020 L-20-137 10 CFR 50.36a A TIN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Beaver Valley Power Station, Unit Nos. 1 and 2 Docket No. 50-334, License No. DPR-66 Docket No. 50-412, License No. NPF-73 Submittal of 2019 Annual Radioactive Effluent Release Report, 2019 Annual Radiological Environmental Operating Report, and 2019 Annual Environmental Operating Report (Non-Radiological)

Energy Harbor Nuclear Corp. hereby submits the Beaver Valley Power Station (BVPS) 2019 Annual Radioactive Effluent Release Report and the 2019 Annual Radiological Environmental Operating Report. These reports are provided in Enclosure A, in accordance with 10 CFR 50.36a and BVPS, Unit Nos. 1 and 2 Technical Specifications 5.5.1, 5.6.1, and 5.6.2.

Energy Harbor Nuclear Corp. also submits the 2019 Annual Environmental Operating Report (Non-Radiological) in accordance with the BVPS, Unit No. 2 Operating License, Appendix B - Environmental Protection Plan. This report is provided in Enclosure B.

There are no regulatory commitments contained in this submittal. If there are any questions or if additional information is required, please contact Mr. Eli Crosby, Manager - Radiation Protection/Chemistry, at (724) 682-7648.

i:Jl;;;:t*

Rod L. Penfiel Site Vice President

Beaver Valley Power Station Unit Nos. 1 and 2 L-20-137 Page2

Enclosures:

A. 2019 Annual Radioactive Effluent Release Report and 2019 Annual Radiological Environmental Operating Report B. 2019 Annual Environmental Operating Report (Non-Radiological) cc: NRG Region I Administrator NRG Resident Inspector NRR Project Manager Director BRP/DEP Site BRP/DEP Representative NRG Region I Health Physics Inspector

Enclosure A L-20-137 2019 Annual Radioactive Effluent Release Report and 2019 Annual Radiological Environmental Operating Report (Reports follow)

Enclosure B L-20-137 2019 Annual Environmental Operating Reporl (Non-Radiologicalj (Report follows)