MONTHYEARML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 ML23258A0212023-09-15015 September 2023 Form 5.1-1 Post-Examination Check Sheet (Clinton 2023) IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 ML23258A0162023-08-24024 August 2023 Form 2.1-1 Examination Prep Checklist (Clinton 2023) ML23258A0132023-08-24024 August 2023 Form 1.3-1 Examination Security Agreement (Clinton 2023) ML23258A0232023-08-0101 August 2023 Post-Exam Comments (None, Clinton 2023) ML23258A0222023-08-0101 August 2023 Licensee Post-Exam Submittal Letter (Clinton 2023) ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23258A0522023-07-0808 July 2023 Form 3.4-1 Events and Evolutions Checklist (Clinton 2023) ML23258A0502023-07-0808 July 2023 Form 2.3-1 Examination Outline Quality Checklist (Clinton 2023) ML23258A0942023-07-0606 July 2023 Form 2.3-4 Written Examination Quality Checklist (Clinton 2023) ML23258A0932023-07-0606 July 2023 Form 2.3-2 Operating Test Quality Checklist (Clinton 2023) RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23258A0952023-04-0606 April 2023 Licensee Exam Submittal Letter (Clinton 2023) ML23258A0562023-02-0606 February 2023 Licensee Outline Submission Letter (Clinton 2023) ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20223012022-04-13013 April 2022 NRC Initial License Examination Report 05000461/2022301 RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22157A3782022-01-28028 January 2022 ES-201-3 Pre Exam ML22153A5222022-01-28028 January 2022 ES-301-5 Clinton 2022 ML22157A3772022-01-28028 January 2022 ES-201-3 Post Exam Security Agreement ML22157A3752022-01-28028 January 2022 ES-201-1 Exam Prep Checklist ML22153A5202022-01-28028 January 2022 ES-201-2 Clinton ML22157A3822022-01-28028 January 2022 ES-403-1 Clinton 2022 ML22153A4722022-01-28028 January 2022 ES-301-6 ML22153A4682022-01-28028 January 2022 ES-301-4 U-604643, U-604643 ILT Exam Outline - Clinton 20222022-01-28028 January 2022 U-604643 ILT Exam Outline - Clinton 2022 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22153A5172022-01-28028 January 2022 ES-201-2 Clinton 2022 NRC Written Outline Only ML22153A4782022-01-28028 January 2022 ES-301-3 ML22153A4762022-01-28028 January 2022 U-604644 - CPS Submittal of Integrated Initial License Training Examination Materials - 75-Day ML22010A0992022-01-11011 January 2022 Operator Licensing Examination Approval ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21174A3062021-06-25025 June 2021 Confirmation of Initial License Examination IR 05000461/20213012021-04-29029 April 2021 NRC Initial License Examination Report 05000461/2021301 ML21144A3022021-04-13013 April 2021 Administered RO Admin JPM ML21144A3222021-04-13013 April 2021 ES-401-3 ML21144A3132021-04-13013 April 2021 Administered SRO Written Exam ML21144A2582021-04-13013 April 2021 Scenarios ML21144A2402021-04-13013 April 2021 LTR 75 Day Submittal ML21144A2372021-04-13013 April 2021 ES-301-4 ML21144A2442021-04-13013 April 2021 ES-401-6 ML21144A2232021-04-13013 April 2021 ES-201-1 ML21144A2382021-04-13013 April 2021 ES-301-6 ML21144A3232021-04-13013 April 2021 ES-D-1 ML21144A2152021-04-13013 April 2021 ES-401-4 ML21145A0332021-04-13013 April 2021 ES-201-2 Written Outline ML21144A2292021-04-13013 April 2021 ES-201-3 ML21144A2312021-04-13013 April 2021 Post Exam Submittal Letter 2024-06-27
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 ML23258A0212023-09-15015 September 2023 Form 5.1-1 Post-Examination Check Sheet (Clinton 2023) IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 ML23258A0162023-08-24024 August 2023 Form 2.1-1 Examination Prep Checklist (Clinton 2023) ML23258A0132023-08-24024 August 2023 Form 1.3-1 Examination Security Agreement (Clinton 2023) ML23258A0222023-08-0101 August 2023 Licensee Post-Exam Submittal Letter (Clinton 2023) ML23258A0232023-08-0101 August 2023 Post-Exam Comments (None, Clinton 2023) ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23258A0502023-07-0808 July 2023 Form 2.3-1 Examination Outline Quality Checklist (Clinton 2023) ML23258A0522023-07-0808 July 2023 Form 3.4-1 Events and Evolutions Checklist (Clinton 2023) ML23258A0932023-07-0606 July 2023 Form 2.3-2 Operating Test Quality Checklist (Clinton 2023) ML23258A0942023-07-0606 July 2023 Form 2.3-4 Written Examination Quality Checklist (Clinton 2023) RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23258A0952023-04-0606 April 2023 Licensee Exam Submittal Letter (Clinton 2023) ML23258A0562023-02-0606 February 2023 Licensee Outline Submission Letter (Clinton 2023) ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20223012022-04-13013 April 2022 NRC Initial License Examination Report 05000461/2022301 RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22153A4762022-01-28028 January 2022 U-604644 - CPS Submittal of Integrated Initial License Training Examination Materials - 75-Day ML22153A5202022-01-28028 January 2022 ES-201-2 Clinton U-604643, U-604643 ILT Exam Outline - Clinton 20222022-01-28028 January 2022 U-604643 ILT Exam Outline - Clinton 2022 ML22153A5172022-01-28028 January 2022 ES-201-2 Clinton 2022 NRC Written Outline Only ML22153A4722022-01-28028 January 2022 ES-301-6 ML22157A3772022-01-28028 January 2022 ES-201-3 Post Exam Security Agreement ML22153A4782022-01-28028 January 2022 ES-301-3 ML22157A3782022-01-28028 January 2022 ES-201-3 Pre Exam ML22153A5222022-01-28028 January 2022 ES-301-5 Clinton 2022 ML22157A3752022-01-28028 January 2022 ES-201-1 Exam Prep Checklist ML22157A3822022-01-28028 January 2022 ES-403-1 Clinton 2022 ML22153A4682022-01-28028 January 2022 ES-301-4 ML22010A0992022-01-11011 January 2022 Operator Licensing Examination Approval ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21174A3062021-06-25025 June 2021 Confirmation of Initial License Examination IR 05000461/20213012021-04-29029 April 2021 NRC Initial License Examination Report 05000461/2021301 ML21144A2232021-04-13013 April 2021 ES-201-1 ML21145A0402021-04-13013 April 2021 ES-301-5 ML21144A2292021-04-13013 April 2021 ES-201-3 ML21144A3022021-04-13013 April 2021 Administered RO Admin JPM ML21144A3232021-04-13013 April 2021 ES-D-1 ML21144A2302021-04-13013 April 2021 ES-403-1 ML21144A3222021-04-13013 April 2021 ES-401-3 ML21144A3202021-04-13013 April 2021 ES-401-1 ML21144A3192021-04-13013 April 2021 ES-301-2 ML21144A2642021-04-13013 April 2021 Sim JPM ML21144A3132021-04-13013 April 2021 Administered SRO Written Exam ML21144A3102021-04-13013 April 2021 Administered Sim JPM ML21144A3182021-04-13013 April 2021 ES-301-1 ML21145A0332021-04-13013 April 2021 ES-201-2 Written Outline 2024-06-27
[Table view] |
Text
CLINTON POWER STATION Job Performance Measure Scram Control Rod 32-13 By Venting The Control Rod Drive Hydraulics (CRDH)
Withdrawal Lines JPM Number: 4411.0801 Revision Number: 02 Date: 10/14/03 Developed By: T. Pickley 10/14/03 Instructor Date Validated By: B. Alvey 10/16/03 SME or Instructor Date Review By: P. K. Ryan 10/16/03 Operations Representative Date
JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.
Prior to JPM usage, revalidate JPM using steps 8 through 11 below.
________ 1. Task description and number, JPM description and number are identified.
________ 2. Knowledge and Abilities (K/A) references are included.
________ 3. Performance location specified. (in-plant, control room, or simulator)
________ 4. Initial setup conditions are identified.
________ 5. Initiating and terminating cues are properly identified.
________ 6. Task standards identified and verified by SME review.
________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
________ 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:
Procedure Rev. _____ Date _____________
________ 9. Pilot test the JPM:
- a. verify cues both verbal and visual are free of conflict, and
- b. ensure performance time is accurate.
________ 10. If the JPM cannot be performed as written with proper responses, then revise the JPM.
________ 11. When JPM is revalidated, SME or Instructor sign and date JPM cover page.
SME/Instructor Date SME/Instructor Date SME/Instructor Date Page 2 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02 Revision Record (Summary)
- 1. Revision 01, Converted JPM 45200J03 to new format
- 2. Revision 02, Changed control rod to 32-13 to reduce rad dose during JPM.
Page 3 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02 Operators Name: SSN:
Job
Title:
NLO RO SRO STA SRO Cert JPM Title/Number: 4411.0801, Scram Control Rod 32-13 By Venting The Control Rod Drive Hydraulics (CRDH) Withdrawal Lines Revision Number: 02 Task Number and
Title:
441108.07, Complete in plant actions to perform Venting CRD Withdrawal Lines method of Alternate Rod Insertion.
Suggested Testing Environment: Plant Actual Testing Environment: Simulator Plant Control Room Testing Method: Simulate Faulted: No Perform Alternate Path: No Time Critical: No Estimated Time to Complete: 30 _minutes Actual Time Used: minutes
References:
EVALUATION
SUMMARY
Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:
Evaluators Name: __________________________
Evaluators Signature: Date:
Page 4 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02 READ TO THE OPERATOR I will explain the initial conditions, which step(s) to simulate or discuss, and provide the initiating cues.
When you complete the task successfully, the objective of this Job Performance Measure will be satisfied.
SIMULATOR SET-UP CONDITIONS:
None TASK STANDARDS:
Control Rod 32-13 is fully inserted.
TOOLS, EQUIPMENT, OTHER SPECIAL REQUIREMENTS:
- 1. Tools are located in OSC. It is not required to take them to the containment.
- 2. CRDH vent valve wrench.
- 3. HP Hose with fitting.
- 4. Other wrenches in the kit.
PROCEDURAL/
REFERENCES:
CPS 4411.08, ALTERNATE CONTROL ROD INSERTION EVALUATOR INSTRUCTIONS:
Amplifying cues are provided within the JPM steps.
INITIAL CONDITIONS AND INITIATING CUE:
A reactor scram occurred but control rod 32-13 failed to insert. Individually scram control rod 32-13 by venting the CRDH withdrawal line in accordance with CPS No. 4411.08, ALTERNATE CONTROL ROD INSERTION. The containment is accessible, the reactor is shutdown and you have RP support.
START TIME:
Page 5 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02
==============================================================
PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM.
==============================================================
PERFORMANCE STEPS
- 1. Connect a hose from selected HCUs 1C11-1F102, CRD Withdraw Riser Vent Valve to below the Suppression Pool water level. (Valves located in HCU cat walk area)
Standard Examinee simulates removing the plug from the CRD riser vent valve.
Examinee should verify 1F102 shut before removing the plug.
CUE Comments The HCU for control rod 32-13 is located at 755' Containment Building, east side, on the outboard end of the second bank of HCU's near the stairway from 737' to 755'. If desired the evaluator may select a different HCU if access to 32-13 is limited. Examinee should explain the venting hose assembly process and routing of the hose. (Access to the vent valve is a catwalk.)
SAT UNSAT Comment Number
- 2. Shut 1C11-F102, HCU Withdraw Riser Valve. (First valve on right above HCU)
Standard Examinee simulates closing the valve for control rod 32-13.
CUE Comments SAT UNSAT Comment Number Page 6 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02
- 3. Open 1C11-1F102, CRD Withdraw Riser Vent Valve, and (MCR) Provide a continuous INSERT signal (if possible) to the selected CRD.
Standard Examinee simulates opening the riser vent valve for control rod 32-13.
CUE MCR is providing continuous insert signal. Control Rod 32-13 is fully inserted. Close 1C11-F102.
Comments SAT UNSAT Comment Number
- 4. Close HCU Withdraw Riser Vent Valve 1C11-1F102.
Standard Examinee simulates closing the valve for control rod 32-13.
CUE Comments SAT UNSAT Comment Number
- 2. Open HCU Withdraw Riser Valve 1C11-F102.
Standard Examinee simulates opening the valve for control rod 32-13.
CUE Comments SAT UNSAT Comment Number Page 7 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02 STOP TIME: _____________
TERMINATING CUES:
Control rod 32-13 is fully inserted.
K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER K/A NUMBER RO SRO 295015 AA 1.01 3.8 3.9 Page 8 of 9
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 4411.0801 REVISION: 02 INITIATING CUE A reactor scram occurred but control rod 32-13 failed to insert. Individually scram control rod 32-13 by venting the CRDH withdrawal line in accordance with CPS No. 4411.08, ALTERNATE CONTROL ROD INSERTION. The containment is accessible and the reactor is shutdown.
Page 9 of 9