Tech Spec Pages for Amendment Nos. 225 & 220 Regarding Revision to TS Surveillance Requirement 4.0.5
ML042080016
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/22/2004
From:
NRC/NRR/DLPM
To:
SHea J, 415-1388, NRR/DLPM
Shared Package
ML042050244 List:
References
TAC MC2242, TAC MC2243
Download: ML042080016 (2)


Text

APPLICABILITY SURVEILLANCE REQUIREMENTS 4.0.1 Surveillance Requirements shall be met during the OPERATIONAL MODES or other conditions specified for individual Limiting Conditions for Operation unless otherwise stated in an individual Surveillance Requirement. Failure to perform a Surveillance Requirement within the allowed surveillance interval, defined by Specification 4.0.2, shall constitute noncompliance with the OPERABILITY requirements for a Limiting Condition for Operation. Surveillance Requirements do not have to be performed on Inoperable equipment.

4.0.2 Each Surveillance Requirement shall be performed within the specified time interval with a maximum allowable extension not to exceed 25% of the surveillance interval. If an ACTION item requires periodic performance on a "once per. . ." basis, the above frequency extension applies to each performance after the initial performance. Exceptions to this Specification are stated in the individual Specifications.

4.0.3 If it is discovered that a Surveillance was not performed within its specified frequency, then compliance with the requirement to declare the Limiting Condition of Operation not met may be delayed, from the time of discovery, up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or up to the limit of the specified frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance. A risk evaluation shall be performed for any Surveillance delayed greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the risk impact shall be managed.

If the surveillance is not performed within the delay period, the Limiting Condition of Operation must immediately be declared not met, and the applicable ACTION(s) must be entered.

When the Surveillance is performed within the delay period and the Surveillance is not met, the Limiting Condition of Operation must immediately be declared not met, and the applicable ACTION(s) must be entered.

4.0.4 Entry into an OPERATIONAL MODE or other specified condition shall not be made unless the Surveillance Requirement(s) associated with a Limiting Condition for Operation has been performed within the stated surveillance interval or as otherwise specified. This provision shall not prevent passage through or to OPERATIONAL MODES as required to comply with ACTION requirements.

4.0.5 Surveillance Requirements for inservice inspection and testing of ASME Code Class 1, 2, and 3 components shall be applicable as follows:

a. Inservice inspection of ASME Code Class 1, 2, and 3 components shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a.

Inservice testing of ASME Code Class 1, 2, and 3 pumps and valves shall be performed in accordance with the ASME Code for Operation and Maintenance of Nuclear Power Plants (ASME OM Code) and applicable Addenda as required by 10 CFR 50, Section 50.55a.

TURKEY POINT - UNITS 3 & 4 314 0-3 AMENDMENTNOS. 225 & 220

APPLICABILITY SURVEILLANCE REQUIREMENTS (CONTINUED)

b. Surveillance intervals specified in Section Xl of the ASME Boiler and Pressure Vessel Code and applicable Addenda and the ASME OM Code and applicable Addenda shall be I applicable as follows in these Technical Specifications:

ASME Boiler and Pressure Vessel Code and the ASME OM Code and applicable Required frequencies for I -

Addenda terminology for inservice performing inservice Inspection inspection and testing activities and testing activities Weekly At least once per 7 days Monthly At least once per 31 days Quarterly or every 3 months At least once per 92 days Semiannually or every 6 months At least once per 184 days Every 9 months At least once per 276 days Yearly or annually At least once per 366 days Biennially or every 2 years At least once per 731 days

c. The provisions of Specification 4.0.2 are applicable to the above required frequencies for performing Inservice inspection and testing activities.
d. Performance of the above inservice inspection and testing activities shall be In addition to other specified Surveillance Requirements.
e. Nothing in the ASME Boiler and Pressure Vessel Code or the ASME OM Code shall be I construed to supersede the requirements of any Technical Specification.

4.0.6 Surveillance Requirements shall apply to each unit individually unless otherwise indicated as stated in Specification 3.0.5 for individual specifications or whenever certain portions of a specification contain surveillance parameters different for each unit, which will be identified in parentheses, footnotes or body of the requirement.

TURKEY POINT - UNITS 3 & 4 3/4 0-4 AMENDMENT NOS. 225 & 220