Responds to NRC 820712 Ltr Re post-accident sampling/post- Implementation review.Post-accident Sampling Sys for Each Unit Expected to Be Installed & Operational Prior to Startup Following Upcoming Refueling Outage
ML18086B617
Person / Time
Site: Salem  
Issue date: 08/13/1982
From: Liden E
Public Service Enterprise Group
To: Varga S
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.3, TASK-TM NUDOCS 8208250198
Download: ML18086B617 (1)


Text

Public Service PS~G Electric and Gas Company 80 Park Plaza, Newark, NJ 07101 / 201 430-7000 MAILING ADDRESS/ PO. Box 570, Newark, NJ 07101 August 13, 1982 Mr. Steven A. Varga, Chief Operating Reactors Branch #1 Division of Licensing

u. s. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, MD 20014 Gentlemen:

NUREG-0737 ITEM II.B.3, POST-ACCIDENT SAMPLING POST IMPLEMENTATION REVIEW SALEM UNITS NO. 1 AND 2 This response is in answer to your letter dated July 12, 1982.

The Post-Accident Sampling System for each Salem Unit is expected to be installed and operational prior to startup following each unit's upcoming refueling outage.

We will document how we have satisfied each of the criteria of NUREG-0737, ITEM II.B.3 within one month after completion of the Unit No. 1 refueling outage. Our submittal will cover both Sale~ Units. *

  • Very truly yours,

/

,~*/"/.j E,./

  • Liden, Manager

,,:Nuclear Licensing and

/Regulation