R. E. Ginna - Completion of Activities to Support Entry Into the Period of Extended Operation
ML092680059
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/18/2009
From: John Carlin
Constellation Energy Nuclear Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML092680059 (1)


Text

John Carlin R.E. Ginna Nuclear Power Plant, LLC Site Vice President 1503 Lake Road Ontario, New York 14519-9364 585.771.5200 585.771.3943 Fax John.Carlin@constellation.com 0 0Constellation Energy° Nuclear Generation Group September 18, 2009 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Control Desk

SUBJECT:

R.E. Ginna Nuclear Power Plant Docket No. 50-244 Completion of Activities to Support Entry into the Period of Extended Operation License Condition Item 2. F. of the R.E. Ginna Nuclear Power Plant Renewed Facility Operating License, No. DPR- 18, issued May 19, 2004 states the following:

"The Updated Final Safety Analysis Report supplement, submitted pursuant to 10 CFR 54.21 (d),

describes certain future activities to be completed prior to the period of extended operation. Ginna LLC shall complete these activities no later than September 18, 2009, and shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection."

In compliance with the above License Condition requirement, this letter is being submitted to notify you that implementation of all the activities required prior to the entry into the period of extended operation have been completed and can be verified by NRC inspection.

If you should have any questions regarding this submittal, please contact Thomas Harding at (585) 771-5219.

cc: S. J. Collins, NRC D. V. Pickett, NRC Resident Inspector, NRC