MONTHYEARML21168A1492021-06-0909 June 2021 Annual Meeting Attendees List ML20261H6032020-09-17017 September 2020 C-10's Certificate of Service for Motion for Leave, Reply to Oppositions and Exhibit INT053 ML20008D2232020-01-0808 January 2020 NRC Region I Twitter Feeds 10-1 to 12-31-2019 ML18136A8602018-05-16016 May 2018 02-2018 Aam NRC Staff List ML16349A1752016-12-21021 December 2016 MSFHI - Tables 1 and 2--Final 12-21-16 ML16203A4022016-06-15015 June 2016 06-15-16 - Publicly Available Documents Provided to Senator Markey in Response to His Letter Dated February 17, 2016, Pertaining to the Seabrook Station UFSAR Revisions 11, 12, 13, 14, and 15 ML16161A5872016-05-17017 May 2016 05-17-16, List of Publicly Available Documents Provided to Senator Edward Markey from Eugene Dacus, OCA Pertaining to the Seabrook Station UFSAR Revision 16 ML16146A1932016-04-28028 April 2016 License Renewal Application, April 28, 2016, Public Meeting - Meeting Attendance List ML16118A2112016-04-19019 April 2016 04-19-16 - List of Publicly Available Documents Provided to Senator Markey in Response to His Letter Dated February 17, 2016, Pertaining to the Seabrook Station UFSAR Chapter 3 ML16071A4422016-03-0606 March 2016 Receipt of External Hard Drive Containing Revised I/O Files from NextEra Seabrook Station Nuclear Power Plant Flood Hazard Re-evaulation Report (CAC MF36782) SBK-L-15120, Independent Spent Fuel Storage Installation (ISFSI) Ics/Eals2016-02-27027 February 2016 Independent Spent Fuel Storage Installation (ISFSI) Ics/Eals ML15072A0372015-03-0909 March 2015 Enclosures 1 and 2 - Response to Request for Additional Information for License Amendment Request 14-04 Revised Reactor Coolant System Pressure - Temperature Limits Applicable for 55 Effective Full Power Years and Affidavit ML14209A0262014-07-28028 July 2014 2014 Seabrook Annual Assessment Meeting Attendance List Sheet ML14182A3382014-06-30030 June 2014 FOIA/PA-2013-0332 - Resp 6 - Partial, Group H, Records Being Released in Their Entirety ML14182A1362014-06-30030 June 2014 FOIA/PA-2013-0332 - Resp 6 - Partial, Group I, Records Being Released in Part ML14182A1322014-06-30030 June 2014 FOIA/PA-2013-0332 - Resp 6 - Partial, Group G, Records Already Publicly Available ML14141A6272014-05-20020 May 2014 LTR-14-0288-Ticket - Senator Edward J. Markey Ltr. Information About NRC-Sanctioned Job Shadow Program with China ML14113A0582014-04-18018 April 2014 LTR-14-0224-Ticket - Senator Edward J. Markey and Senator Elizabeth Warren Ltr. Measures Needed to Protect Pilgrim Nuclear Power Station and the Seabrook Station Against Seismic Vulnerability ML15161A0402014-02-19019 February 2014 Draft Vital Inverter NOED 02191 SBK-L-14006, Response to Request for Additional Information for the Review of the Seabrook Station License Renewal Application Severe Accident Mitigation Alternatives Review. Part 3 of 32014-01-22022 January 2014 Response to Request for Additional Information for the Review of the Seabrook Station License Renewal Application Severe Accident Mitigation Alternatives Review. Part 3 of 3 ML14034A0212014-01-22022 January 2014 Response to Request for Additional Information for the Review of the Seabrook Station License Renewal Application Severe Accident Mitigation Alternatives Review. Part 2 of 3 ML14034A0202014-01-22022 January 2014 Response to Request for Additional Information for the Review of the Seabrook Station License Renewal Application Severe Accident Mitigation Alternatives Review. Part 1 of 3 ML15236A2732014-01-16016 January 2014 We the People, a National Whistleblower Organization ML14007A7152014-01-0707 January 2014 G20140030/LTR-14-0009-Ticket - Senator Jeanne Shaheen Email Seabrook - Piping/Plumbing (Constituent Correspondence) ML13364A2832013-12-30030 December 2013 Announcement of 2014 Generic Fundamentals Examination Administration Dates-Letter Dated Dec 30, 2013 ML13354B9542013-12-18018 December 2013 G20140055/LTR-13-0957-Ticket - Senator Edward Markey, Et Al., Ltr Requests the NRC Make No Decision on the 6/1/10, Request for the Seabrook Nuclear Power Plant for a 20 Year Operating License Until the Concrete Degradation Is Well Tested an ML13354C0052013-12-18018 December 2013 G20140010/LTR-13-0959-Ticket - Bert Knowles Ltr. Opposition for the Relicensing of the Seabrook Nuclear Plant ML12174A0332012-06-0404 June 2012 Region 1 Comments on Draft TIA for Seabrook ASR Issue ML12174A0462012-06-0404 June 2012 Preliminary Draft Response to Request for Technical Assistance for Seabrook Station Alkali-Silica Reaction Degradation of Concrete ML12131A3782012-05-10010 May 2012 Annual Assessment Meeting Signing Sheets April 2012 ML1211603332012-04-23023 April 2012 Detailed Questions for Seabrook ASR Public Meeting on April 23, 2012 ML12088A2142012-03-26026 March 2012 Concrete Degradation - Alkali Silica Reaction ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12054A6432012-02-16016 February 2012 Nextera Control of Contractors for ASR Issues ML12088A2132011-07-20020 July 2011 Concrete Degradation - Alkali Silica Reaction ML1117218982011-06-21021 June 2011 Annual Assessment Meeting Attendance List, June 8, 2011 ML1104802952011-02-15015 February 2011 Attachment to E-mail, Willoughby to Miller, NRC Conference Call on Friday - Seabrook Annulus Debris Interceptor Approach Velocity ML1100504852011-01-0505 January 2011 Attachment to E-mail, Kilby, to Miller, Information Related to Seabrook'S Proposed H License Amendment Request ML1019304602010-03-25025 March 2010 List of Historical Leaks and Spills at Us Commercial Nuclear Power Plants ML0927403272009-09-30030 September 2009 Seabrook Regulatory Conference Sign-in Sheets ML0913200902009-04-30030 April 2009 Annual Assessment Meeting Sign-in Sheet, 4/30/2009 ML0913305422008-11-0303 November 2008 Seabrook - Fire Protection of Safe Shutdown Capability (10CFR50, Appendix R, Revision 9 ML0810904032008-03-25025 March 2008 Annual Assessment Meeting Attendance List, 3/25/08 ML0808000362008-03-13013 March 2008 List of Attendees, 03/13/2008 Summary of Meeting with Eight Operating Nuclear Power Plant Licensees to Discuss Emerging Metallurgical Issues Certain Welds in Reactor Coolant System for Pressurized-Water Reactors ML0806704192008-03-0707 March 2008 CDBI Findings ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions ML0731104102007-10-17017 October 2007 Enclosure 2 to Fple Letter SBK-L-06227 - Emergency Initiating Condition Matrix, Modes 1, 2, 3, & 4 ML0731104072007-10-17017 October 2007 Enclosure 1 to Fple Letter SBK-L-06227 - Summary Explanation Providing the Necessary Justification for Changing the Basis of the Fple Seabrook Emergency Action Level (EAL) Scheme from NUREG-0654 to NEI 99-01, Revision 4 ML0731104132006-12-29029 December 2006 Enclosure 4 to Fple Letter SBK-L-06227 - Seabrook Emergency Classification System, Section 1-5.1 Through 1.5.11 ML0634705992006-12-14014 December 2006 Plant Service List 2021-06-09
[Table view] |
Text
NEXTERA CONTROL OF CONTRACTORS FOR ASR ISSUES Resource Estimate:
- 1. 3 inspection weeks (90 hrs direct inspection) from November, 2011 to February, 2012
- 2. Time charge to IP 71111.15, Operability (92701, Follow-up on URI,05000443/2011003-03).
- 3. Report No. 05000443/2011005, resident quarter
- 4. Outside R1 support is anticipated. For such support all issues of concern should be brought the attention of Region I,.Suresh Chaudhary (610-337-5335) or Richard Conte (610-337-5183)
Inspection Criteria:
- 1. Procurement control document (available in CERTEX)
- 2. ANSI N 45.2.11,
- 3. NEXTERA QA Plan should commit to the above ANSI Standard. (Exceptions should be Noted)
Scope of review:
Priority of review: observe implementations as it occurs or a review test results, the adequacy of plans/procedures should be sampled as it undercuts implementation and test results.
- 1. Review NEXTERA implementation review and associated action plans in order to understand activities including walk-down assessments and testing for the ASR problem and establish a comprehensive list of disconnects between the contractor plans and implementation schedules - tentative list noted below.
- 2. Identify activities and tests not to be done by NEXTERA, but potentially need to be done by either NextEra or NRC - tentative list noted below e.g., Triaxial test.
- 3. Laboratory testing on a selective basis (first time use at WJE, in IL, Nov. 16-18, 2011) with emphasis on:
- a. Calibration of test equipments,
- b. Proper implementation of Procurement Documents and Test Procedures,
- c. Observe set-up and test conditions are consistent with test procedures and standards,
- d. Observe and assure that the failure mode of the test cores are properly documented.
- e. Review and assure that test personnel are properly qualified and certified.
- 4. Review Phase 1 walk-down results prepared by MPR, and Reviewed by NEXTERA, including additional testing, if required, based on initial walk-down results (Week of Nov. 28, 2011).
- 5. Assess progress of Phase 2 walk-downs for Maintenance Rule Structures affected by ASR, including the adequacy of wlk-down procedures(Week of Nov. 28, 2011).
- 6. Based on inputs from R3 inspectors, and independentreview of test results, assess compressive strength values for the B Electrical Tunnel (Final review mat be delayed till January, 2012)
- 7. Assess test results of Tensile tests on concrete core samples from B Electrical Tunnel based on inputs from R3 inspectors, and independent review of test result (Final review mat be delayed till January, 2012).
LONGER TERM PROJECTS:
- 1. Review results of long term laboratory monitoring for residual concrete expansion and aggregate reactivity (Procurement plans should be available mid December 2011).
- 2. Assess NEXTERA in-situ monitoring of concrete expansion (Mapping pins for CEVA to be installed early to mid December, 2011).
- 3. Consider TIA for SGH reanalysis for CEB. Report may be available. mid January to early February, 2011 (Assess crack mapping progress in January, 2012).
- 4. Based on results of the TIA for the Control Bldg, consider the need for additional TIA for structural assessment ASR affected structures.
- 5. Decide on approach for Engineering Evaluation in March 2012, who has the lead NRR/DE or NRR/DLR.
QUESTIONS RELATED TO ADDITIONAL ACTIVITIES/TESTING - not evident from implementation schedule:
Site VP promised a gap analysis between what MPR action plan suggests and implementation schedule BUT when ??? Is there a need for a NextEra produced corrective action plan (requirement not needed; a license is being held up).
Discrepanciesbetween Action Plans and Implementation Schedule:
- 1. In-situ monitoring of temperature and moisture conditions (last bullet of 4.3.2 in ASR Action Plan from MPR)
- 2. Use of alternative surfaces such as in Unit 2 in order to assess investigations that might damage surfaces both internal or external in Unit 1 (section 4.3.3 in ASR Action Plan from MPR).
- 3. Impl. Schedule does not describe an interim and long term structural evaluation of each affected building by ASR per section 4.4 of the ASR action plan - only a structural evaluation is stated.
- 4. Long Term monitoring and Remedial Plan are suggested in ASR action plan per ppl3-14, not evident in the implementation schedule or is it to be assumed in the project SBRK.EN.05.03.20.09, Develop Eng. eVal. To address requests identified in RAI B.2.1.31-1
- 5. Page 12 of ASR Action Plan on Core Analysis suggest the use of a Stiffness Damage Test (qualitative but shorter term results on progression of ASR reaction) - not evident that it will be done on implementation schedule.
- 6. Need for additional Core samples from Buildings other than Control Bldg in Unit 1 -
Implementation schedule does point to Phase I and II assessment walkdowns and the potential to identify additional core/tests - Phase II won't get done until the end of Jan. 2012 which appears relatively late in the schedule.
- 7. Why isn't the Mitigation of Water Intrusion (section 4.2 of Action Plan from MPR) not on the implementation schedule of 24 Oct 2011
- 8. Building floor slabs, most of the discussion has been on basement walls.
Needed Tests and other Activities not planned by NextEra:
- 9. Need to review how NEXTERA is establishing a correlation between Compressive strength and modulus of elasticity, if no tensile test are done (tensile strength testing current planned per Test Plan for ASR section 3.2)
- 10. NOTE: pull out test section 3.4 is contingent on tensile strength testing, if tensile testing not doen the pull out testing may not be done.
- 11. Need for Triaxial Tests by NEXTERA and/or NRC (pro/con analysis needed). Not listed on the Test Plan for ASR
- 12. Need to calculate Poisson's ratio for the Core samples - not listed on the Test Plan for ASR.