Review of Industry Guidelines Related to Interim Compensatory Measures Associated with the May 23, 2002, Security Orders to Decommissioning Facilities and Independent Spent Fuel Storage Installations Using Wet Storage
ML021580264
Person / Time
Issue date: 05/30/2002
From: Zimmerman R
Office of Nuclear Security and Incident Response
To: Ralph Beedle
Nuclear Energy Institute
Gordon D, DNS/NSIR 415-1162
References
Download: ML021580264 (5)


Text

May 30, 2002Mr. Ralph BeedleSenior Vice President and Chief Nuclear Officer Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708

SUBJECT:

REVIEW OF INDUSTRY GUIDELINES RELATED TO INTERIMCOMPENSATORY MEASURES ASSOCIATED WITH THE MAY 23, 2002, SECURITY ORDERS TO DECOMMISSIONING FACILITIES AND INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS USING WET STORAGE

Dear Mr. Beedle:

The U.S. Nuclear Regulatory Commission (NRC) issued Orders dated May 23, 2002, for alldecommissioning commercial nuclear power plants and independent spent fuel storage installations using wet storage, to immediately implement interim safeguards and security compensatory measures (ICMs). The Orders for each plant included a safeguards information (SGI) attachment containing specific ICMs to be implemented by the receiving licensee.Following issuance of the Orders, the Nuclear Energy Institute (NEI) Security Working Group(SWG) developed a draft industry guidance document involving SGI to facilitate licensee implementation of the specific ICMs contained in the Orders. The NRC staff conducted meetings with the NEI SWG at NRC headquarters specifically to discuss the draft implementing guidance.By letter dated May 29, 2002, NEI formally submitted two guidance documents entitled"Implementation Guidance for Interim Compensatory Measures for Decommissioning Facilities located inside a Reactor Protected Area for the Order Dated May 23, 2002," and "Implementation Guidance for Interim Compensatory Measures for Decommissioning Nuclear Power Plants with Fuel in the Spent Fuel Pool and Independent Spent Fuel Storage Installations Using Wet Storage in the Current Threat Environment for the Order Dated May 23, 2002." The NRC staff has completed its review of the NEI guidance dated May 29, 2002, and has determined that it provides an acceptable method for licensee implementation of the ICMs.As discussed in the Order cover letters, the Orders do not obviate the need for licensees tocontinue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001.

Mr. R. Beedle Please contact Mr. Glenn Tracy of my staff at (301) 415-1031 if you have any questions.Sincerely,/RA/Roy P. Zimmerman, DirectorOffice of Nuclear Security and Incident Response cc: See next page

ML021580264DOCUMENT NAME: C:\MyFiles\Checkout\Decom-Endorse-letter.wpd*See previous concurrence OFFICEDNS/RSPSDNS/RSPSDIR:DNSDIR:NSIR NAMED. Gordon*V. Ordaz*G. Tracy*R. ZimmermanDATE05/30/200205/30/200205/30/200205/30/2002 DISTRIBUTION

RZimmerman MWeber GTracy CHaney SCollins/JJohnson BSheron WBorchardt JZwolinski

CHolden RGramm SDembek BBoger/WDean VOrdaz GHolahan KGibson PMadden HMiller, Region I LReyes, Region II JDyer, Region III EMerschoff, Region IV JShea, EDO WBeecher, OPA DRathburn, OCA DNelson, OE LChandler, OGC JGoldberg, OGC SDroggitis, OSTP RStransky, NSIR JLieberman, OIP

ACRS SECY cc: Ms. Lynette Hendricks, Director Plant Support Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708Mr. Ronald RoseNuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708