ML18351A287

From kanterella
Revision as of 03:36, 12 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
GEH-MO: CY2019 Integrated Inspection Plan
ML18351A287
Person / Time
Issue date: 12/17/2018
From: Rhex Edwards
Division of Nuclear Materials Safety III
To: Mcfadden A
General Electric Co
References
Download: ML18351A287 (1)


Text

From: To: Cc:

Subject:

Date: Edwards Rhex "anthony.mcfadden@ae com" Edwards Rhex; Kunowski, Michael GEH-MO: CY2019 Integrated Inspection Plan Monday, December 17, 2018 11:42:34 AM

Dear Mr. McFadden,

In accordance with Inspection Manual Chapter 2690, "Inspection Program for Dry Cask Storage of Spent Reactor Fuel at Independent Spent Fuel Storage Installations and for 10 CFR Part 71 Transportation Packagings," the NRC Region Ill staff developed an Integrated Inspection Plan (IIP) for General Electric-Hitachi Morris Operation for calendar year 2019. The inspection plan is based on your current performance and your planned activities for the site in January through December 2019. Below is a list of the periodic inspection procedures we expect to use during our inspections.

The procedures used during each inspection will depend on the specific activities being conducted at the site. Additional discretionary inspection procedures may be used if ISFSI activities warrant. We will gladly discuss any questions you may have regarding this IIP. If you have questions, please contact me at (630) 829-9722.

If you have questions related to security inspections, please contact the Plant Support Branch Chief at 630-829-9500.

Sincerely, Rhex Edwards Inspection Procedure No. IP 81311, "Physical Security Requirements for ISFSls" Rhex Edwards Senior Health Physicist USNRC Region Ill DNMS MCID 630-829-9722 Approximate Approximate Start Date End Date April 1, 2019 April 5, 2019