2018 Quad Cities Nuclear Station Initial License Examination Prep Checklist ES-201-1
ML19141A398
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 05/21/2019
From: David Reeser
Exelon Generation Co
To:
NRC/RGN-III/DRS/OLB
Shared Package
ML17165A499 List:
References
Download: ML19141A398 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Quad Cities Nuclear Power Station Date of Examination:

Weeks of 7/16/18 and 7/23/18 Developed by: Written

Facility NRC // Operating: Facility NRC Target Date* Task Description (Reference)

Chief Examiner's Initials 11/17/17 1. Examination administration date confirmed (C.1.a; C.2.a

-b). For NRC

-prepared exams, arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3). DWR 12/15/17 2. NRC examiners and facility contact assigned (C.1.d; C.2.f).

DWR 12/15/17 3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facility's prescreening process (ES

-401, D.1.b).

N/A 12/15/17 4. Reference material due for NRC

-prepared exams (C.1.e; C.3.c; Attachment 3). DWR 12/15/17 5. Corporate notification letter sent (C.2.e).

DWR 12/11/17 6.a NRC-developed written examination outline (ES

-401-1/2 or ES-401N-1/2 and ES

-401-3 or ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e

-f; C.2.h; C.3.d

-e). DWR 12/29/17 6.b Facility feedback on the written examination outline due (C.1.f). DWR 02/19/18 7. Operating test outline(s) and other checklists, including Forms ES

-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable

, sent to the facility contact for review and feedback (C.1.e-f; C.3.d-e). DWR 03/19/18 8. Operating test outline(s) reviewed with the facility licensee and feedback provided to the NRC [on-site visit] (C.2.h; C.3.d-e). DWR 04/27/18 9. Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms ES

-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES

-401-3 or ES-401N-3); supporting documentation (including Forms ES

-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, ES-401N-6, and any Form ES

-201-2 and ES-201-3 updates); and reference materials due (C.1.e

-h; C.3.d).

N/A 04/27/18 05/07/18 10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded for facility licensee review (C.1.i; C.2.h; C.3.f

-g). DWR 05/11/18 11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES

-202). DWR -NONE 05/25/18 06/01/18 12. Written exam and operating test reviews completed (C.3.f).

DWR 06/18/18 13. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k

-l; C.2.h; C.3.g). The NRC and the facility licensee conduct exam preparatory week.

DWR 06/15/18 14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398) due (C.1.m; C.2.i; ES

-202). DWR 0 6/29/18 15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due and Form ES-201-4 prepared (C.1.m; C.2.k; ES

-202). DWR 07/06/18 16. Written examinations and operating tests approved by the NRC supervisor (C.2.j

-k; C.3.h).

DWR 07/06/18 17. Request facility licensee management feedback on the examination (C.2.l).

DWR 07/06/18 18. Final applications reviewed; one or two (if more than 10) applications audited to confirm qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; Attachment 5; ES

-202, C.3.j; ES

-204). DWR 07/06/18 19. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k).

DWR 07/06/18 20. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i).

DWR

  • Target dates are based on facility

-prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted on a case