10 CFR 50.55a Rulemaking UpdateKeith Hoffman Division of Materials and License RenewalOffice of Nuclear Reactor RegulationMay 23, 2018 Two Ongoing Rulemakings 1.Proposed Rule: Incorporate by reference ASME Code Case RGs (RG 1.84, Rev. 38; RG 1.147, Rev. 19; RG 1.192, Rev 3)(RIN 3150-AJ93, Docket ID NRC
-2017-0024)2.Proposed Rule: Incorporate by reference ASME 2015 & 2017 BPV Code Editions(RIN 3150-AJ74, Docket ID NRC
-2016-0082)2 Rulemaking Process 3Final RuleProposed RuleRegulatory (Technical)BasisIdentify need for rulemakingIt has been NRC's practice to use ASME codes to establish requirements for nuclear power plants.*Foundation of effective rulemaking
- Draft rule text*Public meeting
- 75 day public comment period (typically)
- Final rule textOpportunities for public participation 3IBR 2015 & 2017 EditionsIBRCode Case RGs Timeline -Edition/Addenda Rulemakings 4PublicationYearASME BPV CodeASME OM NRC Proposed Rule NRC Final Rule 20032003 Addenda2003 Addenda 20042004 Edition2004 Edition69 FR 879 (1/7/2004
)69 FR 58804 (10/1/2004) 20052005 Addenda2005 Addenda 20062006 Addenda2006 Addenda 20072007 Edition72 FR 16731 (4/5/2007) 20082008 Addenda73 FR 52730 (9/10/2008) 20092009 Addenda2009 Edition 20102010 Edition75 FR 24324 (5/4/2010) 20112011 Addenda2011 Addenda76 FR 36232 (6/21/2011) 20122012 Edition 20132013 Edition 2014 20152015 Edition2015 Edition80 FR 56820 (9/18/2015) 2016 20172017 Edition2017 Edition82 FR 32934 (July 18, 2017) 2018Target: September 2018 2019Target: Late 2019 Timeline -Code Case RG Rulemakings 5PublicationYearASME BPV Code Case Supplements NRC Proposed Rule NRC Final RuleRG 1.84RG 1.147RG 1.192 20037 8 9 10 1168 FR 40469 (7/8/2003)Rev. 32Rev. 13Rev. 0 200412 1 2 3 69 FR 46452 (8/3/2004) 20054 5 6 770 FR 56809 (9/29/2005)Rev. 33Rev. 14 20068 9 10 1171 FR 62942 (10/27/2006) 20070 1 2 372 FR 71750 (12/19/2007)Rev. 34Rev. 15 20084 5 6 7 20098 9 10 11 074 FR 26303 (6/2/2009) 20101 2 3 475 FR 61321 (10/5/2010)Rev. 35Rev. 16 20115 6 7 8 20129 10 11 20130 1 2 378 FR 37886 (6/24/2013) 20144 5 6 779 FR 65776 (11/5/2014)Rev. 36Rev. 17Rev. 1 2015x x x x 2016 x x x x81 FR 10780 (3/2/2016) 2017x x x x 2018Target: July 201883 FR 2331 (1/17/
2018)Rev. 37Rev. 18Rev. 2 2019Target: May 2019Rev.38Rev. 19Rev. 3 ASME Code Case RG Rulemaking
-Schedule*Publish proposed rulemaking in the Federal Register in July 2018
- 75 days to submit public comments
- NRC will provide detailed written responses to written public comments
- Target date to publish final rule in the Federal Registeris in May 2019 6
Scope of ASME 2015 & 2017 Editions Rulemaking
- Incorporate by reference the 2015 & 2017 Editions of Section III, Division 1, of ASME BPV Code*Incorporate by reference the 2015 &2017 Editions of Section XI, Division 1, of ASME BPV Code*Incorporate by reference the 2015& 2017 Editions of ASME OM Code 7 Scope of ASME 2015 & 2017Editions Rulemaking (cont'd)
- (-additional items within scope-)
- Update Code Cases N
-770 & N-729*Remove outdated conditions
- Revise existing conditions 8
ASME 2015 & 2017 EditionsRulemaking
-Schedule*Publish proposed rulemaking in the Federal Register in September 2018
- 75 days to submit public comments
- NRC will provide detailed written responses to written public comments
- Target date to publish final rule in the Federal Registeris late in 2019 9
How to get involved10To find information about-Search for docket ID-ASME 2015 & 2017rulemaking NRC-2016-0082ASME Code Case RGs NRC-2017-0024 Questions & Comments 11 AcronymsASMEAmerican Society of Mechanical Engineers BPVBoiler & Pressure VesselCFRCode of Federal Regulations FRFederal RegisterIBRIncorporation by ReferenceISIInservice InspectionISTInservice Testing NRCNuclear Regulatory Commission OMOperation & Maintenance RGRegulatory GuideRINRegulation Identifier Number12