Information Notice 1985-32, Recent Engine Failures of Emergency Diesel Generators | 22 April 1985 | Recent Engine Failures of Emergency Diesel Generators | Jordan E NRC/IE | |
ML20044B248 | 11 July 1990 | Proposed Tech Specs 4.0.5,3/4.4.3.1, RCS Leakage Detection Sys, 3/4.4.3.2, Operational Leakage, 3/4.8.3.1, Onsite Power Distribution Sys-Operating & 3/4.8.1.1, AC Sources - Operating. | Illinois Power Company | |
ML20085N062 | 23 June 1995 | Proposed Tech Specs Bases,Per TS 5.5.11, TS Bases Control Program | Illinois Power Company | |
ML20100H790 | 22 February 1996 | Proposed Tech Specs,Deleting SR 3.3.8.1.1 Which Requires Channel Check for Loss of Power Instrumentation & Changing TS Table 3.3.8.1-1 to Change Allowable Value for Degraded Voltage Function from 3762V & 3832V to 3876V | Illinois Power Company | |
ML20134M318 | 19 November 1996 | Proposed Tech Specs Revising Table 3.3.8.1-1, Loss of Power Instrumentation, by Dividing Function, Degraded Voltage - 4.16 Kv Basis & Degraded Voltage Dropout - 4.16 Kv Basis, re-numbering Items in Table & Revising Associated Notes | Illinois Power Company | |
ML20149J170 | 22 July 1997 | Proposed Tech Specs Requesting Exemption to 10CFR50,App a, General Design Criteria to Allow Operation W/Identified Offsite Circuit Condition | Illinois Power Company | |
ML20196A150 | 20 November 1998 | Revised Pages Constituting Rev 3 to CPS TS Bases,Consisting of Pages Annotated with Rev Numbers 3-1,3-2,3-3,3-4 & 3-5. Changes to Text Identified with Rev Bars.No Rev Bars Included for Changes to Format | Illinois Power Company | |
ML20236K708 | 30 October 1987 | Proposed Tech Specs Re Crvics Instrumentation,Remote Monitoring Instrumentation,Containment Isolation Valves & Radiation Monitoring Instrumentation | Illinois Power Company | |
ML20237C350 | 17 August 1998 | Proposed Tech Specs Partially Reducing Load at Which DGs Are Required to Be Tested Per Affected SRs in Order to Reduce Stress & Wear on Machines While Still Sufficiently Challenging Machines to Confirm Operability | Illinois Power Company | |
ML20245K191 | 30 June 1989 | Proposed Tech Specs,Clarifying Definition of Core Alteration Re Movement of Fuel,Sources or Reactivity Control Components Vs Movement of Incore Instrumentation | Illinois Power Company | |
NRC Generic Letter 1984-15 | 2 July 1984 | NRC Generic Letter 1984-015: Proposed Actions to Improve and Maintain Diesel Generator Reliability | Eisenhut D Office of Nuclear Reactor Regulation | |
RS-07-074, Application for Technical Specification Change TSTF-423, Risk Informed Modification to Selected Required Action End States for BWR Plants, Using the Consolidated Line Item Improvement Process | 21 June 2007 | Application for Technical Specification Change TSTF-423, Risk Informed Modification to Selected Required Action End States for BWR Plants, Using the Consolidated Line Item Improvement Process | Exelon AmerGen Benyak D | Office of Nuclear Reactor Regulation Document Control Desk |
RS-09-003, Additional Information Supporting Requests for License Amendments to Adopt TSTF-423, Technical Specifications End States, NEDC-32988-A | 30 January 2009 | Additional Information Supporting Requests for License Amendments to Adopt TSTF-423, Technical Specifications End States, NEDC-32988-A | Exelon Hansen J | Office of Nuclear Reactor Regulation Document Control Desk |
RS-10-008, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) | 15 February 2010 | Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) | Exelon Hansen J | Office of Nuclear Reactor Regulation Document Control Desk |
RS-10-093, Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B | 21 May 2010 | Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B | Exelon Hansen J | Office of Nuclear Reactor Regulation Document Control Desk |
RS-11-117, License Amendment Request to Modify Technical Specifications Section 3.8.1, AC Sources - Operating. | 15 August 2011 | License Amendment Request to Modify Technical Specifications Section 3.8.1, AC Sources - Operating. | Exelon David Gullott | Office of Nuclear Reactor Regulation Document Control Desk |
RS-18-130, Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO | 1 November 2018 | Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO | Exelon Simpson P | Office of Nuclear Reactor Regulation Document Control Desk |
RS-20-028, 1 to Updated Safety Analysis Report, CPS Tsb | 31 March 2020 | 1 to Updated Safety Analysis Report, CPS Tsb | Exelon | Office of Nuclear Reactor Regulation |
U-601048, Application for Amend to License NPF-62,consisting of 24 Separate Tech Spec Changes,Including Crvics Instrumentation, Remote Shutdown Monitoring Instrumentation & Containment Isolation Valves.Fee Paid | 30 October 1987 | Application for Amend to License NPF-62,consisting of 24 Separate Tech Spec Changes,Including Crvics Instrumentation, Remote Shutdown Monitoring Instrumentation & Containment Isolation Valves.Fee Paid | Hall D Illinois Power Company | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
U-601261, Forwards Interpretation Re Inoperability of Sys Providing Support Function,For Comments | 20 September 1988 | Forwards Interpretation Re Inoperability of Sys Providing Support Function,For Comments | Holtzscher D Illinois Power Company | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
U-603030, Application for Amend to License NPF-62,partially Reducing Load at Which DGs Are Required to Be Tested Per Affected SRs in Order to Reduce Stress & Wear on Machines While Still Sufficiently Challenging Machines to Confirm Operability | 17 August 1998 | Application for Amend to License NPF-62,partially Reducing Load at Which DGs Are Required to Be Tested Per Affected SRs in Order to Reduce Stress & Wear on Machines While Still Sufficiently Challenging Machines to Confirm Operability | Walter MacFarland Illinois Power Company | Office of Information Resources Management |
U-603588, Transmittal of Revision 7 to Clinton Power Station Technical Specification Bases | 27 November 2002 | Transmittal of Revision 7 to Clinton Power Station Technical Specification Bases | AmerGen Iliff W | Office of Nuclear Reactor Regulation Document Control Desk |
U-603987, Transmittal of Revision 13 to Technical Specification Bases | 1 October 2010 | Transmittal of Revision 13 to Technical Specification Bases | Exelon Kemper D | Office of Nuclear Reactor Regulation Document Control Desk |
U-604152, Transmittal of Revision 15 to Technical Specification Bases | 31 December 2013 | Transmittal of Revision 15 to Technical Specification Bases | Exelon Taber B | Office of Nuclear Reactor Regulation Document Control Desk |
U-604454, Transmittal of Revision 20 to Technical Specification Bases | 31 December 2018 | Transmittal of Revision 20 to Technical Specification Bases | Exelon Kapellas B | Office of Nuclear Reactor Regulation Document Control Desk |