Mid-cycle Performance Report and Inspection Plan - Three Mile Island Unit 1
ML062430604
Person / Time
Site: Crane Constellation icon.png
Issue date: 08/31/2006
From: Ronald Bellamy
NRC/RGN-I/DRP/PB7
To: Crane C
AmerGen Energy Co
bellamy r r
References
Download: ML062430604 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 August 31, 2006 Mr. Christopher M. Crane President and CEO AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-E Kennett Square, PA 19348

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - THREE MILE ISLAND UNIT 1

Dear Mr. Crane:

On August 9, 2006, the NRC staff completed its performance review of Three Mile Island Unit 1 for the first half of the calendar year 2006 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in accordance with 10 CFR 2.390" will include the physical protection review and resultant inspection plan.

Plant performance for the most recent quarter at Three Mile Island Unit 1 was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct the standard reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules and Practices, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

C. M. Crane 2 If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Ronald R. Bellamy, Chief Reactor Projects Branch 7 Division of Reactor Projects Docket No. 50-289 License No. DPR-50

Enclosure:

Three Mile Island, Unit 1 Inspection/ Activity Plan cc w/encl:

Chief Operating Officer, AmerGen Site Vice President - TMI Unit 1, AmerGen Plant Manager - TMI, Unit 1, AmerGen Regulatory Assurance Manager - TMI, Unit 1, AmerGen Senior Vice President - Nuclear Services, AmerGen Vice President - Mid-Atlantic Operations, AmerGen Vice President - Operations Support, AmerGen Vice President - Licensing and Regulatory Affairs, AmerGen Director Licensing - AmerGen Manager Licensing - TMI, AmerGen Vice President - General Counsel and Secretary, AmerGen T. ONeill, Associate General Counsel, Exelon Generation Company J. Fewell, Esq., Assistant General Counsel, Exelon Nuclear Correspondence Control Desk - AmerGen Chairman, Board of County Commissioners of Dauphin County Chairman, Board of Supervisors of Londonderry Township R. Janati, Director, Bureau of Radiation Protection, State of PA J. Johnsrud, National Energy Committee E. Epstein, TMI-Alert (TMIA)

D. Allard, PADEP

C. M. Crane 3 Distribution w/encl:

S. Collins, RA M. Dapas, DRA B. Holian, DRP D. Lew, DRP R. Bellamy, DRP R. Fuhrmeister, DRP A. Rosebrook, DRP D. Kern, DRP, Senior Resident Inspector J. Brand, DRP, Resident Inspector TMI Resident OA B. Sosa, RI OEDO R. Laufer, NRR F. Saba, PM, NRR DRS Director, Region I DRS Deputy Director, Region I DRS Branch Chiefs (6)

RidsNrrDipmIipb@nrc.gov Institute of Nuclear Power Operations (INPO)

Region I Docket Room (with concurrences)

SUNSI Review Complete: ____RRB_______ (Reviewers Initials)

DOCUMEN T NA ME: S :\ROP 7 Mid C ycle Re view\2 006 R OP7 Mid-Cycle Letters\T MI 2006 Mid-Cycle Letter.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME ARosebrook/AAR RBellamy/RRB DATE 7/31/06 8/29/06 OFFICIAL RECORD COPY

Page 1 of 2 Three Mile Island 1 08/31/2006 09:45:53 Inspection / Activity Plan Report 22 07/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type MODS - MODS AND 50.59 3 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 07/24/2006 07/28/2006 Baseline Inspections 1 IP 7111117B Permanent Plant Modifications 07/24/2006 07/28/2006 Baseline Inspections 71114 - EP PRGM INSP & PI VERIFICATION 2 1 IP 7111402 Alert and Notification System Testing 07/17/2006 07/21/2006 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 07/17/2006 07/21/2006 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 07/17/2006 07/21/2006 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 07/17/2006 07/21/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 07/17/2006 07/21/2006 Baseline Inspections 7112203 - PUB RAD SAFETY - REMP 1 1 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 08/28/2006 09/01/2006 Baseline Inspections TI-169 - MSPI VERIFICATION 2 1 IP 2515/169 Mitigating Systems Performance Index Verification 09/01/2006 11/15/2006 Safety Issues 71121 - OCC RAD PROT 1 1 IP 7112101 Access Control to Radiologically Significant Areas 11/06/2006 11/10/2006 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 11/06/2006 11/10/2006 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 11/06/2006 11/10/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 11/06/2006 11/10/2006 Baseline Inspections 7111121 - CDBI (COMPONENT DESIGN BASES INSPECTION) 7 1 IP 7111121 Component Design Bases Inspection 01/08/2007 01/12/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 01/22/2007 01/26/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 02/05/2007 02/09/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 02/12/2007 02/16/2007 Baseline Inspections 7111111B - L.O. REQUAL. PROG. + P/F REVIEW 5 1 IP 7111111B Licensed Operator Requalification Program 02/19/2007 02/23/2007 Baseline Inspections 1 IP 7111111B Licensed Operator Requalification Program 02/26/2007 03/02/2007 Baseline Inspections 7111112 - MAINTENANCE RULE INSP 1 1 IP 7111112B Maintenance Effectiveness 02/26/2007 03/02/2007 Baseline Inspections 4/23+EXM - OPERATOR LICENSING INITIAL EXAMS 3 1 U01603 TMI INITIAL EXAM (6/07) 03/26/2007 03/30/2007 Not Applicable 1 U01603 TMI INITIAL EXAM (6/07) 04/23/2007 05/04/2007 Not Applicable 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 03/05/2007 03/09/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 03/05/2007 03/09/2007 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/05/2007 03/09/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Three Mile Island 1 08/31/2006 09:45:53 Inspection / Activity Plan Report 22 07/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7111401 - EP EXERCISE & PI VERIFICATION 4 1 IP 7111401 Exercise Evaluation 04/16/2007 04/20/2007 Baseline Inspections 1 IP 71151-EP01 Drill/Exercise Performance 04/16/2007 04/20/2007 Baseline Inspections 1 IP 71151-EP02 ERO Drill Participation 04/16/2007 04/20/2007 Baseline Inspections 1 IP 71151-EP03 Alert & Notification System 04/16/2007 04/20/2007 Baseline Inspections 7112201 - PUB RAD PROT - RETS 1 1 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 05/14/2007 05/18/2007 Baseline Inspections 7112202 - PUB RAD SAFETY - RADWASTE 1 1 IP 7112202 Radioactive Material Processing and Transportation 08/20/2007 08/24/2007 Baseline Inspections 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 10/01/2007 10/05/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 10/01/2007 10/05/2007 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 10/01/2007 10/05/2007 Baseline Inspections 7111108P - IN-SERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 10/30/2007 11/02/2007 Baseline Inspections 1 IP 7111108P Inservice Inspection Activities - PWR 11/13/2007 11/16/2007 Baseline Inspections 7111107 - HEAT SINK INSP 2 1 IP 7111107B Heat Sink Performance 11/05/2007 11/09/2007 Baseline Inspections 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 11/05/2007 11/09/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 11/05/2007 11/09/2007 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 11/05/2007 11/09/2007 Baseline Inspections TI-166 - CONTAINMENT SUMP MODIFICATIONS 1 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 11/12/2007 11/19/2007 Safety Issues 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 12/03/2007 12/07/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 12/03/2007 12/07/2007 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 12/03/2007 12/07/2007 Baseline Inspections 1 IP 71151 Performance Indicator Verification 12/03/2007 12/07/2007 Baseline Inspections 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 03/03/2008 03/09/2008 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 03/03/2008 03/09/2008 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/03/2008 03/09/2008 Baseline Inspections 71152B - PI&R 4 1 IP 71152B Identification and Resolution of Problems 03/31/2008 04/04/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.