Submits Quarterly Followup Response to Re Const Progress.Schedule Remains Unchanged.Fuel Load Scheduled for Apr 1984
ML20073A812
Person / Time
Site: Callaway Ameren icon.png
Issue date: 03/31/1983
From: Dougherty C
UNION ELECTRIC CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
ULNRC-615, NUDOCS 8304110874
Download: ML20073A812 (2)


Text

t v, g .'

UNION EtscTRic COMPANY 1901 GRATIOT STREET . 37. Louis

(**""*^ " " " * *

, March 31, 1983 """"*(([*[".

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Nuclear Regulatory Commission Washington, D.C. 20555 ULNRC-615

Dear Mr. Denton:

DOCKET NUMBER 50-483 CALLAWAY PLANT, UNIT 1 QUARTERLY PROGRESS UPDATE

Reference:

ULNRC-600' dated January 7, 1983 This is a quarterly follow-up response to your letter of May 29, 1981, regarding progress of our Callaway Plant.

Our schedule remains unchanged since our last report, which was transmitted by the referenced letter. Fuel load is scheduled for April, 1984 with commercial operation scheduled for late 1984 or early 1985.

4 O

Sincerely, he&; o"

/

u d ~

wara'a%i s

.. -Yf cc: Glenn L. Koester Vice President Operations Kansas Gas & Electric P.O. Box 208 Wichita, Kansas 67201 Donald T. McPhee Vice President Kansas City Power and Light Company 1330 Baltimore Avenue Kansas City, Missouri 64141 Gerald.Charnoff, Esq.

Shaw, Pittman, Potts & Trowbridge 1800 M. Street, N.W.

Washington, D.C. 20036 Nicholas A. Petrick Executive Director SNUPPS 5 Choke Cherry Road Rockville, Maryland 20850 John H. Neisler Callaway Resident Office U.S. Nuclear Regulatory Commission RRil i

Steedman, Missouri 65077 4

J J

l_