ML23017A081
| ML23017A081 | |
| Person / Time | |
|---|---|
| Site: | Hermes File:Kairos Power icon.png |
| Issue date: | 01/10/2023 |
| From: | Benjamin Beasley NRC/NRR/DANU/UAL1 |
| To: | Lawrence Burkhart, Weidong Wang Advisory Committee on Reactor Safeguards |
| Shared Package | |
| ML23017A120 | List: |
| References | |
| Download: ML23017A081 (1) | |
Text
From: Benjamin Beasley To: Weidong Wang; Larry Burkhart Cc: William Jessup
Subject:
Preliminary chapters of Hermes SE Date: Tuesday, January 10, 2023 4:50:00 PM Attachments: Preliminary Hermes CP SE Chapter 5 for ACRS.pdf Preliminary Hermes CP SE Chapter 7 for ACRS.pdf Preliminary Hermes CP SE Chapter 8 for ACRS.pdf Preliminary Hermes CP SE Chapter 9 for ACRS.pdf Preliminary Hermes CP SE Chapter 10 for ACRS.pdf Preliminary Hermes CP SE Chapter 11 for ACRS.pdf Preliminary Hermes CP SE Chapter 12 for ACRS.pdf Preliminary Hermes CP SE Chapter 14 for ACRS.pdf Preliminary Hermes CP SE Chapter 16 for ACRS.pdf Preliminary Hermes CP SE Chapter 17 for ACRS.pdf Preliminary Hermes CP SE Chapter 18 for ACRS.pdf
- Weidong,
Attached are several preliminary chapters from the safety evaluation for the Hermes construction permit application. These chapters have been reviewed by branch chiefs and received a preliminary review by OGC. However, these chapters are not final because they still need to be reviewed by division management and receive the final OGC review. Thus, these preliminary chapters could change between now and the approved SE that will be sent to ACRS for formal review.
I am sending these chapters in advance so that members can become familiar with the safety evaluation and begin preparing for the formal review. The NRC staff is willing to answer any questions that members may have.
I expect to send the remaining preliminary chapters to you around the end of January.
Ben