Notifies of Discrepancy Between Mark I Containment Program External Mod Completion Date Listed in SECY-80-359 & Date Submitted in .Final External Major Mod Scheduled for Completion During Fall 1981 Refueling Outage
ML19344B116
Person / Time
Site: Pilgrim
Issue date: 08/15/1980
From: Andognini G
BOSTON EDISON CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
80-190, NUDOCS 8008250598
Download: ML19344B116 (1)


Text

BOSTON EpisON COMPANY GENERAL OFFICES 8o0 Sovtston SimEff Bostow. MassacMusETts 02199 G. Camb AMooawsms suPERINTEMcENT Auguse 15, 1980 uuctEAR o.a.riou s ow..v.E.,

BECo Ltr. #80-190 Mr. Darrell G. Eisenhut, Director Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Comission Washington, D. C.

20555 License No. DPR-35 Docket No. 50-293 Mark I Containment Long-Term Program

References:

(a) SECY-80-359 dated July 30, 1980 (b) BECo Letter, G.C. Andognini to V. Stello dated May 9, 1979 (c) NRC Letter, V. Stello to G.C. Andognini dated March 12, 1979

Dear Sir:

Enclosure I to reference (a) presents each Mark I licensee's schedule for com-pletion of the Mark I modifications. The completion date for external modifi-cations listed for Pilgrim Station, May 1981, does not agree with the information which we submitted to you in reference (b). Our final external major modification, torus attached piping, is scheduled for completion during our 1981 refueling outage which will commence in the fall of 1981.

If any additional information would assist in further clarifying this issue, please do not hesitate to contact us.

Very truly yours,

(