Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
Date released: 04/12/2018 Download: ML18060A411



Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
ML18060A417
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/28/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B H
City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2017-LLA-0102, LAR 17-034
Download: ML18060A417 (7)
Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
ML18060A416
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/28/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B H
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2017-LLA-0102, LAR 17-034
Download: ML18060A416 (5)
Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
ML18060A415
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/28/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B H
City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2017-LLA-0102, LAR 17-034
Download: ML18060A415 (2)
Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
ML18060A414
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/28/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B H
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2017-LLA-0102, LAR 17-034
Download: ML18060A414 (5)
Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
ML18060A413
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/28/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B H
City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2017-LLA-0102, LAR 17-034
Download: ML18060A413 (2)
Vogtle Electric Generating Plant, Units 3 and 4 - Issuance of Amendment Nos. 117 and 116 Technical Specification Changes to Support Control Rod Testing in Cold Shutdown with Reactor Coolant Pumps Not in Operation (LAR 17-034)
ML18060A412
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/28/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B H
Southern Nuclear Operating Co
hoellman j/415-5481
References
EPID L-2017-LLA-0102, LAR 17-034
Download: ML18060A412 (5)