ML081550638

From kanterella
Revision as of 10:30, 12 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Response to the Transmittal of NEI 04-02, Revision 2, Guidance for Implementing a Risk-informed, Performance-based Fire Protection Program Under 10CFR50.48(c).
ML081550638
Person / Time
Issue date: 07/28/2008
From: Klein A
NRC/NRR/ADES/DRA
To: Jeffrey Riley
Nuclear Energy Institute
Moulton C, NRR/DRA, 415-2751
References
NEI 04-02, Rev 2, RG-1.205
Download: ML081550638 (2)


Text

July 28, 2008

Mr. James H. Riley, Director, Engineering Nuclear Generation Division Nuclear Energy Institute 1776 I Street, NW.

Suite 400 Washington, DC 20006-3708

SUBJECT:

RESPONSE TO THE TRANSMITTAL OF NEI 04-02, REVISION 2, "GUIDANCE FOR IMPLEMENTING A RISK-INFORMED, PERFORMANCE-BASED FIRE PROTECTION PROGRAM UNDER 10CFR50.48(c)"

Dear Mr. Riley,

On behalf of the Nuclear Regulatory Commission (NRC) I thank you for the submission of these documents for NRC review and endorsement. As you know, revision 1 of NEI 04-02 is endorsed, with exceptions, in Regulatory Guide (RG) 1.205, "Risk-Informed, Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants." We expect to review revision 2 to NEI 04-02 for endorsement, as appropriate, in RG 1.205, Revision 1. Our schedule will be defined in an update to the fire protection closure plan that will be made publicly available. If you have any questions, please contact my NFPA 805 project manager, Paul Lain, at 301-415-2346.

Sincerely, /RA/ Alexander R. Klein, P.E., Chief Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

Mr. James H. Riley, Director, Engineering Nuclear Generation Division Nuclear Energy Institute 1776 I Street, NW. Suite 400 Washington, DC 20006-3708

SUBJECT:

RESPONSE TO THE TRANSMITTAL OF NEI 04-02, REVISION 2, "GUIDANCE FOR IMPLEMENTING A RISK-INFORMED, PERFORMANCE-BASED FIRE PROTECTION PROGRAM UNDER 10CFR50.48(c)"

Dear Mr. Riley,

On behalf of the Nuclear Regulatory Commission (NRC) I thank you for the submission of these documents for NRC review and endorsement. As you know, revision 1 of NEI 04-02 is endorsed, with exceptions, in Regulatory Guide (RG) 1.205, "Risk-Informed, Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants." We expect to review revision 2 to NEI 04-02 for endorsement, as appropriate, in RG 1.205, Revision 1. Our schedule will be defined in an update to the fire protection closure plan that will be made publicly available. If you have any questions, please contact my NFPA 805 project manager, Paul Lain, at 301-415-2346.

Sincerely, /RA/ Alexander R. Klein, P.E., Chief Fire Protection Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

DISTRIBUTION

DRA R/F DFrumkin AKlein CMoulton HBarrett PLain RGallucci AFPB R/F MCunningham ADAMS Accession Number: ML081550638 OFFICE NRR/DRA/AFPB NRR/DRA/AFPB NRR/DRA/AFPB NAME CMoulton PLain A Klein DATE 06/ 04 /08 06/ 04 /08 07/ 28 /08 OFFICIAL RECORD COPY