LR-N18-0069, Revision to Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 0PSEG NuclearLLC AUG 08 2018 10 CFR 50.55a LR-N18-0069 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Generating Station Unit 1 Renewed Facility Operating License No. DPR-70 NRC Docket No. 50-272
{{#Wiki_filter:PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 0PSEG AUG 08 2018 NuclearLLC 1 0 CFR 50.55a LR-N 18-0069 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001  


==Subject:==
==Subject:==
Revision to Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval
==References:==
==References:==
Salem Generating Station Unit 1 Renewed Facility Operating License No. DPR-70 NRC Docket No. 50-272 Revision to Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval
: 1. PSEG letter to NRC, "Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval,"
: 1. PSEG letter to NRC, "Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval,"
dated January 31, 2017 (ADAMS Accession No. ML17031A278)
dated January 31, 2017 (ADAMS Accession No. ML17031A278)
: 2. NRC letter to PSEG, "Salem Nuclear Generating Station, Unit No. 1 -
: 2. NRC letter to PSEG, "Salem Nuclear Generating Station, Unit No. 1 -
Safety Evaluation of Relief Request S1-14R-160 Regarding the Fourth 10-Year Interval of the lnservice Inspection Program (CAC No.
Safety Evaluation of Relief Request S1-14R-160 Regarding the Fourth 1 0-Year Interval of the lnservice Inspection Program (CAC No.
MF9149)," dated July 17, 2017 (ADAMS Accession No. ML17172A587)
MF9149)," dated July 17, 2017 (ADAMS Accession No. ML17172A587)
In Reference 1, PSEG Nuclear LLC (PSEG) requested approval of Relief Request S1-14R-160 for Salem Unit 1. This request was approved by the NRC in Reference 2.
In Reference 1, PSEG Nuclear LLC (PSEG) requested approval of Relief Request S1-14R-160 for Salem Unit 1. This request was approved by the NRC in Reference 2.
In Relief Request S1-14R-160, PSEG requested to extend the required reactor vessel cold leg nozzle inspections by approximately six months to the Salem Unit 1 S1R26 Refueling Outage in Spring 2019. This request was proposed to align these inspection activities with the scheduled Reactor Vessel Internals Materials Reliability Program (MRP-227) and American Society of Mechanical Engineers (ASME) Section XI Reactor Vessel inspections with the core barrel removed. This would allow the cold leg nozzle inspections to be performed from the inside surface.
In Relief Request S1-14R-160, PSEG requested to extend the required reactor vessel cold leg nozzle inspections by approximately six months to the Salem Unit 1 S1 R26 Refueling Outage in Spring 2019. This request was proposed to align these inspection activities with the scheduled Reactor Vessel Internals Materials Reliability Program (MRP-227) and American Society of Mechanical Engineers (ASME) Section XI Reactor Vessel inspections with the core barrel removed. This would allow the cold leg nozzle inspections to be performed from the inside surface.
PSEG is deferring the removal of the core barrel until the S1R27 Refueling Outage in Fall 2020 outage. In January 2018, subsequent to the Reference 2 approval of the proposed six month extension, MRP-227 baffle-former bolt inspection expansion
PSEG is deferring the removal of the core barrel until the S1 R27 Refueling Outage in Fall 2020 outage. In January 2018, subsequent to the Reference 2 approval of the proposed six month extension, MRP-227 baffle-former bolt inspection expansion  


AUG 06'2018 LR-N18-0069                                                             10 CFR 50.55a Page 2 guidance was issued. Deferring the removal of the core barrel provides PSEG the time to prepare for the required MRP-227 barrel-former bolt expansion inspections. The ASME Section XI Reactor Vessel Weld examinations were originally planned to be performed in the S1R27 refueling outage and were pulled up one outage to the S1R26 refueling outage to align with the removal of the core barrel. Therefore deferring the removal of the core barrel to S1R27 does not impact the required completion schedule for the ASME Section XI Reactor Vessel Weld examinations.
AUG 06'2018 LR-N 18-0069 Page 2 10 CFR 50.55a guidance was issued. Deferring the removal of the core barrel provides PSEG the time to prepare for the required MRP-227 barrel-former bolt expansion inspections. The ASME Section XI Reactor Vessel Weld examinations were originally planned to be performed in the S1 R27 refueling outage and were pulled up one outage to the S1 R26 refueling outage to align with the removal of the core barrel. Therefore deferring the removal of the core barrel to S1 R27 does not impact the required completion schedule for the ASME Section XI Reactor Vessel Weld examinations.
In accordance with 10 CFR 50.55a, "Codes and standards, " PSEG hereby requests NRC approval of Revision 1 of Relief Request S1-14R-160 for Salem Unit 1. PSEG proposes to extend the required reactor vessel cold leg nozzle inspection by approximately 24-months to the Salem Unit 1 S1R27 Refueling Outage in Fall 2020.
In accordance with 10 CFR 50.55a, "Codes and standards," PSEG hereby requests NRC approval of Revision 1 of Relief Request S1-14R-160 for Salem Unit 1. PSEG proposes to extend the required reactor vessel cold leg nozzle inspection by approximately 24-months to the Salem Unit 1 S1 R27 Refueling Outage in Fall 2020.
This will align these examination activities with the revised schedule for removal of the core barrel, allowing these examinations to be performed from the inside surface.
This will align these examination activities with the revised schedule for removal of the core barrel, allowing these examinations to be performed from the inside surface.
PSEG requests approval of the proposed request by April 6, 2019 to align with the start of Unit 1 refueling outage S1R26 when the subject examinations would be required to be performed in accordance with approved Relief Request S1-14R-160.
PSEG requests approval of the proposed request by April 6, 2019 to align with the start of Unit 1 refueling outage S1 R26 when the subject examinations would be required to be performed in accordance with approved Relief Request S1-14R-160.
Relief Request S1- 14R-160 Revision 1 applies to the Unit 1 Fourth lnservice Inspection Interval which began on May 20, 2011 and is scheduled to end on December 31, 2020.
Relief Request S1-14R-160 Revision 1 applies to the Unit 1 Fourth lnservice Inspection Interval which began on May 20, 2011 and is scheduled to end on December 31, 2020.
The Code of Record for the Salem Unit 1 Fourth 10-Year lnservice Inspection Interval is the ASME Code, Section XI, 2004 Edition. The proposed relief request revision is provided in Attachment 1.
The Code of Record for the Salem Unit 1 Fourth 1 0-Year lnservice Inspection Interval is the ASME Code, Section XI, 2004 Edition. The proposed relief request revision is provided in Attachment 1.
There are no regulatory commitments contained in this letter.
There are no regulatory commitments contained in this letter.
Should you have any questions concerning this matter, please contact Mr. Brian Thomas at 856-339-2022.
Should you have any questions concerning this matter, please contact Mr. Brian Thomas at 856-339-2022.  
e:e C- 4 Paul R. Duke, Jr.
e:e C-Paul R. Duke, Jr. 4 Manager - Licensing PSEG Nuclear LLC :
Manager - Licensing PSEG Nuclear LLC :         1 OCFR 50.55a Relief Request S1-14R-160, Revision 1 cc:   Administrator, Region I, NRC NRC Senior Resident Inspector, Salem J. Kim, Project Manager, Salem, USNRC P. Mulligan, Chief, NJBNE L. Marabella, Corporate Commitment Tracking Coordinator T. Cachaza, Salem Commitment Tracking Coordinator
1 OCFR 50.55a Relief Request S1-14R-160, Revision 1 cc:
Administrator, Region I, NRC NRC Senior Resident Inspector, Salem J. Kim, Project Manager, Salem, USNRC P. Mulligan, Chief, NJBNE L. Marabella, Corporate Commitment Tracking Coordinator T. Cachaza, Salem Commitment Tracking Coordinator  


LR-N18-0069                           10 CFR 50.55a Page 3 bee: Manager - Salem Programs Director - Regulatory Compliance Salem lSI Program Owner Corporate lSI Program Owner Records Management
LR-N 18-0069 Page 3 bee:
Manager - Salem Programs Director - Regulatory Compliance Salem lSI Program Owner Corporate lSI Program Owner Records Management 10 CFR 50.55a


LR-N 18-0069 Attachment 1 10CFR 50.55a Relief Request S1- 14R-160, Revision 1 LR-N18-0069 Salem Nuclear Generating Station, Unit No. 1 Renewed Facility Operating License No. DPR-70 NRC Docket No. 50-272 10 CFR 50.55a Request S1-14R-160, Revision 1 Hardship in Accordance with 10 CFR 50.55a(z)(2)
LR-N 18-0069 10CFR 50.55a Relief Request S1-14R-160, Revision 1 LR-N 18-0069 Salem Nuclear Generating Station, Unit No. 1 Renewed Facility Operating License No. DPR-70 NRC Docket No. 50-272 10 CFR 50.55a Request S1-14R-160, Revision 1 Hardship in Accordance with 10 CFR 50.55a(z)(2)
Hardship Without a Compensating Increase in Quality and Safety
Hardship Without a Compensating Increase in Quality and Safety
: 1. ASME Code Component(s) Affected Code Class:                       1 Examination Category:             Code Case N-770-2 Item Number:                     Inspection Item D
: 1. ASME Code Component(s) Affected Code Class:
Examination Category:
Item Number:  


== Description:==
==
Reactor Pressure Vessel (RPV) Cold Leg Nozzle to Safe-End Alloy 600 Welds:
Description:==
Loop 11- 27.5-RC-1110-5 Loop 12 - 27.5-RC-1120-5 Loop 13- 27.5-RC-1130-5 Loop 14 - 27.5-RC-1140-5
1 Code Case N-770-2 Inspection Item D Reactor Pressure Vessel (RPV) Cold Leg Nozzle to Safe-End Alloy 600 Welds:
Loop 11-27.5-RC-1110-5 Loop 12 - 27.5-RC-1120-5 Loop 13-27.5-RC-1130-5 Loop 14 - 27.5-RC-1140-5  


===2. Applicable Code Edition and Addenda===
===2. Applicable Code Edition and Addenda===
Code Case N-770-2 as referenced in 10 CFR 50.55a(g)(6)(ii)(F).
Code Case N-770-2 as referenced in 10 CFR 50.55a(g)(6)(ii)(F).
American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for l nservice Inspection and Testing of Components of Light-Water Cooled Plants," 2004 Edition with no Addenda.
American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for lnservice Inspection and Testing of Components of Light-Water Cooled Plants," 2004 Edition with no Addenda.
For Unit 1 the Fourth 10-Year Interval began on May 20, 2011 and is scheduled to end on December 31, 2020.
For Unit 1 the Fourth 10-Year Interval began on May 20, 2011 and is scheduled to end on December 31, 2020.  


===3. Applicable Code Requirement===
===3. Applicable Code Requirement===
10 CFR 50.55a(g)(6)(ii)(F) requires licensees of existing, operating pressurized-water reactors as of August 17, 2017, to implement the requirements of ASME Code Case N-770-2, subject to the conditions specified in paragraphs (g)(6)(ii)(F)(2) through (13). Table 1 of Code Case N-770-2 requires volumetric examination of all Item D welds (uncracked butt welds mitigated with stress improvement) no sooner than the third refueling outage and no later than 10 years following stress improvement application.
10 CFR 50.55a(g)(6)(ii)(F) requires licensees of existing, operating pressurized-water reactors as of August 17, 2017, to implement the requirements of ASME Code Case N-770-2, subject to the conditions specified in paragraphs (g)(6)(ii)(F)(2) through (13). Table 1 of Code Case N-770-2 requires volumetric examination of all Item D welds (uncracked butt welds mitigated with stress improvement) no sooner than the third refueling outage and no later than 10 years following stress improvement application.
Salem Unit 1 performed the mechanical stress improvement process (MSIP) on the four RPV Cold Leg Nozzle to Safe-End Alloy 600 welds subject to this relief request. The pre-MSIP and post-MSIP weld volumetric examinations were completed with no recordable flaws. Therefore these welds are classified as Item D welds in accordance with ASME Code Case N-770-2.
Salem Unit 1 performed the mechanical stress improvement process (MSIP) on the four RPV Cold Leg Nozzle to Safe-End Alloy 600 welds subject to this relief request. The pre-MSIP and post-MSIP weld volumetric examinations were completed with no recordable flaws. Therefore these welds are classified as Item D welds in accordance with ASME Code Case N-770-2.
Page 1 of 5 LR-N18-0069 The MSIP application was performed in the Fall 2008 refueling outage. This would have required the examinations to be completed in the Salem Unit 1 S1R25 refueling outage in the Fall of 2017 since the S1R26 refueling outage in the Spring of 2019 would be 6 months beyond the 10-year Inspection Interval. PSEG requested and was granted relief on July 17, 2017 to extend the inspections by 6 months until the Spring 2019 refueling outage.
Page 1 of 5 LR-N 18-0069 The MSIP application was performed in the Fall 2008 refueling outage. This would have required the examinations to be completed in the Salem Unit 1 S1 R25 refueling outage in the Fall of 2017 since the S1 R26 refueling outage in the Spring of 2019 would be 6 months beyond the 1 0-year Inspection Interval. PSEG requested and was granted relief on July 17, 2017 to extend the inspections by 6 months until the Spring 2019 refueling outage.  


===4. Reason for Request===
===4. Reason for Request===
PSEG is requesting a one-time 24-month extension to the 10-year inspection interval required by Table 1 of Code Case N-770-2, for Item     0 uncracked butt welds mitigated with stress improvement. This interval extension is being requested in accordance with 10 CFR 50.55a(z)(2) as a hardship without a compensating increase in quality and safety.
PSEG is requesting a one-time 24-month extension to the 1 0-year inspection interval required by Table 1 of Code Case N-770-2, for Item 0 uncracked butt welds mitigated with stress improvement. This interval extension is being requested in accordance with 10 CFR 50.55a(z)(2) as a hardship without a compensating increase in quality and safety.
The 24-month extension would allow the four RPV Cold Leg Nozzle to Safe End weld volumetric examinations to be performed in Unit 1 refueling outage (S1R27) in the Fall of 2020. This would align the RPV Cold Leg nozzle to Safe-End weld volumetric examinations with the Reactor Vessel Internals Materials Reliability Program (MRP-227) and ASME Section XI RPV examinations with the core barrel removed. This would allow the volumetric examination of the RPV Cold Leg Nozzle to Safe-End welds from the inside surface   (10) when the core barrel is currently scheduled to be removed.
The 24-month extension would allow the four RPV Cold Leg Nozzle to Safe End weld volumetric examinations to be performed in Unit 1 refueling outage (S1 R27) in the Fall of 2020. This would align the RPV Cold Leg nozzle to Safe-End weld volumetric examinations with the Reactor Vessel Internals Materials Reliability Program (MRP-227) and ASME Section XI RPV examinations with the core barrel removed. This would allow the volumetric examination of the RPV Cold Leg Nozzle to Safe-End welds from the inside surface (10) when the core barrel is currently scheduled to be removed.
Performance of the RPV Cold Leg Nozzle to Safe-End welds in the S 1R26 refueling outage in the Spring of 2019 would require the examinations to be performed from the outside surface     (00) of the pipe since the core barrel removal has been moved to the S1 R27 refueling outage.
Performance of the RPV Cold Leg Nozzle to Safe-End welds in the S 1 R26 refueling outage in the Spring of 2019 would require the examinations to be performed from the outside surface (00) of the pipe since the core barrel removal has been moved to the S1 R27 refueling outage.
Previous examinations of the RPV Cold Leg Nozzle to Safe-End Alloy 600 welds have been performed from the outside surface of the pipe     (00) at Salem Unit 1. Access to the   00 of these welds is inside a "sandbox" which was installed during original plant construction after all welding was completed. Although these examinations can be performed from the         00 of the cold leg nozzles for Salem Unit 1, this inspection activity would result in the unnecessary personnel radiation exposure for the personnel performing these examinations without a compensating increase in quality or safety as discussed below.
Previous examinations of the RPV Cold Leg Nozzle to Safe-End Alloy 600 welds have been performed from the outside surface of the pipe (00) at Salem Unit 1. Access to the 00 of these welds is inside a "sandbox" which was installed during original plant construction after all welding was completed. Although these examinations can be performed from the 00 of the cold leg nozzles for Salem Unit 1, this inspection activity would result in the unnecessary personnel radiation exposure for the personnel performing these examinations without a compensating increase in quality or safety as discussed below.
Based upon a review of dose records for similar RPV Cold Leg Nozzle to Safe-End weld volumetric examinations performed from the       00 for most recent inservice inspections at Salem Unit 2, the dose exposure to personnel performing the NOE of four RPV Cold Leg Nozzle to Safe-End weld volumetric examinations was approximately 3.5 REM. This is a conservative estimate of the personnel exposure since it does not include any additional dose received by supporting organizations (i.e. , maintenance, radiation protection). Performing the inspections from the 10 during the Fall 2020 Page 2 of 5 LR-N18-0069 refueling outage reduces the overall exposure of the weld examinations since this inspection technique is performed remotely and does not require personnel to access the exterior "sandbox" area of the RPV.
Based upon a review of dose records for similar RPV Cold Leg Nozzle to Safe-End weld volumetric examinations performed from the 00 for most recent inservice inspections at Salem Unit 2, the dose exposure to personnel performing the NOE of four RPV Cold Leg Nozzle to Safe-End weld volumetric examinations was approximately 3.5 REM. This is a conservative estimate of the personnel exposure since it does not include any additional dose received by supporting organizations (i.e., maintenance, radiation protection). Performing the inspections from the 10 during the Fall 2020 Page 2 of 5 LR-N 18-0069 refueling outage reduces the overall exposure of the weld examinations since this inspection technique is performed remotely and does not require personnel to access the exterior "sandbox" area of the RPV.
During the Fall 2008 refueling outage for Salem Unit 1, PSEG performed MSIP of both the RPV hot leg and cold leg nozzle to Safe-End alloy 600 welds. Pre-MSIP volumetric examinations of the four RPV Cold Leg Nozzle to Safe-End welds and post-MSIP volumetric examinations were performed.
During the Fall 2008 refueling outage for Salem Unit 1, PSEG performed MSIP of both the RPV hot leg and cold leg nozzle to Safe-End alloy 600 welds. Pre-MSIP volumetric examinations of the four RPV Cold Leg Nozzle to Safe-End welds and post-MSIP volumetric examinations were performed.
The volumetric ultrasonic examination met ASME Section XI, Appendix VIII requirements, including examination volume of essentially 100%. The pre MSIP and post-MSIP examinations identified no flaws in the four RPV Cold Leg Nozzle to Safe-End welds. The post MSIP weld examinations were the pre-service baseline examinations for these Code Case N-770-2 Inspection Item D welds (MRP-139 requirements at that time).
The volumetric ultrasonic examination met ASME Section XI, Appendix VIII requirements, including examination volume of essentially 1 00%. The pre MSIP and post-MSIP examinations identified no flaws in the four RPV Cold Leg Nozzle to Safe-End welds. The post MSIP weld examinations were the pre-service baseline examinations for these Code Case N-770-2 Inspection Item D welds (MRP-139 requirements at that time).
NUREG/CR-7187, "Managing PWSCC in Butt Weld by Mitigation and Inspection," discusses the management of Primary Water Stress Corrosion Cracking (PWSCC) by MSIP in Section 4. Section 4.4 of NUREG/CR-7187 assessed the effectiveness of MSIP for mitigating PWSCC and states at the end, " ... it is reasonable to conclude that MSIP provides effective mitigation against the initiation of PWSCC and against the growth of any existing PWSCC that has been detected and allowed to remain in service." Section 4.5 of NUREG/CR-7187 performed an assessment of the Code Case N-770-1 inspection requirements and acknowledged that inspection of MSIP welds serves a defense-in-depth monitoring function rather than a degradation management function.
NUREG/CR-7187, "Managing PWSCC in Butt Weld by Mitigation and Inspection," discusses the management of Primary Water Stress Corrosion Cracking (PWSCC) by MSIP in Section 4. Section 4.4 of NUREG/CR-7187 assessed the effectiveness of MSIP for mitigating PWSCC and states at the end, "... it is reasonable to conclude that MSIP provides effective mitigation against the initiation of PWSCC and against the growth of any existing PWSCC that has been detected and allowed to remain in service." Section 4.5 of NUREG/CR-7187 performed an assessment of the Code Case N-770-1 inspection requirements and acknowledged that inspection of MSIP welds serves a defense-in-depth monitoring function rather than a degradation management function.
Since the Salem Unit 1 RPV Cold Leg Nozzle to Safe-End welds have been mitigated by the application of MSIP and were ultrasonically examined without the detection of any flaws, the subsequent ultrasonic examination of these welds is considered as defense-in-depth monitoring and not for the management of PWSCC degradation. Extending the inspection interval 24-months will continue to provide an adequate level of quality and safety. The inspection of the four RPV Cold Leg Nozzle to Safe-End welds will be performed during the Fall 2020 refueling outage.
Since the Salem Unit 1 RPV Cold Leg Nozzle to Safe-End welds have been mitigated by the application of MSIP and were ultrasonically examined without the detection of any flaws, the subsequent ultrasonic examination of these welds is considered as defense-in-depth monitoring and not for the management of PWSCC degradation. Extending the inspection interval 24-months will continue to provide an adequate level of quality and safety. The inspection of the four RPV Cold Leg Nozzle to Safe-End welds will be performed during the Fall 2020 refueling outage.
PSEG believes that imposition of the 1 0-year inspection interval would create a hardship in that personnel would unnecessarily receive additional radiation exposure, in the order of 3.5 REM, if the examinations were performed during the Spring 2019 refueling outage, without an increase in quality or safety as discussed above.
PSEG believes that imposition of the 1 0-year inspection interval would create a hardship in that personnel would unnecessarily receive additional radiation exposure, in the order of 3.5 REM, if the examinations were performed during the Spring 2019 refueling outage, without an increase in quality or safety as discussed above.
Page 3 of 5 LR-N18-0069
Page 3 of 5 LR-N18-0069  
: 5. Proposed Alternative and Basis for Use 10CFR50.55a(z)states:
 
    "Alternatives to codes and standards requirements. Alternatives to the requirements of paragraphs (b) through (h) of this section or portions thereof may be used when authorized by the Director, Office of Nuclear Reactor Regulation, or Director, Office of New Reactors, as appropriate. A proposed alternative must be submitted and authorized prior to implementation. The applicant or licensee must demonstrate that:
===5. Proposed Alternative and Basis for Use===
(1) Acceptable level of quality and safety. The proposed alternative would provide an acceptable level of quality and safety; or (2) Hardship without a compensating increase in quality and safety.
1 OCFR50.55a(z)states:  
"Alternatives to codes and standards requirements. Alternatives to the requirements of paragraphs (b) through (h) of this section or portions thereof may be used when authorized by the Director, Office of Nuclear Reactor Regulation, or Director, Office of New Reactors, as appropriate. A proposed alternative must be submitted and authorized prior to implementation. The applicant or licensee must demonstrate that:
( 1) Acceptable level of quality and safety. The proposed alternative would provide an acceptable level of quality and safety; or (2) Hardship without a compensating increase in quality and safety.
Compliance with the specified requirements of this section would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety."
Compliance with the specified requirements of this section would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety."
PSEG is requesting a one-time 24-month extension to the 10-year volumetric examination interval required by Table 1 of Code Case N-770-2 for Item D (uncracked butt welds mitigated with stress improvement). This interval extension is being requested in accordance with 10CFR50.55a(z)(2) as a hardship without a compensating increase in quality and safety.
PSEG is requesting a one-time 24-month extension to the 1 0-year volumetric examination interval required by Table 1 of Code Case N-770-2 for Item D (uncracked butt welds mitigated with stress improvement). This interval extension is being requested in accordance with 1 OCFR50.55a(z)(2) as a hardship without a compensating increase in quality and safety.
PSEG believes that imposition of the 10-year inspection interval would create a hardship in that personnel would unnecessarily receive additional radiation exposure, in the order of 3.5 REM, if the volumetric examinations were performed during the Spring 2019 refueling outage from the 00, without an increase in quality or safety as discussed in section 4 of this relief request.
PSEG believes that imposition of the 1 0-year inspection interval would create a hardship in that personnel would unnecessarily receive additional radiation exposure, in the order of 3.5 REM, if the volumetric examinations were performed during the Spring 2019 refueling outage from the 00, without an increase in quality or safety as discussed in section 4 of this relief request.
The inspection of the four RPV Cold Leg Nozzle to Safe-End welds will be performed during the Fall 2020 refueling outage.
The inspection of the four RPV Cold Leg Nozzle to Safe-End welds will be performed during the Fall 2020 refueling outage.  
: 6. Duration of Proposed Alternative The duration of the request for proposed alternative for Salem Unit 1 is through the Fall 2020 refueling outage, S1R27.
 
: 7. Precedents Relief requests have been previously approved by the NRC for extension of Code Case N-770-1 & 2 inspection intervals up to 36-months beyond the required interval as listed below; however, the precedents listed below are for Item 8 unmitigated butt welds as opposed to Item D uncracked butt welds mitigated with stress improvement.
===6. Duration of Proposed Alternative===
Page 4 of 5 LR-N18-0069
The duration of the request for proposed alternative for Salem Unit 1 is through the Fall 2020 refueling outage, S1 R27.  
: a. NRC letter to Luminant Generation Company LLC, "Comanche Peak Nuclear Power Plant, Unit 1 - Relief Request 183-3, Alternative to the ASME Code, Section XI, Examination Requirements for Reactor Pressure Vessel Cold-Leg Weld Inspection Frequency (CAC No. MF6125), " dated March 14, 2016 (ADAMS Accession No. ML16074A001)
 
===7. Precedents===
Relief requests have been previously approved by the NRC for extension of Code Case N-770-1 & 2 inspection intervals up to 36-months beyond the required interval as listed below; however, the precedents listed below are for Item 8 unmitigated butt welds as opposed to Item D uncracked butt welds mitigated with stress improvement.
Page 4 of 5 LR-N 18-0069
: a. NRC letter to Luminant Generation Company LLC, "Comanche Peak Nuclear Power Plant, Unit 1 - Relief Request 183-3, Alternative to the ASME Code, Section XI, Examination Requirements for Reactor Pressure Vessel Cold-Leg Weld Inspection Frequency (CAC No. MF6125)," dated March 14, 2016 (ADAMS Accession No. ML16074A001)
: b. NRC Letter to Entergy Nuclear Operations, "Indian Point Nuclear Generating Unit No. 3 - Safety Evaluation for Relief Request IP3-ISI-RR-07 for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations (TAC No. MF3346),11 dated August 4, 2014 (ADAMS Accession No. ML14199A444)
: b. NRC Letter to Entergy Nuclear Operations, "Indian Point Nuclear Generating Unit No. 3 - Safety Evaluation for Relief Request IP3-ISI-RR-07 for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations (TAC No. MF3346),11 dated August 4, 2014 (ADAMS Accession No. ML14199A444)
: c. NRC Letter to Duke Energy Carolinas LLC, "Oconee Nuclear Station, Units 1 and 2- Safety Evaluation for Relief Request No. 17-ON-001 (EPID L-2017-LLR-0099), " dated April 13, 2018 (ADAMS Accession No. ML18100A005)
: c. NRC Letter to Duke Energy Carolinas LLC, "Oconee Nuclear Station, Units 1 and 2 - Safety Evaluation for Relief Request No. 17 -ON-001 (EPID L-2017-LLR-0099)," dated April 13, 2018 (ADAMS Accession No. ML18100A005)
: 8. References
: 8. References
: 1) Regulatory Guide 1.147, 11lnservice Inspection Code Case Acceptability, ASME Section XI, Division 1, .. Revision 18 dated March 2017
: 1) Regulatory Guide 1.147, 11lnservice Inspection Code Case Acceptability, ASME Section XI, Division 1,.. Revision 18 dated March 2017
: 2) Code Case N-770-2, 'lternative Examination Requirements and Acceptance Standards for Class 1 PWR Piping and Vessel Nozzle Butt Welds Fabricated with UNS N06082 or UNS W86182 Weld Filler Material With or Without Application of Listed Mitigation Activities Section XI, Division 1."
: 2) Code Case N-770-2, '¶lternative Examination Requirements and Acceptance Standards for Class 1 PWR Piping and Vessel Nozzle Butt Welds Fabricated with UNS N06082 or UNS W86182 Weld Filler Material With or Without Application of Listed Mitigation Activities Section XI, Division 1."
: 3) NUREG/CR-7187, "Managing PWSCC in Butt Welds by Mitigation and Inspection," November 2014 Page 5 of 5}}
: 3) NUREG/CR-7187, "Managing PWSCC in Butt Welds by Mitigation and Inspection," November 2014 Page 5 of 5}}

Latest revision as of 15:48, 5 January 2025

Revision to Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval
ML18218A481
Person / Time
Site: Salem 
Issue date: 08/06/2018
From: Duke P
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N18-0069
Download: ML18218A481 (9)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 0PSEG AUG 08 2018 NuclearLLC 1 0 CFR 50.55a LR-N 18-0069 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

References:

Salem Generating Station Unit 1 Renewed Facility Operating License No. DPR-70 NRC Docket No. 50-272 Revision to Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval

1. PSEG letter to NRC, "Request for One-Time Relief for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations Inspection Interval,"

dated January 31, 2017 (ADAMS Accession No. ML17031A278)

2. NRC letter to PSEG, "Salem Nuclear Generating Station, Unit No. 1 -

Safety Evaluation of Relief Request S1-14R-160 Regarding the Fourth 1 0-Year Interval of the lnservice Inspection Program (CAC No.

MF9149)," dated July 17, 2017 (ADAMS Accession No. ML17172A587)

In Reference 1, PSEG Nuclear LLC (PSEG) requested approval of Relief Request S1-14R-160 for Salem Unit 1. This request was approved by the NRC in Reference 2.

In Relief Request S1-14R-160, PSEG requested to extend the required reactor vessel cold leg nozzle inspections by approximately six months to the Salem Unit 1 S1 R26 Refueling Outage in Spring 2019. This request was proposed to align these inspection activities with the scheduled Reactor Vessel Internals Materials Reliability Program (MRP-227) and American Society of Mechanical Engineers (ASME)Section XI Reactor Vessel inspections with the core barrel removed. This would allow the cold leg nozzle inspections to be performed from the inside surface.

PSEG is deferring the removal of the core barrel until the S1 R27 Refueling Outage in Fall 2020 outage. In January 2018, subsequent to the Reference 2 approval of the proposed six month extension, MRP-227 baffle-former bolt inspection expansion

AUG 06'2018 LR-N 18-0069 Page 2 10 CFR 50.55a guidance was issued. Deferring the removal of the core barrel provides PSEG the time to prepare for the required MRP-227 barrel-former bolt expansion inspections. The ASME Section XI Reactor Vessel Weld examinations were originally planned to be performed in the S1 R27 refueling outage and were pulled up one outage to the S1 R26 refueling outage to align with the removal of the core barrel. Therefore deferring the removal of the core barrel to S1 R27 does not impact the required completion schedule for the ASME Section XI Reactor Vessel Weld examinations.

In accordance with 10 CFR 50.55a, "Codes and standards," PSEG hereby requests NRC approval of Revision 1 of Relief Request S1-14R-160 for Salem Unit 1. PSEG proposes to extend the required reactor vessel cold leg nozzle inspection by approximately 24-months to the Salem Unit 1 S1 R27 Refueling Outage in Fall 2020.

This will align these examination activities with the revised schedule for removal of the core barrel, allowing these examinations to be performed from the inside surface.

PSEG requests approval of the proposed request by April 6, 2019 to align with the start of Unit 1 refueling outage S1 R26 when the subject examinations would be required to be performed in accordance with approved Relief Request S1-14R-160.

Relief Request S1-14R-160 Revision 1 applies to the Unit 1 Fourth lnservice Inspection Interval which began on May 20, 2011 and is scheduled to end on December 31, 2020.

The Code of Record for the Salem Unit 1 Fourth 1 0-Year lnservice Inspection Interval is the ASME Code,Section XI, 2004 Edition. The proposed relief request revision is provided in Attachment 1.

There are no regulatory commitments contained in this letter.

Should you have any questions concerning this matter, please contact Mr. Brian Thomas at 856-339-2022.

e:e C-Paul R. Duke, Jr. 4 Manager - Licensing PSEG Nuclear LLC :

1 OCFR 50.55a Relief Request S1-14R-160, Revision 1 cc:

Administrator, Region I, NRC NRC Senior Resident Inspector, Salem J. Kim, Project Manager, Salem, USNRC P. Mulligan, Chief, NJBNE L. Marabella, Corporate Commitment Tracking Coordinator T. Cachaza, Salem Commitment Tracking Coordinator

LR-N 18-0069 Page 3 bee:

Manager - Salem Programs Director - Regulatory Compliance Salem lSI Program Owner Corporate lSI Program Owner Records Management 10 CFR 50.55a

LR-N 18-0069 10CFR 50.55a Relief Request S1-14R-160, Revision 1 LR-N 18-0069 Salem Nuclear Generating Station, Unit No. 1 Renewed Facility Operating License No. DPR-70 NRC Docket No. 50-272 10 CFR 50.55a Request S1-14R-160, Revision 1 Hardship in Accordance with 10 CFR 50.55a(z)(2)

Hardship Without a Compensating Increase in Quality and Safety

1. ASME Code Component(s) Affected Code Class:

Examination Category:

Item Number:

==

Description:==

1 Code Case N-770-2 Inspection Item D Reactor Pressure Vessel (RPV) Cold Leg Nozzle to Safe-End Alloy 600 Welds:

Loop 11-27.5-RC-1110-5 Loop 12 - 27.5-RC-1120-5 Loop 13-27.5-RC-1130-5 Loop 14 - 27.5-RC-1140-5

2. Applicable Code Edition and Addenda

Code Case N-770-2 as referenced in 10 CFR 50.55a(g)(6)(ii)(F).

American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, "Rules for lnservice Inspection and Testing of Components of Light-Water Cooled Plants," 2004 Edition with no Addenda.

For Unit 1 the Fourth 10-Year Interval began on May 20, 2011 and is scheduled to end on December 31, 2020.

3. Applicable Code Requirement

10 CFR 50.55a(g)(6)(ii)(F) requires licensees of existing, operating pressurized-water reactors as of August 17, 2017, to implement the requirements of ASME Code Case N-770-2, subject to the conditions specified in paragraphs (g)(6)(ii)(F)(2) through (13). Table 1 of Code Case N-770-2 requires volumetric examination of all Item D welds (uncracked butt welds mitigated with stress improvement) no sooner than the third refueling outage and no later than 10 years following stress improvement application.

Salem Unit 1 performed the mechanical stress improvement process (MSIP) on the four RPV Cold Leg Nozzle to Safe-End Alloy 600 welds subject to this relief request. The pre-MSIP and post-MSIP weld volumetric examinations were completed with no recordable flaws. Therefore these welds are classified as Item D welds in accordance with ASME Code Case N-770-2.

Page 1 of 5 LR-N 18-0069 The MSIP application was performed in the Fall 2008 refueling outage. This would have required the examinations to be completed in the Salem Unit 1 S1 R25 refueling outage in the Fall of 2017 since the S1 R26 refueling outage in the Spring of 2019 would be 6 months beyond the 1 0-year Inspection Interval. PSEG requested and was granted relief on July 17, 2017 to extend the inspections by 6 months until the Spring 2019 refueling outage.

4. Reason for Request

PSEG is requesting a one-time 24-month extension to the 1 0-year inspection interval required by Table 1 of Code Case N-770-2, for Item 0 uncracked butt welds mitigated with stress improvement. This interval extension is being requested in accordance with 10 CFR 50.55a(z)(2) as a hardship without a compensating increase in quality and safety.

The 24-month extension would allow the four RPV Cold Leg Nozzle to Safe End weld volumetric examinations to be performed in Unit 1 refueling outage (S1 R27) in the Fall of 2020. This would align the RPV Cold Leg nozzle to Safe-End weld volumetric examinations with the Reactor Vessel Internals Materials Reliability Program (MRP-227) and ASME Section XI RPV examinations with the core barrel removed. This would allow the volumetric examination of the RPV Cold Leg Nozzle to Safe-End welds from the inside surface (10) when the core barrel is currently scheduled to be removed.

Performance of the RPV Cold Leg Nozzle to Safe-End welds in the S 1 R26 refueling outage in the Spring of 2019 would require the examinations to be performed from the outside surface (00) of the pipe since the core barrel removal has been moved to the S1 R27 refueling outage.

Previous examinations of the RPV Cold Leg Nozzle to Safe-End Alloy 600 welds have been performed from the outside surface of the pipe (00) at Salem Unit 1. Access to the 00 of these welds is inside a "sandbox" which was installed during original plant construction after all welding was completed. Although these examinations can be performed from the 00 of the cold leg nozzles for Salem Unit 1, this inspection activity would result in the unnecessary personnel radiation exposure for the personnel performing these examinations without a compensating increase in quality or safety as discussed below.

Based upon a review of dose records for similar RPV Cold Leg Nozzle to Safe-End weld volumetric examinations performed from the 00 for most recent inservice inspections at Salem Unit 2, the dose exposure to personnel performing the NOE of four RPV Cold Leg Nozzle to Safe-End weld volumetric examinations was approximately 3.5 REM. This is a conservative estimate of the personnel exposure since it does not include any additional dose received by supporting organizations (i.e., maintenance, radiation protection). Performing the inspections from the 10 during the Fall 2020 Page 2 of 5 LR-N 18-0069 refueling outage reduces the overall exposure of the weld examinations since this inspection technique is performed remotely and does not require personnel to access the exterior "sandbox" area of the RPV.

During the Fall 2008 refueling outage for Salem Unit 1, PSEG performed MSIP of both the RPV hot leg and cold leg nozzle to Safe-End alloy 600 welds. Pre-MSIP volumetric examinations of the four RPV Cold Leg Nozzle to Safe-End welds and post-MSIP volumetric examinations were performed.

The volumetric ultrasonic examination met ASME Section XI, Appendix VIII requirements, including examination volume of essentially 1 00%. The pre MSIP and post-MSIP examinations identified no flaws in the four RPV Cold Leg Nozzle to Safe-End welds. The post MSIP weld examinations were the pre-service baseline examinations for these Code Case N-770-2 Inspection Item D welds (MRP-139 requirements at that time).

NUREG/CR-7187, "Managing PWSCC in Butt Weld by Mitigation and Inspection," discusses the management of Primary Water Stress Corrosion Cracking (PWSCC) by MSIP in Section 4. Section 4.4 of NUREG/CR-7187 assessed the effectiveness of MSIP for mitigating PWSCC and states at the end, "... it is reasonable to conclude that MSIP provides effective mitigation against the initiation of PWSCC and against the growth of any existing PWSCC that has been detected and allowed to remain in service." Section 4.5 of NUREG/CR-7187 performed an assessment of the Code Case N-770-1 inspection requirements and acknowledged that inspection of MSIP welds serves a defense-in-depth monitoring function rather than a degradation management function.

Since the Salem Unit 1 RPV Cold Leg Nozzle to Safe-End welds have been mitigated by the application of MSIP and were ultrasonically examined without the detection of any flaws, the subsequent ultrasonic examination of these welds is considered as defense-in-depth monitoring and not for the management of PWSCC degradation. Extending the inspection interval 24-months will continue to provide an adequate level of quality and safety. The inspection of the four RPV Cold Leg Nozzle to Safe-End welds will be performed during the Fall 2020 refueling outage.

PSEG believes that imposition of the 1 0-year inspection interval would create a hardship in that personnel would unnecessarily receive additional radiation exposure, in the order of 3.5 REM, if the examinations were performed during the Spring 2019 refueling outage, without an increase in quality or safety as discussed above.

Page 3 of 5 LR-N18-0069

5. Proposed Alternative and Basis for Use

1 OCFR50.55a(z)states:

"Alternatives to codes and standards requirements. Alternatives to the requirements of paragraphs (b) through (h) of this section or portions thereof may be used when authorized by the Director, Office of Nuclear Reactor Regulation, or Director, Office of New Reactors, as appropriate. A proposed alternative must be submitted and authorized prior to implementation. The applicant or licensee must demonstrate that:

( 1) Acceptable level of quality and safety. The proposed alternative would provide an acceptable level of quality and safety; or (2) Hardship without a compensating increase in quality and safety.

Compliance with the specified requirements of this section would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety."

PSEG is requesting a one-time 24-month extension to the 1 0-year volumetric examination interval required by Table 1 of Code Case N-770-2 for Item D (uncracked butt welds mitigated with stress improvement). This interval extension is being requested in accordance with 1 OCFR50.55a(z)(2) as a hardship without a compensating increase in quality and safety.

PSEG believes that imposition of the 1 0-year inspection interval would create a hardship in that personnel would unnecessarily receive additional radiation exposure, in the order of 3.5 REM, if the volumetric examinations were performed during the Spring 2019 refueling outage from the 00, without an increase in quality or safety as discussed in section 4 of this relief request.

The inspection of the four RPV Cold Leg Nozzle to Safe-End welds will be performed during the Fall 2020 refueling outage.

6. Duration of Proposed Alternative

The duration of the request for proposed alternative for Salem Unit 1 is through the Fall 2020 refueling outage, S1 R27.

7. Precedents

Relief requests have been previously approved by the NRC for extension of Code Case N-770-1 & 2 inspection intervals up to 36-months beyond the required interval as listed below; however, the precedents listed below are for Item 8 unmitigated butt welds as opposed to Item D uncracked butt welds mitigated with stress improvement.

Page 4 of 5 LR-N 18-0069

a. NRC letter to Luminant Generation Company LLC, "Comanche Peak Nuclear Power Plant, Unit 1 - Relief Request 183-3, Alternative to the ASME Code,Section XI, Examination Requirements for Reactor Pressure Vessel Cold-Leg Weld Inspection Frequency (CAC No. MF6125)," dated March 14, 2016 (ADAMS Accession No. ML16074A001)
b. NRC Letter to Entergy Nuclear Operations, "Indian Point Nuclear Generating Unit No. 3 - Safety Evaluation for Relief Request IP3-ISI-RR-07 for Reactor Vessel Cold Leg Nozzle to Safe-End Weld Examinations (TAC No. MF3346),11 dated August 4, 2014 (ADAMS Accession No. ML14199A444)
c. NRC Letter to Duke Energy Carolinas LLC, "Oconee Nuclear Station, Units 1 and 2 - Safety Evaluation for Relief Request No. 17 -ON-001 (EPID L-2017-LLR-0099)," dated April 13, 2018 (ADAMS Accession No. ML18100A005)
8. References
1) Regulatory Guide 1.147, 11lnservice Inspection Code Case Acceptability, ASME Section XI, Division 1,.. Revision 18 dated March 2017
2) Code Case N-770-2, '¶lternative Examination Requirements and Acceptance Standards for Class 1 PWR Piping and Vessel Nozzle Butt Welds Fabricated with UNS N06082 or UNS W86182 Weld Filler Material With or Without Application of Listed Mitigation ActivitiesSection XI, Division 1."
3) NUREG/CR-7187, "Managing PWSCC in Butt Welds by Mitigation and Inspection," November 2014 Page 5 of 5