| title = Furnishing Comments on Commission'S Engineering Department Report Re Applicant'S 5/16/1977 System Disturbance Concerning Starting of Gas Turbines Upon Occurrence of Single Contingency
| title = Furnishing Comments on Commissions Engineering Department Report Re Applicants 5/16/1977 System Disturbance Concerning Starting of Gas Turbines Upon Occurrence of Single Contingency
| author name = Bivans E
| author name = Bivans E
| author affiliation = Florida Power & Light Co
| author affiliation = Florida Power & Light Co
Line 16: Line 16:
=Text=
=Text=
{{#Wiki_filter:REGULATORY INFORMATION DISTRIBUTION SYSTEM (RID=)
{{#Wiki_filter:REGULATORY INFORMATION DISTRIBUTION SYSTEM (RID=)
DISTRIBUTION FOR INCOMING MATERIAL                         50-250   51/   F35 REC:    SWAFFORD D L                ORG: BIVANS E L                     DOCDATE: 0   "/O'9/78 FL PUB SVC  COMM                  FL PWR   ~~
DISTRIBUTION FOR INCOMING MATERIAL 50-250 51/ F35 ORG:
LIGHT               DATE RCVD:   04/12/78 DUCTYPE: LETTER       NOTARIZED: NO                                     COPIES RECEIVED
BIVANS E L DOCDATE:
0 "/O'9/78 FL PWR
~~
LIGHT DATE RCVD: 04/12/78 REC:
SWAFFORD D L FL PUB SVC COMM DUCTYPE:
LETTER NOTARIZED:
NO COPIES RECEIVED


==SUBJECT:==
==SUBJECT:==
LTR 1     ENCL 0 URNSIHING COMMENTS ON THE COMMISSION"S ENGINEERING DEPT REPT OF 02/01/JS               RE APPLICANT ' 05/ 1 6/77 SYSTEM D I STURBAhlCE CONCERNING START I NG QF GAS TURB Ih!ES
LTR 1
~UPON OCCIJRANCE OF A - INGLE CONTINGENCY.
ENCL 0 URNSIHING COMMENTS ON THE COMMISSION"S ENGINEERING DEPT REPT OF 02/01/JS RE APPLICANT '
INITIAL:
05/ 1 6/77 SYSTEM DISTURBAhlCE CONCERNING START ING QF GAS TURBIh!ES
PLANT hNME: TURKEY PT ~~)3 1
~UPON OCCIJRANCE OF A
TURKEY PT N3 ST LUCIE Si REVIEWER DISTRIBUTER INITIAL:
- INGLE CONTINGENCY.
                                                                                        ~
PLANT hNME: TURKEY PT
X JM DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS GENERAL DISTRIBUTION FOR AFTER ISSUANCE OF OPERATING LICENSE.
~~)3 1
(DISTRIBUTION CODE   A001)
TURKEY PT N3 ST LUCIE Si REVIEWER INITIAL:
FQR ACTION:       BR CHIEF SCHWENCER+''~LTR ONLY(7)
XJM DISTRIBUTER INITIAL:~
INTERNAL:          F
DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS GENERAL DISTRIBUTION FOR AFTER ISSUANCE OF OPERATING LICENSE.
                            &w L -'NLY(i)
(DISTRIBUTION CODE A001)
NLY(2)
FQR ACTION:
INTERNAL:
E ETERNAL:
BR CHIEF SCHWENCER+''~LTR ONLY(7)
F L -'NLY(i)
&w NLY(2)
HANAIJER-:>+LTR ONLY ( 1 EISEhlHUT~+LTR ONLY( 1)
. BAER~~~LTR ONLY(l>
EEB4+LTR ONLY( 1)
J.
MCGOUGH~~LTR ONLY(1)
LPDR S MIAMI, FL4+LTR ONLY(1)
TIC'~~LTR ONLY(1)
NSIC<-<LTR ONLY( 1)
ACRS CAT B>+LTR ONLY(16)
LPQ ~
NRC PDR++LTR ONLY(1)
NRC PDR++LTR ONLY(1)
OELD++LTR ONLY( 1)
OELD++LTR ONLY( 1)
HANAIJER-:>+LTR ONLY ( 1  >        CHECK+~LTR ONLY(i)
CHECK+~LTR ONLY(i)
EISEhlHUT~+LTR ONLY( 1)            SHAQ+<LTR ONLY(i)
SHAQ+<LTR ONLY(i)
                    . BAER~~~LTR  ONLY(l>              BUTLER~~LTR ONLY(i>
BUTLER~~LTR ONLY(i>
EEB4+LTR ONLY( 1)                  J COLLINS<+LTR ONLY(i)
J COLLINS<+LTR ONLY(i) g.. Re.i& ~~~~Qc.~'5 DISTRIBUTION:
J. MCGOUGH~~LTR ONLY(1)            g.. Re.i& ~~~~Qc.~'5 E ETERNAL:       LPDR S MIAMI, FL4+LTR ONLY(1)
LTR~
TIC'~~LTR ONLY(1)
ENCL 0 SIZE:
NSIC<-<LTR ONLY( 1)
2P-THE END CONTROL NBR:
ACRS  CAT B>+LTR ONLY(16)
7'='1030020
LPQ  ~
DISTRIBUTION:
SIZE: 2P-LTR  ~      ENCL 0                          CONTROL NBR:   7'='1030020 THE END


P. 0   OX OI3100, PhIAMI, FLOIIIOA 33IOI F> QRIDA POWcR 5 LIGHT COMPANY March 29, 1978
P. 0 OX OI3100, PhIAMI, FLOIIIOA 33IOI F> QRIDA POWcR 5 LIGHT COMPANY March 29, 1978
                                                          ~o - 25>( 2.5             )
~o - 25>( 2.5 )
Mr. David L. Swaf ford Executive Director                                                               C  ~
Mr. David L. Swaf ford Executive Director Engineering Department Florida Public Service Commission 700 South Adams Street Tallahassee FL 32304
Engineering Department                                   I                    Cg Florida Public Service Commission 700 South Adams Street                               )~~
C )C'.j Tallahassee FL 32304                                 R I~                      CD


==Dear Mr. Swafford:==
==Dear Mr. Swafford:==
 
I
)~~
R I~
C
~
Cg C )C'.j CD C)
C)
C)
With regard to your request for comments M the             C) o3 Commission's Engineering Department report of February 1, 1978, regarding our Clay 16, 1977 System Disturbance, I submit the following:
With regard to your request for comments M the o3 Commission's Engineering Department report of February 1,
1978, regarding our Clay 16, 1977 System Disturbance, I submit the following:
The Commission's Engineering Department should be complimented on their treatment of this difficult ancL sometimes misunderstood subject, of power system reliability.
The Commission's Engineering Department should be complimented on their treatment of this difficult ancL sometimes misunderstood subject, of power system reliability.
We have initiated work to implement, the actions recommended in their report.
We have initiated work to implement, the actions recommended in their report.
In the Staff's report, they asked if we would clarify our policy regarding the starting of gas turbines upon occurrence of a single contingency. At the present time we utilize gas turbines for a number of system conditions:
In the Staff's report, they asked if we would clarify our policy regarding the starting of gas turbines upon occurrence of a single contingency.
At the present time we utilize gas turbines for a number of system conditions:
.(1) to.maintain our suoplemental reserve obligation to FCG, (2) to control tne amount of powei being transferred into our South and East areas, (3) for interchange transactions, (4) for testing, and (5) to serve load when no other genera-tion is available.
.(1) to.maintain our suoplemental reserve obligation to FCG, (2) to control tne amount of powei being transferred into our South and East areas, (3) for interchange transactions, (4) for testing, and (5) to serve load when no other genera-tion is available.
Our supolemental reserve requirement, the oower transfer limit, and the status of each gas turbine are continuously monitored by the System Operator. If a generator or major transmission line in the South or East areas is tripped and either requirement is violated, the System Ooerator will immediately start gas turbines. This procedure will be automated to a certain extent with the installation of our 7SaO=-Oooo
Our supolemental reserve requirement, the oower transfer limit, and the status of each gas turbine are continuously monitored by the System Operator.
If a generator or major transmission line in the South or East areas is tripped and either requirement is violated, the System Ooerator will immediately start gas turbines.
This procedure will be automated to a certain extent with the installation of our 7SaO=-Oooo


Mr. David L. Swafford Page 2 March 29, 1978 new System   Control Center later this year. This system will routinely. evaluate system conditions and direct the dispatcher's, attention to problem areas.
Mr. David L. Swafford Page 2
March 29, 1978 new System Control Center later this year.
This system will routinely. evaluate system conditions and direct the dispatcher's, attention to problem areas.
Should you or the staff require additional clarification, please contact me.
Should you or the staff require additional clarification, please contact me.
Very truly yours, E. L. Bivans Vice President JSB/JRS/ds xc:   Messrs:
Very truly yours, E. L. Bivans Vice President JSB/JRS/ds xc:
E. A'. Adomat F. E. Autrey J. J., Hudiburg
Messrs:
    'R. E. Talion W. E. Coe R. T. Culberson Tracy Danese William L. Weeks, Escr.
E.
Joseph D. Jenkins The Honorable Commissioners   =
A'. Adomat F. E. Autrey J.
Paula Hawkins,. Chairman William T. Mayo Robert T. Mann U.S. Environmental Protection Agency U. S. Nuclear Regulatory Commission U.S. Deoartment of Energy Florida Department of Environmental Regulation Florida Division of State Planning Florida Regional Planning Council Palm Beach County Health Department, Broward County Environmental Control Board Dade County Pollution Control State Energy Office SERC
J., Hudiburg
'R. E. Talion W. E.
Coe R. T. Culberson Tracy Danese William L. Weeks, Escr.
Joseph D. Jenkins The Honorable Commissioners
=
Paula Hawkins,. Chairman William T.
Mayo Robert T.
Mann U.S. Environmental Protection Agency U. S. Nuclear Regulatory Commission U.S.
Deoartment of Energy Florida Department of Environmental Regulation Florida Division of State Planning Florida Regional Planning Council Palm Beach County Health Department, Broward County Environmental Control Board Dade County Pollution Control State Energy Office SERC


0}}
0}}

Latest revision as of 14:34, 5 January 2025

Furnishing Comments on Commissions Engineering Department Report Re Applicants 5/16/1977 System Disturbance Concerning Starting of Gas Turbines Upon Occurrence of Single Contingency
ML18227D407
Person / Time
Site: Turkey Point  
Issue date: 03/29/1978
From: Bivans E
Florida Power & Light Co
To: Swafford D
Office of Nuclear Reactor Regulation, State of FL, Public Service Commission, Engineering Dept
References
Download: ML18227D407 (4)


Text

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RID=)

DISTRIBUTION FOR INCOMING MATERIAL 50-250 51/ F35 ORG:

BIVANS E L DOCDATE:

0 "/O'9/78 FL PWR

~~

LIGHT DATE RCVD: 04/12/78 REC:

SWAFFORD D L FL PUB SVC COMM DUCTYPE:

LETTER NOTARIZED:

NO COPIES RECEIVED

SUBJECT:

LTR 1

ENCL 0 URNSIHING COMMENTS ON THE COMMISSION"S ENGINEERING DEPT REPT OF 02/01/JS RE APPLICANT '

05/ 1 6/77 SYSTEM DISTURBAhlCE CONCERNING START ING QF GAS TURBIh!ES

~UPON OCCIJRANCE OF A

- INGLE CONTINGENCY.

PLANT hNME: TURKEY PT

~~)3 1

TURKEY PT N3 ST LUCIE Si REVIEWER INITIAL:

XJM DISTRIBUTER INITIAL:~

DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS GENERAL DISTRIBUTION FOR AFTER ISSUANCE OF OPERATING LICENSE.

(DISTRIBUTION CODE A001)

FQR ACTION:

INTERNAL:

E ETERNAL:

BR CHIEF SCHWENCER+~LTR ONLY(7)

F L -'NLY(i)

&w NLY(2)

HANAIJER-:>+LTR ONLY ( 1 EISEhlHUT~+LTR ONLY( 1)

. BAER~~~LTR ONLY(l>

EEB4+LTR ONLY( 1)

J.

MCGOUGH~~LTR ONLY(1)

LPDR S MIAMI, FL4+LTR ONLY(1)

TIC'~~LTR ONLY(1)

NSIC<-<LTR ONLY( 1)

ACRS CAT B>+LTR ONLY(16)

LPQ ~

NRC PDR++LTR ONLY(1)

OELD++LTR ONLY( 1)

CHECK+~LTR ONLY(i)

SHAQ+<LTR ONLY(i)

BUTLER~~LTR ONLY(i>

J COLLINS<+LTR ONLY(i) g.. Re.i& ~~~~Qc.~'5 DISTRIBUTION:

LTR~

ENCL 0 SIZE:

2P-THE END CONTROL NBR:

7'='1030020

P. 0 OX OI3100, PhIAMI, FLOIIIOA 33IOI F> QRIDA POWcR 5 LIGHT COMPANY March 29, 1978

~o - 25>( 2.5 )

Mr. David L. Swaf ford Executive Director Engineering Department Florida Public Service Commission 700 South Adams Street Tallahassee FL 32304

Dear Mr. Swafford:

I

)~~

R I~

C

~

Cg C )C'.j CD C)

C)

With regard to your request for comments M the o3 Commission's Engineering Department report of February 1,

1978, regarding our Clay 16, 1977 System Disturbance, I submit the following:

The Commission's Engineering Department should be complimented on their treatment of this difficult ancL sometimes misunderstood subject, of power system reliability.

We have initiated work to implement, the actions recommended in their report.

In the Staff's report, they asked if we would clarify our policy regarding the starting of gas turbines upon occurrence of a single contingency.

At the present time we utilize gas turbines for a number of system conditions:

.(1) to.maintain our suoplemental reserve obligation to FCG, (2) to control tne amount of powei being transferred into our South and East areas, (3) for interchange transactions, (4) for testing, and (5) to serve load when no other genera-tion is available.

Our supolemental reserve requirement, the oower transfer limit, and the status of each gas turbine are continuously monitored by the System Operator.

If a generator or major transmission line in the South or East areas is tripped and either requirement is violated, the System Ooerator will immediately start gas turbines.

This procedure will be automated to a certain extent with the installation of our 7SaO=-Oooo

Mr. David L. Swafford Page 2

March 29, 1978 new System Control Center later this year.

This system will routinely. evaluate system conditions and direct the dispatcher's, attention to problem areas.

Should you or the staff require additional clarification, please contact me.

Very truly yours, E. L. Bivans Vice President JSB/JRS/ds xc:

Messrs:

E.

A'. Adomat F. E. Autrey J.

J., Hudiburg

'R. E. Talion W. E.

Coe R. T. Culberson Tracy Danese William L. Weeks, Escr.

Joseph D. Jenkins The Honorable Commissioners

=

Paula Hawkins,. Chairman William T.

Mayo Robert T.

Mann U.S. Environmental Protection Agency U. S. Nuclear Regulatory Commission U.S.

Deoartment of Energy Florida Department of Environmental Regulation Florida Division of State Planning Florida Regional Planning Council Palm Beach County Health Department, Broward County Environmental Control Board Dade County Pollution Control State Energy Office SERC