#REDIRECT [[L-2023-003, Units 1 and 2 - Response to Requests for Additional Information (Rals) Regarding License Amendment Request 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk Informed .]]
{{Adams
| number = ML23128A283
| issue date = 05/08/2023
| title = Email Dated May 8, 2023, from T. E. Sellmer (Simco) to N. Garcia Santos (NRC) and D. Smith (Doe), Subject: Halfpact Letter Authorization (Change in Need Date)
| author name = Sellmer T
| author affiliation = Salado Isolation Mining Contractors (SIMCO) LLC
| addressee name = Garcia-Santos N, Smith D
| addressee affiliation = NRC/NMSS/DFM/STLB, US Dept of Energy (DOE)
| docket = 07109279
| license number =
| contact person =
| case reference number = 001029, L-2023-0030
| document type = E-Mail
| page count = 4
}}
 
=Text=
{{#Wiki_filter:From:
Sellmer, Todd (CONTR)
To:
Norma Garcia Santos; Smith, DaBrisha - CBFO Cc:
Burns, Scott (CONTR)
 
==Subject:==
[External_Sender] RE: RE: RE: HALFPACT Letter Authorizations Date:
Monday, May 8, 2023 2:15:16 PM Attachments:
image001.png
: Norma,
 
There is no sensitive information contained.
: Thanks,
 
Todd
 
Todd Sellmer I Manager, Packaging & Information Systems Salado Isolation Mining Contractors I Waste Isolation Pilot Plant ASNT Level III / ASNT Fellow M: 575-302-7583 I O: 575-234-7396 I E: todd.sellmer@wipp.ws
 
From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>
Sent: Monday, May 08, 2023 12:12 PM To: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>; Smith, DaBrisha - CBFO
<DaBrisha.Smith@cbfo.doe.gov>
Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>
 
==Subject:==
RE: RE: RE: HALFPACT Letter Authorizations
 
The message to Todd.Sellmer@wipp.ws on Mon May 08 2023 12:10:33 contains a file attachment:
image001.png that may have been dropped.
 
Good afternoon,
 
Before I place this email in ADAMS, is there any information that I should not include as publicly available. The email does not seem to include sensitive information, but I want to confirm with you.
: Thanks, Norma
 
From: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>
Sent: Thursday, April 27, 2023 12:51 PM To: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>; Smith, DaBrisha - CBFO
<DaBrisha.Smith@cbfo.doe.gov>
Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>
 
==Subject:==
[External_Sender] RE: RE: HALFPACT Letter Authorizations
: Norma,
 
Right now my Operations & Nuclear Safety Group will not begin the activities necessary to perform the shipment back to SRS until we have the approval. We applied yesterday to the New Mexico Environmental Department (NMED) for an additional 180 days above surface storage extension. We are hopeful that the additional 180 day extension from NMED will be granted however, the sooner we get the approval from your organization the sooner our organizations at the WIPP Site can start their activities to support the shipment back to SRS.
: Thanks,
 
Todd
 
Todd Sellmer I Manager, Packaging & Information Systems Salado Isolation Mining Contractors I Waste Isolation Pilot Plant ASNT Level III / ASNT Fellow M: 575-302-7583 I O: 575-234-7396 I E: todd.sellmer@wipp.ws
 
From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>
Sent: Thursday, April 27, 2023 10:41 AM To: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>; Smith, DaBrisha - CBFO
<DaBrisha.Smith@cbfo.doe.gov>
Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>
 
==Subject:==
RE: RE: HALFPACT Letter Authorizations
 
The message to Todd.Sellmer@wipp.ws on Thu Apr 27 2023 10:39:12 contains a file attachment:
image001.png that may have been dropped.
: Todd,
 
What would be the impact of not providing the response to you by 5/24/23? My understanding is that you would not ne able to ship the package. Any other impact that I pr my management should be aware of?
: Thanks, Norma
 
From: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>
Sent: Thursday, April 27, 2023 12:38 PM To: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>; Smith, DaBrisha - CBFO
<DaBrisha.Smith@cbfo.doe.gov>
Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>
 
==Subject:==
[External_Sender] RE: HALFPACT Letter Authorizations
: Norma,
 
Thank you for the follow up email. We could get by with an approval date of 05/24/2023.
: Regards,
 
Todd
 
Todd Sellmer I Manager, Packaging & Information Systems Salado Isolation Mining Contractors I Waste Isolation Pilot Plant ASNT Level III / ASNT Fellow M: 575-302-7583 I O: 575-234-7396 I E: todd.sellmer@wipp.ws
 
From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>
Sent: Thursday, April 27, 2023 9:26 AM To: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>; Smith, DaBrisha - CBFO
<DaBrisha.Smith@cbfo.doe.gov>
 
==Subject:==
HALFPACT Letter Authorizations Importance: High
 
WARNING - EXTERNAL EMAIL This message does not originate from a known WIPP email system.
 
Use caution if this message contains attachments, links or requests for information.
 
Good morning,
 
Thanks for providing the RAI responses in a timely manner. The staff is working diligently on you application. I want to confirm with you if May 17th is still the date that you need the response on the letter authorization and if there is some room on that date.
 
Thanks in advance,
 
Norma Garcia Santos Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards}}

Latest revision as of 18:18, 2 January 2025

Email Dated May 8, 2023, from T. E. Sellmer (Simco) to N. Garcia Santos (NRC) and D. Smith (Doe), Subject: Halfpact Letter Authorization (Change in Need Date)
ML23128A283
Person / Time
Site: 07109279
Issue date: 05/08/2023
From: Sellmer T
Salado Isolation Mining Contractors (SIMCO) LLC
To: Garcia-Santos N, Danni Smith
Storage and Transportation Licensing Branch, US Dept of Energy (DOE)
References
001029, L-2023-0030
Download: ML23128A283 (4)


Text

From:

Sellmer, Todd (CONTR)

To:

Norma Garcia Santos; Smith, DaBrisha - CBFO Cc:

Burns, Scott (CONTR)

Subject:

[External_Sender] RE: RE: RE: HALFPACT Letter Authorizations Date:

Monday, May 8, 2023 2:15:16 PM Attachments:

image001.png

Norma,

There is no sensitive information contained.

Thanks,

Todd

Todd Sellmer I Manager, Packaging & Information Systems Salado Isolation Mining Contractors I Waste Isolation Pilot Plant ASNT Level III / ASNT Fellow M: 575-302-7583 I O: 575-234-7396 I E: todd.sellmer@wipp.ws

From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>

Sent: Monday, May 08, 2023 12:12 PM To: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>; Smith, DaBrisha - CBFO

<DaBrisha.Smith@cbfo.doe.gov>

Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>

Subject:

RE: RE: RE: HALFPACT Letter Authorizations

The message to Todd.Sellmer@wipp.ws on Mon May 08 2023 12:10:33 contains a file attachment:

image001.png that may have been dropped.

Good afternoon,

Before I place this email in ADAMS, is there any information that I should not include as publicly available. The email does not seem to include sensitive information, but I want to confirm with you.

Thanks, Norma

From: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>

Sent: Thursday, April 27, 2023 12:51 PM To: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>; Smith, DaBrisha - CBFO

<DaBrisha.Smith@cbfo.doe.gov>

Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>

Subject:

[External_Sender] RE: RE: HALFPACT Letter Authorizations

Norma,

Right now my Operations & Nuclear Safety Group will not begin the activities necessary to perform the shipment back to SRS until we have the approval. We applied yesterday to the New Mexico Environmental Department (NMED) for an additional 180 days above surface storage extension. We are hopeful that the additional 180 day extension from NMED will be granted however, the sooner we get the approval from your organization the sooner our organizations at the WIPP Site can start their activities to support the shipment back to SRS.

Thanks,

Todd

Todd Sellmer I Manager, Packaging & Information Systems Salado Isolation Mining Contractors I Waste Isolation Pilot Plant ASNT Level III / ASNT Fellow M: 575-302-7583 I O: 575-234-7396 I E: todd.sellmer@wipp.ws

From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>

Sent: Thursday, April 27, 2023 10:41 AM To: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>; Smith, DaBrisha - CBFO

<DaBrisha.Smith@cbfo.doe.gov>

Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>

Subject:

RE: RE: HALFPACT Letter Authorizations

The message to Todd.Sellmer@wipp.ws on Thu Apr 27 2023 10:39:12 contains a file attachment:

image001.png that may have been dropped.

Todd,

What would be the impact of not providing the response to you by 5/24/23? My understanding is that you would not ne able to ship the package. Any other impact that I pr my management should be aware of?

Thanks, Norma

From: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>

Sent: Thursday, April 27, 2023 12:38 PM To: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>; Smith, DaBrisha - CBFO

<DaBrisha.Smith@cbfo.doe.gov>

Cc: Burns, Scott (CONTR) <Scott.Burns@wipp.ws>

Subject:

[External_Sender] RE: HALFPACT Letter Authorizations

Norma,

Thank you for the follow up email. We could get by with an approval date of 05/24/2023.

Regards,

Todd

Todd Sellmer I Manager, Packaging & Information Systems Salado Isolation Mining Contractors I Waste Isolation Pilot Plant ASNT Level III / ASNT Fellow M: 575-302-7583 I O: 575-234-7396 I E: todd.sellmer@wipp.ws

From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>

Sent: Thursday, April 27, 2023 9:26 AM To: Sellmer, Todd (CONTR) <Todd.Sellmer@wipp.ws>; Smith, DaBrisha - CBFO

<DaBrisha.Smith@cbfo.doe.gov>

Subject:

HALFPACT Letter Authorizations Importance: High

WARNING - EXTERNAL EMAIL This message does not originate from a known WIPP email system.

Use caution if this message contains attachments, links or requests for information.

Good morning,

Thanks for providing the RAI responses in a timely manner. The staff is working diligently on you application. I want to confirm with you if May 17th is still the date that you need the response on the letter authorization and if there is some room on that date.

Thanks in advance,

Norma Garcia Santos Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards