Chicago. Illinois 60690 July 16, 1982 Mr. Harold R. Denton, Director Of fice o f Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555 | 'N Commonwealth Edison l | ||
. ' One ~irst Nabonal Plaza Chicago. Ilhnois 7 Address R; ply to: Post Office Box 767 s | |||
x Chicago. Illinois 60690 July 16, 1982 Mr. Harold R. Denton, Director Of fice o f Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555 | |||
==Subject:== | ==Subject:== | ||
Byron Station Units 1 and 2 Construction Completion Schedule NRC Docket Nos. 50-454 and 50-455 Reference (a): | Byron Station Units 1 and 2 Construction Completion Schedule NRC Docket Nos. 50-454 and 50-455 Reference (a): | ||
Ma y 2 9, 1981, letter from H.R. | |||
Denton to J. | |||
J. O ' Co n n o r. | |||
==Dear Mr. Denton:== | ==Dear Mr. Denton:== | ||
This letter is the fif th in a series of quarterly reports to you regarding the construction completion date for Byron Unit 1. | This letter is the fif th in a series of quarterly reports to you regarding the construction completion date for Byron Unit 1. | ||
The Byron 1 construction and testing schedule has been revised. | The Byron 1 construction and testing schedule has been revised. | ||
The fuel load date is delayed 5 months from April 1, 1983 to August 31, 1983 due to piping analysis work which is more invol-ved than anticipated and which results in additional construction manhours. | |||
Please address questions regarding the Byron 1 schedule to this office. | Please address questions regarding the Byron 1 schedule to this office. | ||
Very truly yours, L. O. DelGeo rg e l | Very truly yours, L. O. | ||
8207230342 820716 PDR ADOCK 05000454 A | DelGeo rg e l | ||
Nuclear Licensing Administrator TRT/lm 4535N Sool i | |||
8207230342 820716 PDR ADOCK 05000454 A | |||
PDR | |||
-}} | |||
Latest revision as of 15:43, 17 December 2024
| ML20055B832 | |
| Person / Time | |
|---|---|
| Site: | Byron |
| Issue date: | 07/16/1982 |
| From: | Delgeorge L COMMONWEALTH EDISON CO. |
| To: | Harold Denton Office of Nuclear Reactor Regulation |
| References | |
| 4535N, NUDOCS 8207230342 | |
| Download: ML20055B832 (1) | |
Text
_ _____
}
/'
'N Commonwealth Edison l
. ' One ~irst Nabonal Plaza Chicago. Ilhnois 7 Address R; ply to: Post Office Box 767 s
x Chicago. Illinois 60690 July 16, 1982 Mr. Harold R. Denton, Director Of fice o f Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555
Subject:
Byron Station Units 1 and 2 Construction Completion Schedule NRC Docket Nos. 50-454 and 50-455 Reference (a):
Ma y 2 9, 1981, letter from H.R.
Denton to J.
J. O ' Co n n o r.
Dear Mr. Denton:
This letter is the fif th in a series of quarterly reports to you regarding the construction completion date for Byron Unit 1.
The Byron 1 construction and testing schedule has been revised.
The fuel load date is delayed 5 months from April 1, 1983 to August 31, 1983 due to piping analysis work which is more invol-ved than anticipated and which results in additional construction manhours.
Please address questions regarding the Byron 1 schedule to this office.
Very truly yours, L. O.
DelGeo rg e l
Nuclear Licensing Administrator TRT/lm 4535N Sool i