ML20076C280: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 20: Line 20:


==SUMMARY==
==SUMMARY==
ILEVEL11 AUGUST 4,1983 l
ILEVEL11 AUGUST 4,1983 l
Washington Public Power Supply System
Washington Public Power Supply System
Line 28: Line 27:


==SUMMARY==
==SUMMARY==
 
This portion is intended tc provide executive level information relative to the plan,~anagement principles and the most critical aspects of the construction m
This portion is intended tc provide executive level information relative to the plan,~anagement m          principles and the most critical aspects of the construction delay.
delay.
J LEVEL II - DESCRIPTION OF PERFORMANCE Bf FUNCTION This is intended to describe, at the management level, those functions which will or might be performed during the construction delay. This level II portion together with Level I constitutes middle management's guidelines.
J LEVEL II - DESCRIPTION OF PERFORMANCE Bf FUNCTION This is intended to describe, at the management level, those functions which will or might be performed during the construction delay.
LEVEL III - SUPPORTING DOCUMENTS These documents are all of the supporting procedures, data, budgets, etc., which support the Level II and I. These are internal documents and are not intended for consolidation or distribution outside the project except as may be required.
This level II portion together with Level I constitutes middle management's guidelines.
LEVEL III - SUPPORTING DOCUMENTS These documents are all of the supporting procedures, data, budgets, etc., which support the Level II and I.
These are internal documents and are not intended for consolidation or distribution outside the project except as may be required.
a l
a l
l l


08/03/83 MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY OF WNP-3 1.0     EXECUTIVE  
08/03/83 MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY OF WNP-3 1.0 EXECUTIVE  


==SUMMARY==
==SUMMARY==
 
==1.1 INTRODUCTION==
==1.1       INTRODUCTION==
This Management Plan is a description of the policy and guidelines to be fol-lowed in executing an extended construction delay at WNP-3. The Supply System will use this plan as the basis for management direction relative to the delay period. The delay plan must be executed in strict accordance with the limited funding plan while preserving the assets of WNP-3 during the delay.
This Management Plan is a description of the policy and guidelines to be fol-lowed in executing an extended construction delay at WNP-3. The Supply System will use this plan as the basis for management direction relative to the delay period. The delay plan must be executed in strict accordance with the limited funding plan while preserving the assets of WNP-3 during the delay.


==1.2     BACKGROUND==
==1.2 BACKGROUND==
 
The delay of construction of this project is a result of several major events.
The delay of construction of this project is a result of several major events.
These include numerous matters of litigation two of which can be deemed major:
These include numerous matters of litigation two of which can be deemed major:
(1) the decision by the \'ashington State Supreme Court on June 15, 1983 ruling that WNP-4/5 Participants are not bound to make payments to the Supply System, and (2) the question of the authority of certain participants to enter into the WNP-1, 2 and 3 net-billing agreements. These and other related issues impact the ability of the Supply System to continue financing construction of WNP-3.
(1) the decision by the \\'ashington State Supreme Court on June 15, 1983 ruling that WNP-4/5 Participants are not bound to make payments to the Supply System, and (2) the question of the authority of certain participants to enter into the WNP-1, 2 and 3 net-billing agreements.
As a result of the status of these issues, on May 27, 1983, the Executive Board through Resolution No. 147 directed that the Managing Director slowdown con-struction on WNP-3 for a period not to exceed thirty (30) days in such a manner that, should additional funding be found during that period, work could be resumed with no impact to the 1983 total budget and official schedule. Then, on i   July 8,1983, the Executive Board Resolution No.152 directed the Managing Director to implement an immediate extended construction delay of Project 3 until'an assured source of funding for continued construction can be obtained and to prepare and deliver a detailed implementation plan to the Executive Board. Tnis Management Plant satisfies the latter direction.
These and other related issues impact the ability of the Supply System to continue financing construction of WNP-3.
As a result of the status of these issues, on May 27, 1983, the Executive Board through Resolution No. 147 directed that the Managing Director slowdown con-struction on WNP-3 for a period not to exceed thirty (30) days in such a manner that, should additional funding be found during that period, work could be resumed with no impact to the 1983 total budget and official schedule. Then, on i
July 8,1983, the Executive Board Resolution No.152 directed the Managing Director to implement an immediate extended construction delay of Project 3 until'an assured source of funding for continued construction can be obtained and to prepare and deliver a detailed implementation plan to the Executive Board.
Tnis Management Plant satisfies the latter direction.
i 1
i 1
1 08/03/83 1.3     CRITERIA The criterion upon which this plan are based is at Attachment 1.
1 08/03/83 1.3 CRITERIA The criterion upon which this plan are based is at Attachment 1.
The Managing Director must be notified of any requirements and recommendations to change these criteria. Without the Managing Director's approval of such changes, the existing criteria are to be met.
The Managing Director must be notified of any requirements and recommendations to change these criteria. Without the Managing Director's approval of such changes, the existing criteria are to be met.
1.4     MANAGEMENT PRINCIPLES 1.4.1   Execution The management of the extended construction delay will be implemented through the site organization with the appropriate assistance from the Richland head-quarters. In managing the delay, maximum utilization will be made of existing procedures, systems and reports. All actions taken must be with full compliance of the existiag Ownership Agreements, Net-Billing Agreement and the Project Agreement.
1.4 MANAGEMENT PRINCIPLES 1.4.1 Execution The management of the extended construction delay will be implemented through the site organization with the appropriate assistance from the Richland head-quarters.
1.4.2   Changes To The Plan Changes to this plan will require approval of the Program Director and at his discretion the concurrence of the Managing Director, BPA, the Private Owners, the Participants' Committee and the Executive Board.
In managing the delay, maximum utilization will be made of existing procedures, systems and reports. All actions taken must be with full compliance of the existiag Ownership Agreements, Net-Billing Agreement and the Project Agreement.
1.5     LICENSING A major element of the criteria is preservation of licenses. Because of the sensitivity of this aspect of the construction delay, a brief description of licenses and associated activities is at Attachment 2.
1.4.2 Changes To The Plan Changes to this plan will require approval of the Program Director and at his discretion the concurrence of the Managing Director, BPA, the Private Owners, the Participants' Committee and the Executive Board.
1.6 -   CASH FLOW Because of the limited funding available and the flow thereof, forecasted ex-penditures of that funding and flow are of executive level interest.     That may be found at Attachment 3.
1.5 LICENSING A major element of the criteria is preservation of licenses.
Because of the sensitivity of this aspect of the construction delay, a brief description of licenses and associated activities is at Attachment 2.
1.6 -
CASH FLOW Because of the limited funding available and the flow thereof, forecasted ex-penditures of that funding and flow are of executive level interest.
That may be found at Attachment 3. _.


08/03/83 1.7     MANPOWER PROFILE Manpower requirements on the Project are closely related to the level of docu-mentation, rampdown and preservation activities. These requirements are graphic-ally displayed on the associated manpower profile at Attachments 4 and 5.
08/03/83 1.7 MANPOWER PROFILE Manpower requirements on the Project are closely related to the level of docu-mentation, rampdown and preservation activities.
1.8     SCHEDULE 1.8.1     Implementation Implementation of the delay plan began immediately after the Board action was taken on July 8, 1983. Concurrently, this Management Plan, as well as detailed plans which support the limited funding and associated manpower levels, were developed. All are consistent with the Board's action and specific guicance provided by the Managing Director.
These requirements are graphic-ally displayed on the associated manpower profile at Attachments 4 and 5.
1.8.2   Submittals e       First draft for Program Director's review on July 26, 1983.
1.8 SCHEDULE 1.8.1 Implementation Implementation of the delay plan began immediately after the Board action was taken on July 8, 1983. Concurrently, this Management Plan, as well as detailed plans which support the limited funding and associated manpower levels, were developed. All are consistent with the Board's action and specific guicance provided by the Managing Director.
e       Final " Management Plan For Extended Construction Delay of WNP-3" for Executive Board Committee review on August 11, 1983.
4 1.8.2 Submittals e
1.9     REPORTING Reporting against this plan will generally follow the monthly report of WNP-1 tailored to WNP-3 as further described in Section 9.0 of the Level II portion of this plan.
First draft for Program Director's review on July 26, 1983.
e Final " Management Plan For Extended Construction Delay of WNP-3" for Executive Board Committee review on August 11, 1983.
1.9 REPORTING Reporting against this plan will generally follow the monthly report of WNP-1 tailored to WNP-3 as further described in Section 9.0 of the Level II portion of this plan.
4 I
4 I
I l                                           :
l :


GENERAL CRITERZA               ATTACHMENT 1 IINP-3 CONSTRUCTf0N DELAY IMPLEMENTATION PLAN       08/03/83 I. Introduction l
GENERAL CRITERZA ATTACHMENT 1 IINP-3 CONSTRUCTf0N DELAY IMPLEMENTATION PLAN 08/03/83 I. Introduction l
Executive Board Resolution No.152 directed the Supply System to implement an immediate extended construction delay of Project No. 3 until an assured source of funding for continued construction can be obtained, and to pre-
Executive Board Resolution No.152 directed the Supply System to implement an immediate extended construction delay of Project No. 3 until an assured source of funding for continued construction can be obtained, and to pre-pare and deliver a detailed implementation plan to the Executive Board consistent with the foregoing.
      '.      pare and deliver a detailed implementation plan to the Executive Board consistent with the foregoing.
II. General Criteria I
II. General Criteria                                                                 I A. As of July 8,1983, continue further rampdown of construction and related activities from the current manpower level to a documentation roll-up and preservation / maintenance staff of approximately 800 by October 1983.
A.
B. Maintain the documentation roll-up and preservation / maintenance efforts from October 1983 to July 1984 with a manpower level of approximately 800 as of October 1983 gradually declining to a mini-mum preservation staff of approximately 375 as of July 1984. Man-power reductions to be generally accomplished within the profile shown on Attachment 1.
As of July 8,1983, continue further rampdown of construction and related activities from the current manpower level to a documentation roll-up and preservation / maintenance staff of approximately 800 by October 1983.
C. Maintain construction restart ability through approximately March 1984 by retaining the contractual ability to reactivate the essen-tial construction and prepurchased contracts.
B.
D. The implementation plan shall cover the period from July 8,1983 through June 30,1985 (FY-1984 and FY-1985).
Maintain the documentation roll-up and preservation / maintenance efforts from October 1983 to July 1984 with a manpower level of approximately 800 as of October 1983 gradually declining to a mini-mum preservation staff of approximately 375 as of July 1984.
E. Preserve all state and federal licensability requirements.
Man-power reductions to be generally accomplished within the profile shown on Attachment 1.
F. Preserve and control all documentation required for licenses, opera-tion and construction status.
C.
G. Optimize (to the extent practicable) the retention of the Supply System's resource capabilities over those of the AE/CM and contrac-tors.
Maintain construction restart ability through approximately March 1984 by retaining the contractual ability to reactivate the essen-tial construction and prepurchased contracts.
H. Outstanding licensing issues should be resolved to the largest extent possible.
D.
I. Complete those activities essential to planning for restart of con-struction.
The implementation plan shall cover the period from July 8,1983 through June 30,1985 (FY-1984 and FY-1985).
J. Establish and implement a cost tracking system for construction versus nonconstruction costs.
E.
Preserve all state and federal licensability requirements.
F.
Preserve and control all documentation required for licenses, opera-tion and construction status.
G.
Optimize (to the extent practicable) the retention of the Supply System's resource capabilities over those of the AE/CM and contrac-tors.
H.
Outstanding licensing issues should be resolved to the largest extent possible.
I.
Complete those activities essential to planning for restart of con-struction.
J.
Establish and implement a cost tracking system for construction versus nonconstruction costs.
I l
I l
l
l


General Criteria                                                         08/03/83 -
General Criteria 08/03/83 -
UllP-3 Construction Delay Implementation Plan Page 2 of 4 III. Financial Consideration A. Detailed cost and cash flow estimates shall be consistent with the following:
UllP-3 Construction Delay Implementation Plan Page 2 of 4 III. Financial Consideration A.
: 1. The estimating guidelines (as applicable) provided by the
Detailed cost and cash flow estimates shall be consistent with the following:
                    " General Criteria Fiscal Year 1984 Financing Planning Process".
1.
: 2. Actuals as of June 30, 1983.
The estimating guidelines (as applicable) provided by the
: 3. On a monthly basis for the period from July 1,1983 through June 30, 1985 (FY-1984 and FY-1985) at 100 percent ownership values.
" General Criteria Fiscal Year 1984 Financing Planning Process".
: 4. Summary presentations shall be formatted similar to the rolli.ng cash flow forecast (Attachment 2).
2.
5.'   Supporting cost and cash flow details shall as a minimum be broken down to the following levels:
Actuals as of June 30, 1983.
                    . Major budget line items.
3.
                    . Contract-by-contract.
On a monthly basis for the period from July 1,1983 through June 30, 1985 (FY-1984 and FY-1985) at 100 percent ownership values.
                    . Construction activities and nonconstruction activities.
4.
                    . One-time costs and on-going costs.
Summary presentations shall be formatted similar to the rolli.ng cash flow forecast (Attachment 2).
: 6. Funding for contract settlements or other costs, which may be rescheduled (due to the above Item II.C requirement) to a later time than planned in the May 1983 Wr1P-3 Alternative Analysis, are not available for other or additional disbursements.
5.'
: 7. Cash disbursements shall be planned in accordance with the Supply System's fiscal year calendar, which will be the basis for future performance measurement.
Supporting cost and cash flow details shall as a minimum be broken down to the following levels:
: 8. Include all applicable construction and fuel costs; i.e.,
Major budget line items.
Contract-by-contract.
Construction activities and nonconstruction activities.
One-time costs and on-going costs.
6.
Funding for contract settlements or other costs, which may be rescheduled (due to the above Item II.C requirement) to a later time than planned in the May 1983 Wr1P-3 Alternative Analysis, are not available for other or additional disbursements.
7.
Cash disbursements shall be planned in accordance with the Supply System's fiscal year calendar, which will be the basis for future performance measurement.
8.
Include all applicable construction and fuel costs; i.e.,
escalation, sales tax, nuclear fuel, applicable financing, contingency, etc.
escalation, sales tax, nuclear fuel, applicable financing, contingency, etc.
: 9. Exclude all potential cost sharing adjustments identified as a result of Supply System management review.
9.
B. July 1, 1983 through September 30, 1984 financial baseline ($ in millions):
Exclude all potential cost sharing adjustments identified as a result of Supply System management review.
Construction & Fuel Fund as of June 30, 1983     5 74.0 Estimated Investment Income                           1.5 Payments by 100's                                   59.5 Payments by BPA                                     63.0 Total Disbursements                           $3d
B.
July 1, 1983 through September 30, 1984 financial baseline ($ in millions):
Construction & Fuel Fund as of June 30, 1983 5 74.0 Estimated Investment Income 1.5 Payments by 100's 59.5 Payments by BPA 63.0 Total Disbursements
$3d


General Criteria                                                                                                                          08/03/83 UNP-3 Construction Delay Implementation Plan Page 3 of 4 C. Total cash disbursements for the period from July 1,1983 through September 30, 1984 shall not exceed $198 million (above). Further-
08/03/83 General Criteria UNP-3 Construction Delay Implementation Plan Page 3 of 4 C.
;                                                      more, the total cash disbursements from July 1,1983 through                                                                                         '
Total cash disbursements for the period from July 1,1983 through September 30, 1984 shall not exceed $198 million (above).
November 30, 1933 shall not exceed 5108 million.
Further-more, the total cash disbursements from July 1,1983 through November 30, 1933 shall not exceed 5108 million.
                                  '.            D. October 1,1984 through September 30, 1985 financial baseline ($ in millions):
D.
1 Payments by 100's                                                                 $13. 5                                                 i Payments by BPA                                                                   31.5 I
October 1,1984 through September 30, 1985 financial baseline ($ in millions):
Total Disbursements                                                           $45.0 IV. Format                                                                                                                                                             :
1 Payments by 100's
Utilize the "flanagement Plan for Extended Construction Delay of UNP-1",
$13. 5 i
9                                                dated November 30, 1982, as both a guide and a checklist tailored as
Payments by BPA 31.5 I
                                                            ~
Total Disbursements
j                                                 necessary to include UNP-3 considerations.
$45.0 IV. Format Utilize the "flanagement Plan for Extended Construction Delay of UNP-1",
V. Schedule A. First draft for Managing Director's review on July 26, 1983.
dated November 30, 1982, as both a guide and a checklist tailored as 9
B. Final "UNP-3 Construction Delay Implementation Plan" for Executive Board Committee review on August 11, 1983.
j necessary to include UNP-3 considerations.
~
V. Schedule A.
First draft for Managing Director's review on July 26, 1983.
B.
Final "UNP-3 Construction Delay Implementation Plan" for Executive Board Committee review on August 11, 1983.
l 1
l 1


      ' Pag? 4 of 4 08/03/83 UASHIflGTON PUBLIC POWER SUPPLY SYSTEM NUCLEAR PROJECT NO. 3 CONSTRUCTIO:t DELAY I!!PLEMEtiTATI0tt PLAft FISCAL YEAR 1984 AtlD 1985 GEllERAL TOTAL PROJECT 11ANPOWER PROFILE
' Pag? 4 of 4 08/03/83 UASHIflGTON PUBLIC POWER SUPPLY SYSTEM NUCLEAR PROJECT NO. 3 CONSTRUCTIO:t DELAY I!!PLEMEtiTATI0tt PLAft FISCAL YEAR 1984 AtlD 1985 GEllERAL TOTAL PROJECT 11ANPOWER PROFILE
* Average Monthly
* Average Monthly FY-1984 Equivalent fianpower July 1,500 Rampdown August 1,200 Period September 1,000 October 8005 f!ovember 800 December 750 Documentation January 725 and Preservation February 700 )
                    . FY-1984                                       Equivalent fianpower July                                                 1,500 August                                                         Rampdown 1,200 September                                           1,000     Period October                                                 8005 f!ovember                                             800 December                                               750   Documentation January                                                 725   and Preservation February                                               700 ) Effort March                                                 675 April                                                 650 May                                                   550 June                                                   450s Average Monthly FY-1985                                       Equivalent Manpower July                                                   375' August                                                 375 September                                             375 October                                                 375 November                                               375   Preservation and December                                               375 \ Maintenance Only January                                                 375 February                                               375(
Effort March 675 April 650 May 550 June 450s Average Monthly FY-1985 Equivalent Manpower July 375' August 375 September 375 October 375 November 375 Preservation and December 375 \\ Maintenance Only January February 375(
,                      !! arch                                                 375 April                                                   375 May                                                     375 June 375s
375
!! arch 375 April 375 May 375 June 375s
* Total project manpower includes the following:
* Total project manpower includes the following:
                            . Craft
Craft Contractor's ilonmanuel Construction Management Architect-Engineer Home Office On-site Supply System On-site Home Office Direct y
                            . Contractor's ilonmanuel
Home Office A&G Allocation t
                      ,    . Construction Management
i
                          . Architect-Engineer Home Office On-site
                          . Supply System On-site Home Office Direct y
Home Office A&G Allocation                                   '
t i


y.
y.
                                                                                                                                                                                    .                e e
e e
WASHINGTON PUSLIC POWER SUPPLY SYSTEM ATTACimi 2                                              .
ATTACimi 2 WASHINGTON PUSLIC POWER SUPPLY SYSTEM NUCLEAR PROJECT NO. 3 Sheet 1 of 2 CONSTRUCTION FU.'s CASil FLOW t M 10U5 M 5) 1983 1984 0 0tN.
NUCLEAR PROJECT NO. 3 Sheet 1 of 2 CONSTRUCTION FU.'s CASil FLOW t M 10U5 M 5) 1983                                                   1984
July Aq Sept Oct Ptw Dec
                                                                                                                              .                                                    0 0tN.
.La Feb Mr Apr Mqr are 11y As Sapt
July   Aq       Sept     Oct       Ptw     Dec     .La     Feb   Mr Apr Mqr   are     11y   As     Sapt                       ' 7-1-83 to 9-hot h6girejBalaor Reteipts Irretsut frume
' 7-1-83 to 9-hot h6girejBalaor Reteipts Irretsut frume PJ)muets ter IW's
* PJ)muets ter IW's                                                                                                                                               }                               .
}
fit Billirsp lotal Receipts Diprsammts                             ,                                                                                          ,
fit Billirsp lotal Receipts Diprsammts PlsA DesisfvTngiratring EXAMPLE htinsthsud Espipasit Plwit Cuistrution/Capletim Cuistewtlue Cuitra.ts Ca structtui Ka uf.c N ax's Re m tes (d)
PlsA DesisfvTngiratring                                                               EXAMPLE htinsthsud Espipasit Plwit Cuistrution/Capletim Cuistewtlue Cuitra.ts Ca structtui Ka uf.c N ax's Re m tes (d)
Na. lear final Cuitirsysay Ismtus livs Total Di:,tAYstNGts f.'!!"9 S'h'i' O'
* Na. lear final                                                                                         .
(4) Ircitakes prisf sy Ewrapasit, plait garation arsi caprate allocation.
Cuitirsysay Ismtus livs
D w
* Total Di:,tAYstNGts f.'!!"9 S'h'i'                     _
O' (4) Ircitakes prisf sy Ewrapasit, plait garation arsi caprate allocation.                                                                                                                     D w
CD w.
CD w.


l
l
                                                  ~
~
s m
s m
WASHINGT018 PUBLIC POK R SUPPLY SYSTEM                   ATTACitMENT 2 NULLEAR 8110 JECT NO. 3 COIISTRUCTION FUNu CASH FLOW Sheet 2 of 2
WASHINGT018 PUBLIC POK R SUPPLY SYSTEM ATTACitMENT 2 NULLEAR 8110 JECT NO. 3 Sheet 2 of 2 COIISTRUCTION FUNu CASH FLOW
($ IN TlluuSANDS) 1984                                             1985 Oct Itw                                                                              [     Total               Total '" * "
($ IN TlluuSANDS) 1984 1985
Dec   Jan       Feb       Mr         Apr   My an     Ari Asj Sm     10-1-tM to 9-3)E 7-1-tu to 9-2H6,
[
            .@fd'''I1MU      dI8"                                                                 _ .
Total Total '" * "
bh"ijits Irewstmusit Ircuse l'.rpents ty (W's
Oct Itw Dec Jan Feb Mr Apr My an Ari Asj Sm 10-1-tM to 9-3)E 7-1-tu to 9-2H6,
* fot Billitsjs
.@fd'''I1M dI8" U
* IOld! Rt.Ct'Ipts I)i hs soimts E X A M*P L E l'l.eit Ibigi/Erigineering thiestiwxt 6pignes.t l'I. set Gristrittlui/Gmpletion fiarstrittlui Cuitr.s ts Gerstru.tka Msuff luier's Resoistes (a) tia le.r fuel Leeitlesysicy frustccftzs Mal Dislasumuits
bh"ijits Irewstmusit Ircuse l'.rpents ty (W's fot Billitsjs IOld! Rt.Ct'Ipts I)i hs soimts E X A M*P L E l'l.eit Ibigi/Erigineering thiestiwxt 6pignes.t l'I. set Gristrittlui/Gmpletion fiarstrittlui Cuitr.s ts Gerstru.tka Msuff luier's Resoistes (a) tia le.r fuel Leeitlesysicy frustccftzs Mal Dislasumuits
(!!'I! *l!$60
(!!'I *l!$60
                                                                                                                                                          .. =::::::..: :: ::
.. =::::::..: :: ::
                                                                                                                                                                  -.. .... ....                    O*
O*
R o
R o
(a) Ira.luks payas avoyet, plait querattui mui corporate allocattat.
(a) Ira.luks payas avoyet, plait querattui mui corporate allocattat.
Line 162: Line 192:
08/03/83 ATTACHMENT 2 LICENSE MAINTENANCE
08/03/83 ATTACHMENT 2 LICENSE MAINTENANCE


==1.0     DESCRIPTION==
==1.0 DESCRIPTION==
OF LICENSES 1.1     LICENSE REQllIREMENTS AND WNP-3 LICENSE STATUS The Supply System currently possesses an Nuclear Regulatory Commission (NRC) construction permit for WNP-3. NRC regulations do not require that any phase of construction of a total project be completed on a specific schedule. The only requirement relating to construction schedule is that construction be completed by the latest completion date specified in the construction permit. The latest completion date may be extended by the NRC for " good cause". The WNP-3 Con-struction Permit (CP) specifies a latest construction completion date of January 1, 1985.
OF LICENSES 1.1 LICENSE REQllIREMENTS AND WNP-3 LICENSE STATUS The Supply System currently possesses an Nuclear Regulatory Commission (NRC) construction permit for WNP-3. NRC regulations do not require that any phase of construction of a total project be completed on a specific schedule. The only requirement relating to construction schedule is that construction be completed by the latest completion date specified in the construction permit. The latest completion date may be extended by the NRC for " good cause".
1.2     LICENSE EXTENSIONS It has been typical for NRC licensees to seek construction permit amendments to extend latest completion dates. Such amendments are usually granted. " Good cause" for such amendments can be demonstrated by factors beyond the licensee's control such as labor difficulties, changing regulatory requirements, and adverse economic conditions. However, applications for extension are required to be noticed in the Federal Register and an opportunity given for a public hearing if requested by an intervenor. It will be necessary to request an extention from the NRC prior to the construction completion date. However, it is not necessary to complete the process and obtain approval before the com-pletion date. Under NRC regulations, the Construction Permit will remain in effect pending NRC action on the request.
The WNP-3 Con-struction Permit (CP) specifies a latest construction completion date of January 1, 1985.
The Coalition for Safe Power, the intervenor on the WNP-3 Operating License application can be expected to intervene on the WNP-3 Construction Permit extention application. The Supply System's and the NP.C's legal staffs will be i
1.2 LICENSE EXTENSIONS It has been typical for NRC licensees to seek construction permit amendments to extend latest completion dates.
Such amendments are usually granted.
" Good cause" for such amendments can be demonstrated by factors beyond the licensee's control such as labor difficulties, changing regulatory requirements, and adverse economic conditions.
However, applications for extension are required to be noticed in the Federal Register and an opportunity given for a public hearing if requested by an intervenor.
It will be necessary to request an extention from the NRC prior to the construction completion date. However, it is not necessary to complete the process and obtain approval before the com-pletion date. Under NRC regulations, the Construction Permit will remain in effect pending NRC action on the request.
The Coalition for Safe Power, the intervenor on the WNP-3 Operating License application can be expected to intervene on the WNP-3 Construction Permit extention application. The Supply System's and the NP.C's legal staffs will be..
i


N/ awl @J required to develop and file briefs in opposition to the petition. A pre-hearing conference would then be required to determine whether the petition would be admitted and a hearing required. The review of petitions, conduct of the pre-hearing conference, and the conduct of the hearings is accomplished by a board of administrative law judges which constitute the Atomic Safety and Licensing Board.
N/ awl @J required to develop and file briefs in opposition to the petition. A pre-hearing conference would then be required to determine whether the petition would be admitted and a hearing required.
The review of petitions, conduct of the pre-hearing conference, and the conduct of the hearings is accomplished by a board of administrative law judges which constitute the Atomic Safety and Licensing Board.
Should a hearing be necessary, the Supply System's legal staff, licensing staff and the technical staff would be required to support the effort to contest the petition. Failure to support this activity could result in loss of the Con-struction Pemit.
Should a hearing be necessary, the Supply System's legal staff, licensing staff and the technical staff would be required to support the effort to contest the petition. Failure to support this activity could result in loss of the Con-struction Pemit.
1.3     NRC OVERVIEW 0F DELAY The NRC Inspection and Enforcement staff has a direct interest in the activities associated with preservation of the facility records and hardware. Their concerns were considered during the formulation of plans for deferral of WNP-3 construction, and they will be kept informed of pertinent activites.
1.3 NRC OVERVIEW 0F DELAY The NRC Inspection and Enforcement staff has a direct interest in the activities associated with preservation of the facility records and hardware. Their concerns were considered during the formulation of plans for deferral of WNP-3 construction, and they will be kept informed of pertinent activites.
While the NRC staff has the authority to require licensees to "show cause" why permits should not be modified, suspended or revoked in view of significant new information, the issuance of a "show cause" order solely because of an extended construction delay on WNP-3 is considered to be unlikely, particularly in view of the state of completion of the project and the likelihood of eventual re-sumption of construction. In response to a petition filed by the Coalition     for Safe Power to have the WNP-4/5 Construction Permits revoked because of the termination of these projects the NRC replied that the project terminations did not pose any hazard to public health and safety and as such the petition was denied.
While the NRC staff has the authority to require licensees to "show cause" why permits should not be modified, suspended or revoked in view of significant new information, the issuance of a "show cause" order solely because of an extended construction delay on WNP-3 is considered to be unlikely, particularly in view of the state of completion of the project and the likelihood of eventual re-sumption of construction.
In response to a petition filed by the Coalition for Safe Power to have the WNP-4/5 Construction Permits revoked because of the termination of these projects the NRC replied that the project terminations did not pose any hazard to public health and safety and as such the petition was denied.
The NRC has reversed their earlier position that no action would be taken on the Construction Pemit extension request fer WNP-1 until resumption of construc-tien. An extension was granted to June 1,1991 for completion of construction.
The NRC has reversed their earlier position that no action would be taken on the Construction Pemit extension request fer WNP-1 until resumption of construc-tien. An extension was granted to June 1,1991 for completion of construction.
,    Therefore, WNP-3 should be prepared to proceed with the extension process in the event a similar decision is reached on the WNP-3 application.
Therefore, WNP-3 should be prepared to proceed with the extension process in the event a similar decision is reached on the WNP-3 application.
_2_
_2_


08/03/83 As stated above, the NRC response to the Coalition for Safe Power petition to withdraw the construction permits for WNP-4/5 on the basis of their termination was that the terminations do not pose any hazard to public health and safety, and the petition was denied. The NRC staff is expected to take the same posi-tion with regard to the construction delay of WNP-3.
08/03/83 As stated above, the NRC response to the Coalition for Safe Power petition to withdraw the construction permits for WNP-4/5 on the basis of their termination was that the terminations do not pose any hazard to public health and safety, and the petition was denied.
1.4       SITE CERTIFICATION AGREEMENT As a requirement of State Law, parties desiring to construct energy facilities in excess of 250 megawatts must meet the application and certification require-ments of the Washington Energy Facility Site Evaluations Council (EFSEC). The Supply System has secured the requisite Site Certification Agreements for WNP-3.
The NRC staff is expected to take the same posi-tion with regard to the construction delay of WNP-3.
Early in 1982, the Supply System briefed EFSEC on the various stages of the termination process for WNP-4 and 5. On March 11, 1982, the Supply System requested EFSEC to defer any actions that would impact the Site Certification Agreements for WNP-4 and 5, as a facility with a license was definitely more marketable than one without. On April 12, 1982, EFSEC took formal action to concur with the request, and will postpone any consideration of Agreement amendments until later in 1983.
1.4 SITE CERTIFICATION AGREEMENT As a requirement of State Law, parties desiring to construct energy facilities in excess of 250 megawatts must meet the application and certification require-ments of the Washington Energy Facility Site Evaluations Council (EFSEC). The Supply System has secured the requisite Site Certification Agreements for WNP-3.
On May 20, 1982, the Supply System submitted a similar request to EFSEC for WNP-3. On June 14, 1982, EFSEC agreed "to continue to treat WNP-1 as a licensed facility and to take no action which would in any way diminish or jeopardize the current Site Certification Agreement for WNP-1." A similar agreement is ex-pected to be available for WNP-3 after discussions with EFSEC.
Early in 1982, the Supply System briefed EFSEC on the various stages of the termination process for WNP-4 and 5.
On March 11, 1982, the Supply System requested EFSEC to defer any actions that would impact the Site Certification Agreements for WNP-4 and 5, as a facility with a license was definitely more marketable than one without. On April 12, 1982, EFSEC took formal action to concur with the request, and will postpone any consideration of Agreement amendments until later in 1983.
On May 20, 1982, the Supply System submitted a similar request to EFSEC for WNP-3. On June 14, 1982, EFSEC agreed "to continue to treat WNP-1 as a licensed facility and to take no action which would in any way diminish or jeopardize the current Site Certification Agreement for WNP-1."
A similar agreement is ex-pected to be available for WNP-3 after discussions with EFSEC.
t i
t i


WASallNETON diaLIC PotEst SUPPLY SVSIDI                   AliACMM 3 IRACLEAR PROJECT ND. 3                           Sheet 1 of 2 CONSTRUCiloll FMIS CASH FLOW
WASallNETON diaLIC PotEst SUPPLY SVSIDI AliACMM 3 IRACLEAR PROJECT ND. 3 Sheet 1 of 2 CONSTRUCiloll FMIS CASH FLOW
($ Ill Ill0USAfss) 1984                                           1985 Total           Idil' ' " '
($ Ill Ill0USAfss) 1984 1985 Total Idil' ' " '
Oct   hr     Dec Jai     feb         Mu-     W     My   Ja   dal   Asg   S,   10-1-84 to 9-3}& 7-I-al to 9 .n m_
Oct hr Dec Jai feb Mu-W My Ja dal Asg S,
Dtyireil3   alace B                                                                                                -o-                     74000 bfD lawe.tmas.t Irroe 1500 P.ounts ty IW's                                                       1631   1140   2303   901     894       951     904   917   1138   907   907   908 t6 t Billings                                                                                                                                                     13501            12685 3805 2659   5375 2101     2087       2220     2108   2138   2655- 2117 2117   2117                       94815 31499 heal ikreipts                                                         $436 3799   7678 3002     2981       3171'   3012   3055   3793 3024 3024 3025       45000         Jgg               ,
10-1-84 to 9-3}& 7-I-al to 9.n m_
fli Jarsousas Piet DesigvErgituring                                                   452   454   457   459     461       464     467   470   473   470   470   470       5567           29211 husethasal Epipest                                                       569   357   1099   219     219       220     219   219   220   220   220   220       4001           50282 l' lait Gsstnttlu&mpletim                                                                                                                                           6682           68116 Gastnx. tim Cuar.scis                                               1532   442   594   435     410       593     4e'0 437   498   437   437   437       Sill           29385 Gsstnttim muir                                                       416   418   420   422     421       426     429   432   434   430   430   430       18310           51498 (kaar's Resuates (4)                                                   1465 1465   1465 1165     1465       1465     1465   1495   2165 1465 1465 1465       4668             3704 ina:les fin:1                                                               1     2   3643     2       2           3       2     2     3     2     2             1661           10085 3
Dtyireil3 alace -o-74000 B
(asitir9ny                                                             1000   661                                                                                                     739 h ustee Facs hAal Dislarsemias                                                     $436 3799   1678 3002     2981       3171     3012   3055   3793 30/4 3024 302'.     45ggg           243000 1:$
bfD lawe.tmas.t Irroe 1500 P.ounts ty IW's 1631 1140 2303 901 894 951 904 917 1138 907 907 908 13501 12685 t6 t Billings 3805 2659 5375 2101 2087 2220 2108 2138 2655-2117 2117 2117 31499 94815 heal ikreipts
          -- lies   j Halmre                                                                                         -C-   0-                                                                                                                                                                                                                   .n o
$436 3799 7678 3002 2981 3171' 3012 3055 3793 3024 3024 3025 45000 Jgg fli Jarsousas Piet DesigvErgituring 452 454 457 459 461 464 467 470 473 470 470 470 5567 29211 husethasal Epipest 569 357 1099 219 219 220 219 219 220 220 220 220 4001 50282 l' lait Gsstnttlu&mpletim 6682 68116 Gastnx. tim Cuar.scis 1532 442 594 435 410 593 4e'0 437 498 437 437 437 Sill 29385 Gsstnttim muir 416 418 420 422 421 426 429 432 434 430 430 430 18310 51498 (kaar's Resuates (4) 1465 1465 1465 1165 1465 1465 1465 1495 2165 1465 1465 1465 4668 3704 ina:les fin:1 1
k o
2 3643 2
(al lea:lules pvyaa meafsmst, plant quratim arut aalurele allocatim.                                                                                                                                           g
2 3
                                                                                                                                                                                                                        .e
2 2
3 2
2 3
1661 10085 (asitir9ny 1000 661 739 h ustee Facs hAal Dislarsemias
$436 3799 1678 3002 2981 3171 3012 3055 3793 30/4 3024 302'.
45ggg 243000 1:$ lies Halmre -C-0- -- j
.n ok o
(al lea:lules pvyaa meafsmst, plant quratim arut aalurele allocatim.
g
.e


t WASHIBGTON PUBLIC PoiKR SUPPLY SYSIEg                               ATTACHMENT 3 Ml8 CLEAR PROJECT No. 3                                     Sheet 2 of 2 CiNSTRUCT1081 fuse CASH FLOW (flOklU5hfE35')
t WASHIBGTON PUBLIC PoiKR SUPPLY SYSIEg ATTACHMENT 3 Ml8 CLEAR PROJECT No. 3 Sheet 2 of 2 CiNSTRUCT1081 fuse CASH FLOW (flOklU5hfE35')
1983                                                   1984 101Ai Aly     Aug     Set     Oct   br     Ibc     Jan           Mar                Asie    Aly
1983 1984 101Ai Aly Aug Set Oct br Ibc Jan
                                                                                            . Feb       4r     Mer               Asg     5+t     71-83 to 9-3tH4 tispelg B.alag             74000 58321 42370 30784 18292             6721                                     74000 i
. Feb Mar 4r Mer Asie Aly Asg 5+t 71-83 to 9-3tH4 tispelg B.alag 74000 58321 42370 30784 18292 6721 74000 Ihf d.5 i
Ihf d.5                                                                                                                                 i Inwestmas4 Innue             500   400       300     200   100 Penasts ty 100's           6891                                                                                                                   1500 6%0       5051   5396 4959     4606     4591 3629     2728 2257 3309     2247   2701 2199     1660 tot Billin.js                                                                                                                                     59184 4126     10811 8475     6366 5267   7720 5244   6301 5132     3874       63316 lotal ihreipts             7391   7360     5351   55 % 5059     8732   15402 12104     9094 7524 11029   7491   9002           5534 7331              124000 D,tgawasA,s, Plar th:sifVtrajirusing    2368     2303     2059 2677 2260         1820     1650 1686     1546 1346   1090   934     789   655     461       23644 Pngaatta,al Epipurg       5636     4637     5108 4438 4937         7276     4700 2002     1148   894   1633   997   1836   519     520       46281 PlaA Gmtrts.tia VDmpletim Gsistnttim Quitra.ts   7354   10217     5416 5636 4736         2920     5057 3384     2307 1555 4490   1647   2704 2562     1449       61434 cmt,u; tim Msurpr       1809   1913     1752   3288 2877     1666     1221 1394     1233 1238   1244 1366   1351 1128     794       24274 a,ar's Resentes (a)       5800     4129     2499   1947 1718     1668     2672 2527     1757 1389   1470 1362   1320 1465     1465       33188 h.les ru:)                     3     2         3       2     2         3         2       2     3     2     2     3       2     2       3         36 n,4 isayny                                                                           1100   1100 1100   1100' 1182   1000 1000     842       8424 Trmtce fit:s                 100   110       100     100   100     100       100       9                                                         719 lotal DistiswasAs         23070 23311       16937 18088 16630     15453   15402 12104     9094 7524 11029   7491   9002 7331     5534     198000 fidig Balare                   58323 42370 30784 18292 6721                                                                                                                                                                                                                     O (a) Ircluk:s puy.su aseymmt, pimt operatian ad corprate aWcatim.                                                                                                 A R
i Inwestmas4 Innue 500 400 300 200 100 1500 Penasts ty 100's 6891 6%0 5051 5396 4959 4606 4591 3629 2728 2257 3309 2247 2701 2199 1660 59184 tot Billin.js 4126 10811 8475 6366 5267 7720 5244 6301 5132 3874 63316 lotal ihreipts 7391 7360 5351 55 % 5059 8732 15402 12104 9094 7524 11029 7491 9002 7331 5534 124000 D,tgawasA,s, Plar th:si Vtrajirusing 2368 2303 2059 2677 2260 1820 1650 1686 1546 1346 1090 934 789 655 461 23644 f
b
Pngaatta,al Epipurg 5636 4637 5108 4438 4937 7276 4700 2002 1148 894 1633 997 1836 519 520 46281 PlaA Gmtrts.tia VDmpletim Gsistnttim Quitra.ts 7354 10217 5416 5636 4736 2920 5057 3384 2307 1555 4490 1647 2704 2562 1449 61434 cmt,u; tim Msurpr 1809 1913 1752 3288 2877 1666 1221 1394 1233 1238 1244 1366 1351 1128 794 24274 a,ar's Resentes (a) 5800 4129 2499 1947 1718 1668 2672 2527 1757 1389 1470 1362 1320 1465 1465 33188 h.les ru:)
                                                                                                                .                                                        r
3 2
3 2
2 3
2 2
3 2
2 3
2 2
3 36 n,4 isayny 1100 1100 1100 1100' 1182 1000 1000 842 8424 Trmtce fit:s 100 110 100 100 100 100 100 9
719 lotal DistiswasAs 23070 23311 16937 18088 16630 15453 15402 12104 9094 7524 11029 7491 9002 7331 5534 198000 fidig Balare 58323 42370 30784 18292 6721 O A
(a) Ircluk:s puy.su aseymmt, pimt operatian ad corprate aWcatim.
Rb r


08/03/83 ATTACHMENT 4 300HNOI1YA83S3Bdl!!,                               b a
08/03/83 ATTACHMENT 4 300HNOI1YA83S3Bdl!!,
ll           I
b ll I
                                                          / //            I
                                                                                    ~
3 5
G                                            /
                                                    !"/l  /
I E
M                                            I l//    l            l
                                                                                    ~
I dm 4
d
                                                /Illl                  i I
                                                                                  ~
                                                                                    ~
e-CD O  Z
                                              /
i        '
I 5$ 05  8E s              '
j                    l        '
h 8
e EE  a  a        lg*              )      :1 1  -
I E
os a w              l              /        //                I            .
U$ 5g  "                                  /      !R          I E    8 88        z                    /E i          /E          I            5. 8 o- z e ils                    /$/            I          I              -
g 5                              / s/ / sI          g                      $. S Es E      d          l        ///$I                                             l E
a
a
                            / // ,/         /
/ //
                                              /         gls; u
I
l                 -
~
g i     =                         /s       /                 i"I                 .
3
                    /
!"/l 5
                            /U        /               /           /              E
/
                          /           i 8
E I l//
        .        /     /        g&b"g/             /           /               .
G
l         .
/
m l
I M
D m
l l
e                                                   -
~I 4
8 I
/ ll i
~
>-dm d
Il I
~I e-
/
i CD O Z
j l
' h 5$ 05 s
8 EE 8E lg*
)
:1 1 I
E e
a os a w l
/
//
I a
/
!R I
E 8
U$
5g
/E i
/E I
: 5. 8 88 z
e ils
/$/
I g
/ s/
/ g I
o-z 5
Es sI S
E d
l
///$I l
E
//
/ gls; l
g a
/
,/
/
u i
=
/s
/
i"I
/U
/
/
/
E
/
/
g&b"g/
/
/
i 8
/
/
l m
l D
m e
8I


MONTH           CONTRACTOR CRAFT     CONTRACTOR NONMANl!AL EBASCO CM   ERASCO AE           SUPPLY SYSTEM
MONTH CONTRACTOR CRAFT CONTRACTOR NONMANl!AL EBASCO CM ERASCO AE SUPPLY SYSTEM
* TOTAL JULY                   250                 502                 380           280                   358         1770 AUGUST                 213                 357                 350           246                   280         1446 SEPTEMBER             179                 256                 300           232                   256         1223
* TOTAL JULY 250 502 380 280 358 1770 AUGUST 213 357 350 246 280 1446 SEPTEMBER 179 256 300 232 256 1223
~0CTOBER               135                 189                 250           211                   251         1036' NOVEMBER               113                 137                 250           200                   242         942 DECEMBER                 92                 117                 250           187                   231         877 JANUARY                 60                 96                 250           158                   228         792 FEBRUARY                 60                 90                 250           140                   226         766 MARCH                   60                 71                 250           118                   222         721 APRIL                   60                 66                 225           97                   219         667 MAY                     60                 54                 175           80                   214         583 JUNE                     60                 44                 125           72                   204         505 1342                 1979               3055         2021                 2931       11328 PRESERVATION MODE       45                   20                 80           50                   204         399
~0CTOBER 135 189 250 211 251 1036' NOVEMBER 113 137 250 200 242 942 DECEMBER 92 117 250 187 231 877 JANUARY 60 96 250 158 228 792 FEBRUARY 60 90 250 140 226 766 MARCH 60 71 250 118 222 721 APRIL 60 66 225 97 219 667 MAY 60 54 175 80 214 583 JUNE 60 44 125 72 204 505 1342 1979 3055 2021 2931 11328 PRESERVATION MODE 45 20 80 50 204 399
                                                                                                                            %?
%?
5! o
5! o
* NOTE: Supply System manpower includes equivalent manpower for indirect overhead and corporate allocation       h!,
* NOTE: Supply System manpower includes equivalent manpower for indirect overhead and corporate allocation h!,
as an estimated value.                                                                                 g; e
as an estimated value.
g; e
U1
U1


l MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY                                           ;
MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY 0F WNP-3 ILEVEL 111 AUGUST 4,1983 l
0F WNP-3 ILEVEL 111 AUGUST 4,1983 l
Washington Public Power Supply System
Washington Public Power Supply System


__          ..        .      __-_ _= _ -_.  ...
_= _ -_.
s                                                                                   !
s TABLE OF CONTENTS SECTION PAGE PLAN STRUCTURE i
TABLE OF CONTENTS SECTION                                 PAGE
1.0 FINANCIAL 1
:              PLAN STRUCTURE                                         i 1.0 FINANCIAL                                     1 2.0 LICENSING                                     4 3.0 ASSET PRESERVATION                           8 4.0 CONSTRUCTION ACTIVITIES                     12 5.0 ENGINEERING                                 15 6.0 QUALITY ASSURANCE                           18 7.0 DOCUMENTATION AND RECORDS                   21 8.0 COMMERCIAL ACTIONS                           25 9.0 MANAGEMENT OF EXTENDED CONSTRUCTION DELAY   30 2
2.0 LICENSING 4
3.0 ASSET PRESERVATION 8
4.0 CONSTRUCTION ACTIVITIES 12 5.0 ENGINEERING 15 6.0 QUALITY ASSURANCE 18 7.0 DOCUMENTATION AND RECORDS 21 8.0 COMMERCIAL ACTIONS 25 9.0 MANAGEMENT OF EXTENDED CONSTRUCTION DELAY 30 2
l s
l s
1 I
1 I
I
I


      ',                                                                            08/03/83 PLAN STRUCTURE LEVEL I - EXECUTIVE  
08/03/83 PLAN STRUCTURE LEVEL I - EXECUTIVE  


==SUMMARY==
==SUMMARY==
This portion is intended to provide executive level information relative to the plan, management principles and the most critical aspects of the construction delay.
This portion is intended to provide executive level information relative to the plan, management principles and the most critical aspects of the construction delay.
LEVEL II - DESCRIPTION OF PERFORMANCE BY FUNCTION This is intended to describe, at the management level, those functions which will or might be performed during the construction delay. This level II portion together with Level I constitutes middle management's guidelines.
LEVEL II - DESCRIPTION OF PERFORMANCE BY FUNCTION This is intended to describe, at the management level, those functions which will or might be performed during the construction delay.
LEVEL III - SUPPORTING DOCUMENTS These documents are all of the supporting procedures, data, budgets, etc., which support the Level II and I. These are internal documents and are not intended for consolidation or distribution outside the project except as may be required.
This level II portion together with Level I constitutes middle management's guidelines.
LEVEL III - SUPPORTING DOCUMENTS These documents are all of the supporting procedures, data, budgets, etc., which support the Level II and I.
These are internal documents and are not intended for consolidation or distribution outside the project except as may be required.
t l
t l
l l
l l
Line 273: Line 375:
i l
i l


                                                                                                                                            .                                    i a.
i a.
e t                                                                                                     .
e t
WASHilIETGIl PUBLIC PotER SUPPLY SYS1[N                                 TABLE I InsCLEAR PROJCCT IIG. 3                                     Sheet I of 2 COIISTRUCT1001 fille CA531 FLOW
TABLE I WASHilIETGIl PUBLIC PotER SUPPLY SYS1[N InsCLEAR PROJCCT IIG. 3 Sheet I of 2 COIISTRUCT1001 fille CA531 FLOW
                                                                                  - IfIlnliolfSAlms) 1983                                                       1984 10fn Aly       Aq     Set     att     hr       Dec     Jai     Feb   Mar   Apr   Mer   Ase   Aly   Ag     5:14     7-1-al to 94 34 tt36mint Dalate                74000 58321 42370 30784 18292               6721                       a. 3_               74000 NSli5 i                                                                                                                                       i Y       lemenst latime               500       400     300     200     100                                                                                     1500 P.yassts ty lau's             6891     6960     5051   5396 4959       4606       4591 3629     2728 2257 3309     2247 2701   2199     1660       59184 fu Billitys                                                               4126     10811 8475     6366 5267   7720 5244 6301   5132     3874       63316 lotal ikteipts               7391-     7360     5351   55 % 5059       8732     15402 12104     9094 7524 11029   7491 9002   7331     5534       124000 DiJanssasits Pl.m.t Desigi/Lrvjiruring   2368       2303     2059 2677 2260           1820     1650 1686     1546 1346   1090   9 34 789   655     461       23644 Iwpattael Erpalpiest         5636       4637     5108 4438 4937           7276       4700 2002     1148   894   1633   997 1836   519     520       46281 Plait Os6tna. tim /Qmgeletim Gsstnattim Gastracts       7354     10217     5416 5636 4736           2920       5057 3384     2307 1555 4490   1647 2704 2562       1449       61434 n.,structim Niayr         1809     1913     1752   3288 2877         1666     1221 1394     1233 1238   1244 1366 1351   1128     794       24274 asa r's inesamtes (a)       5800       4129     2499   1947   1718     1668       2672 2527     1757 1389   1470 1362 1320   1465     1465       33188 terlearFia:1                     3         2       3       2     2           3       2   *2         3     2     2     3     2     2       3           36 nadirmj sty                                                                                 1100   1100 1100   1100' 1182 1000   1000     842         8424 Trustee tws                   100       110     100     100   100       100       100       9                                                         719 Total Dislaswasats           23070 23311       16937 18088 16630       15453     15402 12104     9094 7524 11029   7491 9002   7331     5534       198000 Irshrg ibt.mm e                 58321 42370 30784 18292 6721                 - O'-                                                                                                                                                                                         I                           s 8
- IfIlnliolfSAlms) 1983 1984 10fn Aly Aq Set att hr Dec Jai Feb Mar Apr Mer Ase Aly Ag 5:14 7-1-al to 94 34 tt3 mint alate 74000 58321 42370 30784 18292 6721 a. 3_ 74000 6
i-b c
D i
(a) Incitales proyau asiagtment, plat geratim ard corporate ellacottm.                                                                                                     R-B 9
NSli5 i
Y lemenst latime 500 400 300 200 100 1500 P.yassts ty lau's 6891 6960 5051 5396 4959 4606 4591 3629 2728 2257 3309 2247 2701 2199 1660 59184 fu Billitys 4126 10811 8475 6366 5267 7720 5244 6301 5132 3874 63316 lotal ikteipts 7391-7360 5351 55 % 5059 8732 15402 12104 9094 7524 11029 7491 9002 7331 5534 124000 DiJanssasits Pl.m.t Desigi/Lrvjiruring 2368 2303 2059 2677 2260 1820 1650 1686 1546 1346 1090 9 34 789 655 461 23644 Iwpattael Erpalpiest 5636 4637 5108 4438 4937 7276 4700 2002 1148 894 1633 997 1836 519 520 46281 Plait Os6tna. tim /Qmgeletim Gsstnattim Gastracts 7354 10217 5416 5636 4736 2920 5057 3384 2307 1555 4490 1647 2704 2562 1449 61434 n.,structim Niayr 1809 1913 1752 3288 2877 1666 1221 1394 1233 1238 1244 1366 1351 1128 794 24274 asa r's inesamtes (a) 5800 4129 2499 1947 1718 1668 2672 2527 1757 1389 1470 1362 1320 1465 1465 33188 terlearFia:1 3
2 3
2 2
3 2
*2 3
2 2
3 2
2 3
36 nadirmj sty 1100 1100 1100 1100' 1182 1000 1000 842 8424 Trustee tws 100 110 100 100 100 100 100 9
719 Total Dislaswasats 23070 23311 16937 18088 16630 15453 15402 12104 9094 7524 11029 7491 9002 7331 5534 198000 Irshrg ibt.mm e 58321 42370 30784 18292 6721
- O'- I s
8 i - b c
(a) Incitales proyau asiagtment, plat geratim ard corporate ellacottm.
R-B 9


                                                                                    ~
~
08/03/83 1.0     FINANCIAL 1.1     GENERAL Funding of the WNP-3 extended construction delay is limited to approximately
08/03/83 1.0 FINANCIAL 1.1 GENERAL Funding of the WNP-3 extended construction delay is limited to approximately
  $243 million for the period July 1, 1983 through September 30, 1985 (this coincides with BPA's fiscal years). Scurces of funding are as follows:
$243 million for the period July 1, 1983 through September 30, 1985 (this coincides with BPA's fiscal years).
07/01/83 - 09/30/84 Construction & Fuel Fund Balance as of 6/30/83                     $    74.0 M Estimated Investment Income                                             1.5 M Payments by 100's                                                       59.5 M Payments by BPA                                                         63.0 M
Scurces of funding are as follows:
                                                                                $ 198.0 M 10/01/84 - 09/30/85 Payments by 100's                                                 $    13.5 M Payments by BPA                                                         31.5 M
07/01/83 - 09/30/84 Construction & Fuel Fund Balance as of 6/30/83 74.0 M Estimated Investment Income 1.5 M Payments by 100's 59.5 M Payments by BPA 63.0 M
                                                                                $    45.0 M Planned expenditures for the period January 1983 through September 30, 1985, must not exceed the cumulative BPA contribution profile. Table I summarizes the estimated cash expenditures through September 30, 1985.
$ 198.0 M 10/01/84 - 09/30/85 Payments by 100's 13.5 M Payments by BPA 31.5 M 45.0 M Planned expenditures for the period January 1983 through September 30, 1985, must not exceed the cumulative BPA contribution profile.
1.2     BUDGET AND CASH FLOW REQUIREMENTS See Attachment 1 to Executive Summary (Level I) of this Management Plan.
Table I summarizes the estimated cash expenditures through September 30, 1985.
e
1.2 BUDGET AND CASH FLOW REQUIREMENTS See Attachment 1 to Executive Summary (Level I) of this Management Plan.
_ _ _ _ _ _ _ _ _ . . _ . . _ _ __                    .J
e _ _ _ _ _ _ _ _ _.. _.. _
.J


vu
vu i
                                                                                                                                                                      .                                              i
(
(
i WASHINGTON PUBLIC P0lfR 541PPLY SYSIEN                                 TABLE I                                                         '
i WASHINGTON PUBLIC P0lfR 541PPLY SYSIEN TABLE I lefCLEAR PROJECT ND. 3 COIESTRUCTICII FUIS CASH FLOW Sheet 2 of 2
lefCLEAR PROJECT ND. 3                                                                                                       '
($Ill1HOUSAlmS) 1984 1985 Total lutal ' ~
COIESTRUCTICII FUIS CASH FLOW                                   Sheet 2 of 2
Oct kw Dec Jm Feb Mr 4r Mar Asi dal Asj Sep 10-1-Bi to 9-3&E 7-1-ni to 9 3) tt, Ikyi33 alare -o-74000 1 8 Sldd.5
($Ill1HOUSAlmS) 1984                                                     1985 Oct      kw                      Jm Total               lutal ' ~
.W Irwestmard httme l'. spuds ty IGPs 1631 1140.
Dec                       Feb       Mr     4r       Mar   Asi     dal       Asj     Sep   10-1-Bi to 9-3&E 7-1-ni to 9 3) tt, Ikyi33   1 alare 8                                                                                                                                                                                                          -o-                             74000 Sldd.5 W               Irwestmard httme l'. spuds ty IGPs           1631   1140 . 2303             901       894       951 1500 904     917   1838     907     907     908 ftt Dillisajs               3805   2659     5315         -2101         2087       2220   2108 13501                72685 2138 2655     2117 2117       2117         31499                 94815 Total Rareipts             5436   3799     7678           3CO2       2981       3171   3012     3055   3793   3024 3024         3025         45000           .
1500 2303 901 894 951 904 917 1838 907 907 908 13501 72685 ftt Dillisajs 3805 2659 5315
j69000 Iqslas sesuas l't.eit D stydigiarring     452     454       457             459       461       464   467     470     473     470     470 liqisdesal Dpi lsuit          569     357                                                                                               470          5567                29211 1099             219       219       220   219     219     220     220     220     220           4001               50282 l'I.e.t Gsistrutiud4mpletim 6mtru.tlui ContrdLis             442                                                                                                             668?                68116 1531                594             435       4l0       593   410     437     498     437     437     437                               29385 Osritna.tia; Mosfr       416     418       420             422       421       426   429     432     434 Sill 430     4 30     430         18310                 51493 insar's Resmates (a)       1465     1465     1465           1165       1465       1465   1465     1495 ris.les finel                                                                                              2165     1465   1465     1465           1668                 3704 i       2   3643                 2         2           3       2     2       3 i es Ainupsty                                                                                                            2       2         3         1661               10085 1000     661 h ustm fws                                                                                                                                                                 I19 lutal DivarsemuAs         $436   3799     7678           3002         2981       3171   3012     3055 3791     30J4   3024     3025 -                             243000
-2101 2087 2220 2108 2138 2655 2117 2117 2117 31499 94815 Total Rareipts 5436 3799 7678 3CO2 2981 3171 3012 3055 3793 3024 3024 3025 45000
                                                                                                  '                                                                45.000 0.hesj 1141mce                                                               -c-                                                                                                                                                                                                                 ..::::. .
. j69000 Iqslas sesuas l't.eit D stydigiarring 452 454 457 459 461 464 467 470 473 470 470 470 5567 29211 liqisdesal Dpi suit 569 357 1099 219 219 220 219 219 220 220 220 220 4001 50282 l
l'I.e.t Gsistrutiud4mpletim 668?
68116 6mtru.tlui ContrdLis 1531 442 594 435 4l0 593 410 437 498 437 437 437 Sill 29385 Osritna.tia; Mosfr 416 418 420 422 421 426 429 432 434 430 4 30 430 18310 51493 insar's Resmates (a) 1465 1465 1465 1165 1465 1465 1465 1495 2165 1465 1465 1465 1668 3704 ris.les finel i
2 3643 2
2 3
2 2
3 2
2 3
1661 10085 i es Ainupsty 1000 661 h ustm fws I19 lutal DivarsemuAs
$436 3799 7678 3002 2981 3171 3012 3055 3791 30J4 3024 3025 -
45.000 243000 0.hesj 1141mce -c-..::::..
s
s
                                                                                                                                                                                                  ~ - . . -
~ -.. -
                                                                                                                                                                                                                  'a
'a'Q (a) ha-Itals lirT;spissiinsL*ymit. [1144 pdian mal wate Olixdial.
                                                                                                                                                                                                                  'Q (a) ha-Itals lirT;spissiinsL*ymit. [1144 pdian mal wate Olixdial.                                                                                                                                     8 N
8N m
m


      ,                                                                            08/03/83 2.0       LICENSING 2.1       NOTIFICATIONS The NRC was formally advised of the 30 day construction delay decision by the Executive Board and the decision of July 8,1983 to implement an immediately
08/03/83 2.0 LICENSING 2.1 NOTIFICATIONS The NRC was formally advised of the 30 day construction delay decision by the Executive Board and the decision of July 8,1983 to implement an immediately construction delay until an assured source of funds becomes available to con-tinue construction. These notifications were made to both Nuclear Reactor Regulation (NRR-Bethesda) and Inspection and Enforcement (I&E - Region V) by formal letters.
,        construction delay until an assured source of funds becomes available to con-tinue construction. These notifications were made to both Nuclear Reactor Regulation (NRR-Bethesda) and Inspection and Enforcement (I&E - Region V) by formal letters. No other formal submittals are considered necessary at this time to maintain the WNP-3 Construction Permit or to satisfy normal practices of keeping the NRC informed of significant activities. A meeting with NRC staff (Bethesda)washeldonJuly 19, 1983 to review the Supply System's planning in regards to completion of the responses to NRC round one questions, completion of the environmental review and submittal of the construction delay implementation plan to the NRC staff. Additional meetings with the NRR and I&E staffs will be scheduled if it appears necessary to keep them informed of WNP-3 implementation plans.
No other formal submittals are considered necessary at this time to maintain the WNP-3 Construction Permit or to satisfy normal practices of keeping the NRC informed of significant activities.
Infonnal discussions were held with the Washington State Energy Facility Site Evaluation Council (EFSEC) officials on June 6, 1983, at which time the ac-tivities planned for the delay period were discussed. Formal notification to EFSEC of the extended construction delay was provided on August 1,1983.
A meeting with NRC staff (Bethesda)washeldonJuly 19, 1983 to review the Supply System's planning in regards to completion of the responses to NRC round one questions, completion of the environmental review and submittal of the construction delay implementation plan to the NRC staff. Additional meetings with the NRR and I&E staffs will be scheduled if it appears necessary to keep them informed of WNP-3 implementation plans.
2.2       LICENSING APPLICATIONS The operating license application for WNP-3 was docketed on August 22, 1983.
Infonnal discussions were held with the Washington State Energy Facility Site Evaluation Council (EFSEC) officials on June 6, 1983, at which time the ac-tivities planned for the delay period were discussed.
Formal notification to EFSEC of the extended construction delay was provided on August 1,1983.
2.2 LICENSING APPLICATIONS The operating license application for WNP-3 was docketed on August 22, 1983.
The Supply System responses to the NRC Safety and Environmental review questions l
The Supply System responses to the NRC Safety and Environmental review questions l
and issues will be limited due to the construction delay and funding limitations.
and issues will be limited due to the construction delay and funding limitations.
j         Emphasis will be placed on completing efforts in areas where closcout of issues l         appears feasible without major expenditures or where changes in technology are not expected to invalidate current efforts if a prolonged extended delay occurs.
j Emphasis will be placed on completing efforts in areas where closcout of issues l
l         The NRC Safety and Environmental reviews have proceeded to the point where:
appears feasible without major expenditures or where changes in technology are not expected to invalidate current efforts if a prolonged extended delay occurs.
i e         The environmental questions have been received and responses provided to the NRC staff.
l The NRC Safety and Environmental reviews have proceeded to the point where:
e        The NRC staff is prepared to generate a craf t invironhental statement.
i e
The completion is expected by Septembe,r.1983.                   '                      -
The environmental questions have been received and responses provided to the NRC staff.
i'                                                                                                      ~
The NRC staff is prepared to generate a craf t invironhental statement.
e         A series of six submittals of safety review questions (approximately 300) have been received. Three branches have not provided questions to.
e The completion is expected by Septembe,r.1983.
date. A significant fraction (approximately 2/3) are~ scheduled to'be completed and responses provided to the NRC staff.                 -
i
~
e A series of six submittals of safety review questions (approximately 300) have been received.
Three branches have not provided questions to.
date. A significant fraction (approximately 2/3) are~ scheduled to'be completed and responses provided to the NRC staff.
s.
s.
e        TheNRCstaffhasagreedtocompleteapartialdraft)afetyEvaluation                                                 .
TheNRCstaffhasagreedtocompleteapartialdraft)afetyEvaluation e
Report (SER) based upon the state of completion of question responses.                               1 2.3       OPERATING EXPERIENCE REVIEW WNP-3 nill continue to screen and review operating experience documents generated
Report (SER) based upon the state of completion of question responses.
  !        by NRC (Bulletins, Circulars, information notices), INPO (Operating Experience Reports - OERs), and Combustion Engineering (CE Infobulletins). Commitments   -
1 2.3 OPERATING EXPERIENCE REVIEW WNP-3 nill continue to screen and review operating experience documents generated by NRC (Bulletins, Circulars, information notices), INPO (Operating Experience Reports - OERs), and Combustion Engineering (CE Infobulletins). Commitments 4.
,                                                                                                  4 .           ,
made regarding design or operation which result frem.the reviews will be tracked for implementation later. WNP-3 will continue to respond to NRC Bullatins, as,
made regarding design or operation which result frem.the reviews will be tracked                                       ,
for implementation later. WNP-3 will continue to respond to NRC Bullatins, as ,                       '                  ~
necessary. The size of the operating experience documents backlog will be
necessary. The size of the operating experience documents backlog will be
                                                                                                                        '~
~
monitored and a plan will be generated during the construction delay perio'd to
monitored and a plan will be generated during the construction delay perio'd to
                                                                  ~
~ '
~
s ensure that the backlog can be worked off prior to fuel load.
s ensure that the backlog can be worked off prior to fuel load.
2.4       CURRENT ISSUES REVIEW As part of the ongoing efforts, the WNP-3 staff will continue participation in                                     l the Combustion Engineering'0wner's Group and Generic Issues Industry Groups as'
2.4 CURRENT ISSUES REVIEW As part of the ongoing efforts, the WNP-3 staff will continue participation in l
        -well as monitor generic licensing issues with the NRC and licensing activities on other Combustion Engineering plants.                                                                         '
the Combustion Engineering'0wner's Group and Generic Issues Industry Groups as'
i 2.5       REQUIRED ACTION l
-well as monitor generic licensing issues with the NRC and licensing activities on other Combustion Engineering plants.
2.5.1'   Licensing Actions
i 2.5 REQUIRED ACTION l
                                                                                          ,        s During the extended construction delay, Project Licensing will:
2.5.1' Licensing Actions s
l l         e         Complete review and approval of a portion of the NRC Round One questions.
During the extended construction delay, Project Licensing will:
l l
e Complete review and approval of a portion of the NRC Round One questions.,


                                                                  , ~, 4                                 m l                                                             x
, ~, 4 m
      ,  -                    e         Support Partial Draft SER from NRC e         Resolve Stiff Clamp Issue with NRC             '
l x
  -      Y                    e        Complete;subcoppartment pressurization analytical tasks in response to NRC' questions
e Support Partial Draft SER from NRC e
                                                  -~.s   ..
Resolve Stiff Clamp Issue with NRC Y
~
Complete;subcoppartment pressurization analytical tasks in response to e
e     -  Complete NRC requested Structural Audit & Site Visit u
NRC' questions
                ,              o         Schedule and Conduct Security Site Visit e        Participate in Licensing' Board Pre-hearing conference to resolve issue of which contentions will require litigation, e'       Complete CESSAR-F FDA Activities.
-~.s
L-   ,                      o         Complete Documentation of Licensing Commitments into General Tracking System (GTS).
~
                              ,e         Review commitment dates and develop basis for revision of dates to         ,
e Complete NRC requested Structural Audit & Site Visit u
reflect slowdown.
o Schedule and Conduct Security Site Visit Participate in Licensing' Board Pre-hearing conference to resolve issue e
                              ,e         Develop and submit FSAR/ER Amendments in support of Draft Environmental Statement (DES) and Draft Safety Evaluation Report (DSER).
of which contentions will require litigation, e'
Initiate application for Extention of Construction Permit (Expires e
Complete CESSAR-F FDA Activities.
1/1/85) e         Prepare Plans and Licensing Strategies on major issues.
L-o Complete Documentation of Licensing Commitments into General Tracking System (GTS).
e  '
,e Review commitment dates and develop basis for revision of dates to reflect slowdown.
Gather documentation and review critical files for completeness, e         Maintain involvement in CE Owners Group on shared basis with Project Engineering.
,e Develop and submit FSAR/ER Amendments in support of Draft Environmental Statement (DES) and Draft Safety Evaluation Report (DSER).
e         Maintain membership and participation in industry groups associated with generic issues.
e Initiate application for Extention of Construction Permit (Expires 1/1/85) e Prepare Plans and Licensing Strategies on major issues.
1 l
Gather documentation and review critical files for completeness, e
L               _ _ _ . . _ .          _        . _    ._            . . _ . . _ . _
e Maintain involvement in CE Owners Group on shared basis with Project Engineering.
e Maintain membership and participation in industry groups associated with generic issues.
1 l L


    ,                                                                            08/03/83 I
08/03/83 I
e     Monitor licensing meetings / hearings on other CE plants, o     Monitor NRC meetings / hearings /rulemakings on generic licensing issues and unresolved safety issues.
e Monitor licensing meetings / hearings on other CE plants, o
e     Continue interface with NRC and other regulatory agencies.
Monitor NRC meetings / hearings /rulemakings on generic licensing issues and unresolved safety issues.
2.5.2 Nuclear Safety Assurance Actions e     Complete establishment of the Operating Experience Review (0ER) data bas.e (tracking list),
e Continue interface with NRC and other regulatory agencies.
e     Screen Operating Experience Review (0ER) backlog.
2.5.2 Nuclear Safety Assurance Actions e
e     Screen, track and coordinate reviews of new incoming OER information.
Complete establishment of the Operating Experience Review (0ER) data bas.e (tracking list),
o     Evaluate OER information and prepare recommendations for appropriate management.
e Screen Operating Experience Review (0ER) backlog.
e    Review procedures for Plant Operations Committee (P0C) meetings.
e Screen, track and coordinate reviews of new incoming OER information.
e     Participate in resolution of remaining issues of field design change and NCR review council.
o Evaluate OER information and prepare recommendations for appropriate management.
o    Finalize development of the onsite Nuclear Safety Assessment Program Plan.
Review procedures for Plant Operations Committee (P0C) meetings.
e     Complete procedures for Operating Experience Reviews.
e Participate in resolution of remaining issues of field design change and e
e    Establish plans for nuclear safety assessment activities and procedures as necessary.
NCR review council.
Finalize development of the onsite Nuclear Safety Assessment Program o
Plan.
e Complete procedures for Operating Experience Reviews.
Establish plans for nuclear safety assessment activities and procedures e
as necessary. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _


      .                                                                                              08/03/83 3.0     ASSET PRESERVATION 3.1     PURPOSE To provide the methods to be utilized to preserve WNP-3 assets and the capacity for a rapid restart while optimizing Supply System financial and personnel resources.
08/03/83 3.0 ASSET PRESERVATION 3.1 PURPOSE To provide the methods to be utilized to preserve WNP-3 assets and the capacity for a rapid restart while optimizing Supply System financial and personnel resources.
3.2     OBJECTIVES / REQUIREMENTS 3.2.1   Preservation of Installed WNP-3 Assets Systems, components and structures must be preserved and maintained in the most cost effective manner possible to satisfy commercial, regulatory, and code requirements.
3.2 OBJECTIVES / REQUIREMENTS 3.2.1 Preservation of Installed WNP-3 Assets Systems, components and structures must be preserved and maintained in the most cost effective manner possible to satisfy commercial, regulatory, and code requirements.
Preservation considerations must ensure licensability of the plant and provide the capability for efficient and expedient resumption of start-up activities and operation of the plant. To satisfy these goals the following actions are to be taken:
Preservation considerations must ensure licensability of the plant and provide the capability for efficient and expedient resumption of start-up activities and operation of the plant. To satisfy these goals the following actions are to be taken:
e        Maintain a cold iron watch with the following responsibilities:
Maintain a cold iron watch with the following responsibilities:
                      - Operate temporary and permanent plant systems which are necessary to preserve the plant such as HVAC, Electrical Distribution, Lighting, and Dewatering, etc.
e
                      - Continuous security of plant island.
- Operate temporary and permanent plant systems which are necessary to preserve the plant such as HVAC, Electrical Distribution, Lighting, and Dewatering, etc.
                      - Provide control room functions for canmunications, maintenance activities and surveillances, etc.
- Continuous security of plant island.
                      - Operation of fire protection systam.
- Provide control room functions for canmunications, maintenance activities and surveillances, etc.
                      - Operate other plant systems necessary to facilitate extended plant construction delay such as construction water, sewage treatment, etc.
- Operation of fire protection systam.
l 4
- Operate other plant systems necessary to facilitate extended plant construction delay such as construction water, sewage treatment, etc.
l 4.


08/03/83 ,
08/03/83
l
- Maintain records of above activities to satisfy licensing and in-surance requirements.
                - Maintain records of above activities to satisfy licensing and in-surance requirements.
e Maintain a Maintenance and Technical force with the following responsi-bilities:
e       Maintain a Maintenance and Technical force with the following responsi-bilities:
- Evaluate, determine and implement required preservation activities.
                - Evaluate, determine and implement required preservation activities.
- Evaluate, determine and implement required long term preventive maintenance and preservation activities in the event of a prolonged construction delay.
                - Evaluate, determine and implement required long term preventive maintenance and preservation activities in the event of a prolonged construction delay.
- Correct deficiencies identified during preventive maintenance.
                - Correct deficiencies identified during preventive maintenance.
- Maintain temporary and permanent plant systems which are necessary to preserve the plant such as HVAC, Electrical Distribution, lighting, and Dewatering, etc.
                - Maintain temporary and permanent plant systems which are necessary to preserve the plant such as HVAC, Electrical Distribution, lighting, and Dewatering, etc.
- Maintain plant systems necessary to facilitate extended plant con-struction ' delay such as construction water, sewage treatment, etc.
                - Maintain plant systems necessary to facilitate extended plant con-struction ' delay such as construction water, sewage treatment, etc.
- Preserve and maintain existing Operational Spare Parts.
                - Preserve and maintain existing Operational Spare Parts. Procure, receive, store and issue parts and supplies necessary for plant preservation.
: Procure, receive, store and issue parts and supplies necessary for plant preservation.
                - Maintain all permanent plant activities to satisfy licensing and insurance requirements.
- Maintain all permanent plant activities to satisfy licensing and insurance requirements.
3.3     PRESERVATION OF RESTART / START-UP AND OPERATIONS CAPABILITIES WNP-3, at the time of construction delay, was at the point of Provisional Acceptance and Start de testing of several major plant systems. The permanent plant staff and the s. art-Up contractor conduct the start-up activities at WNP-3. The folicwing joint actions must be taken to preserve the ability to maintain the presently scheduled sequence between construction completion, start-up and operation of the plant:                                                 I l
3.3 PRESERVATION OF RESTART / START-UP AND OPERATIONS CAPABILITIES WNP-3, at the time of construction delay, was at the point of Provisional Acceptance and Start de testing of several major plant systems.
l l
The permanent plant staff and the s. art-Up contractor conduct the start-up activities at WNP-3.
The folicwing joint actions must be taken to preserve the ability to maintain the presently scheduled sequence between construction completion, start-up and operation of the plant: '
1
1


N     I e         Complete fragnet development to support cold hydro testing.
N I
e       Maintain presently existing programs and procedures.
e Complete fragnet development to support cold hydro testing.
e       Develop the procedures to start up those systems necessary to preserve the plant.
e Maintain presently existing programs and procedures.
e       Maintain the inventory of plant components / systems to support both preservation, construction completion and start-up of the plant.
e Develop the procedures to start up those systems necessary to preserve the plant.
                          - Material Equipment List (MEL)/ Construction Commodity Control Systems (CCCS) completion, integration and upgrading.
e Maintain the inventory of plant components / systems to support both preservation, construction completion and start-up of the plant.
                          - Field verification and identification of installed equipment to support preservation and permanent plant documentation, e       Review the start-up schedule through commercial operation, develop detailed fragnets, levelize system acceptance dates and integrate into the master construction schedule.
- Material Equipment List (MEL)/ Construction Commodity Control Systems (CCCS) completion, integration and upgrading.
                          - Maintain records of above activities to satisfy licensing and in-l                             surance requirements.
- Field verification and identification of installed equipment to support preservation and permanent plant documentation, e
l 3.4     BENEFITS i
Review the start-up schedule through commercial operation, develop detailed fragnets, levelize system acceptance dates and integrate into the master construction schedule.
e       Performance of the above actions will result in the following:
- Maintain records of above activities to satisfy licensing and in-l surance requirements.
                          - Minimize the financial loss to the Supply System by retaining those highly technical personnel recruited and trained at great expense.
l 3.4 BENEFITS i
e Performance of the above actions will result in the following:
- Minimize the financial loss to the Supply System by retaining those highly technical personnel recruited and trained at great expense.
I
I
                          - Retention of the personnel necessary to ensure licensability, start-up and operation of the plant.
- Retention of the personnel necessary to ensure licensability, start-up and operation of the plant.
l                         - Ensures the most cost effective and highest quality maintenance and preservation of the plant.
l
- Ensures the most cost effective and highest quality maintenance and preservation of the plant....- - _..


senmin n
senmin n s
  ,    s Provides maximum opportunity for owner involvem:nt throughout the extended delay and resumption of start-up activities.
Provides maximum opportunity for owner involvem:nt throughout the extended delay and resumption of start-up activities.
Provides maximum opportunity for permanent plant personnels' familiar-ization with plant systems and components which will enhance the cost effectiveness of subsequent start-up and operations.
Provides maximum opportunity for permanent plant personnels' familiar-ization with plant systems and components which will enhance the cost effectiveness of subsequent start-up and operations.
                        - Provides the minimum required capacity for restart capability.
- Provides the minimum required capacity for restart capability.
+
+
l 1
l 1
t 1
t 1._ -,, _


4.0     CONSTRUCTION ACTIVITIES 4.1     Construction Objectives The primary Construction objectives to support the extended delay are:
4.0 CONSTRUCTION ACTIVITIES 4.1 Construction Objectives The primary Construction objectives to support the extended delay are:
e       Bring work to a logical and reasonable stopping point.
e Bring work to a logical and reasonable stopping point.
e       Support the turnover of documentation through the clearing of Non Confor-mance Reports (NCRs), Document Deficiency Notices (DDNs), Conditional Releases and completion of in-process work.
e Support the turnover of documentation through the clearing of Non Confor-mance Reports (NCRs), Document Deficiency Notices (DDNs), Conditional Releases and completion of in-process work.
e        Implement cost effective plans to complete work required to preserve assets and ensure capability of construction restart.
Implement cost effective plans to complete work required to preserve e
4.2     CONSTRUCTION PLAN Construction activities have been reviewed in detail for each construction contract. The activities identified below represent the minimum effort required to provide a controlled rampdown and prepare the project for an extended con-struction delay. The asset preservation program reflects the local atmospheric conditions (i.e., high humidity) and the associated detrimental effects on equipment. Inherent in the construction plan is preparation and implementation of long tenn preservation of assets, securing quality assurance documentation, inventorying and assuming custody of all permanent material and equipment.
assets and ensure capability of construction restart.
4.2 CONSTRUCTION PLAN Construction activities have been reviewed in detail for each construction contract.
The activities identified below represent the minimum effort required to provide a controlled rampdown and prepare the project for an extended con-struction delay. The asset preservation program reflects the local atmospheric conditions (i.e., high humidity) and the associated detrimental effects on equipment.
Inherent in the construction plan is preparation and implementation of long tenn preservation of assets, securing quality assurance documentation, inventorying and assuming custody of all permanent material and equipment.
The proposed plan provides the following types of work:
The proposed plan provides the following types of work:
o       Complete in-process welds and associated Non Destructive Examination (NDE) work.
o Complete in-process welds and associated Non Destructive Examination (NDE) work.
e       Complete fire protection pumps and tanks and energize completed portions of permanent system.
e Complete fire protection pumps and tanks and energize completed portions of permanent system.
e       Complete mechanical and electrical work at makeup water wells. (Necessary to provide ability to cycle pumps.)
e Complete mechanical and electrical work at makeup water wells.
(Necessary to provide ability to cycle pumps.)
l 08/03/83 l
l 08/03/83 l
e     Complete certain identified terminations, and pull pre-cut cable.
e Complete certain identified terminations, and pull pre-cut cable.
(Facilitates equipment closure.)
(Facilitates equipment closure.)
e     Install cathodic protection necessary for long term layup.   (Engineering requirement regardless of term of layup.)
e Install cathodic protection necessary for long term layup.
e     Perform touch up painting and coating, as specified, such as external steel surface areas of the containment vessel. (Required to remain withindesigncorrosionallowance.)
(Engineering requirement regardless of term of layup.)
e     Complete weatherizing of administration building and site access facility.
e Perform touch up painting and coating, as specified, such as external steel surface areas of the containment vessel.
(Required to remain withindesigncorrosionallowance.)
e Complete weatherizing of administration building and site access facility.
(Requirement for preservation of permanent assets located and stored within these facilities.)
(Requirement for preservation of permanent assets located and stored within these facilities.)
e     Continue care and maintenance on equipment as identified by the Con-struction Manager; start turnover of asset preservation responsibilities to Owner.
e Continue care and maintenance on equipment as identified by the Con-struction Manager; start turnover of asset preservation responsibilities to Owner.
e    Install Reactor Vessel (RV) head and layup Nuclear Steam Supply System (NSSS) system.
Install Reactor Vessel (RV) head and layup Nuclear Steam Supply System e
e     Inventory and assure custody of Owner and Contractor furnished permanent plant materials and equipment.
(NSSS) system.
e     Review, disposition, and closecut as appropriate NCRs, DDNs and Con-ditional Releases.
e Inventory and assure custody of Owner and Contractor furnished permanent plant materials and equipment.
e     Carry out drawing roll-up and documentation turnover on all completed work.
e Review, disposition, and closecut as appropriate NCRs, DDNs and Con-ditional Releases.
e . Bring documentation to current state on all partially completed work and turnover to the Construction Manager.
e Carry out drawing roll-up and documentation turnover on all completed work.
e     Perform walkdown of plant and enter status in Construction Commodity Control System (CCCS) and support design verification program as directed by the Construction Manager.
Bring documentation to current state on all partially completed work and e
turnover to the Construction Manager.
e Perform walkdown of plant and enter status in Construction Commodity Control System (CCCS) and support design verification program as directed by the Construction Manager.. _ -.


08/03/83 e       Energization of the 230 KV line.   (Cable manufacturer recommendation for long term preservation.)
08/03/83 e
Energization of the 230 KV line.
(Cable manufacturer recommendation for long term preservation.)
It has been determined all activities recommended are essential to preservation of assets.
It has been determined all activities recommended are essential to preservation of assets.
4.3     ADDITIONAL CONSTRUCTION RECOMMENDATIONS Excluded from the plan due to financial constraints but recommended by the AE/CM for long term preservation, are the below listed activities. It is emphasized that, while undesirable, the Project can fully recover from these delays.
4.3 ADDITIONAL CONSTRUCTION RECOMMENDATIONS Excluded from the plan due to financial constraints but recommended by the AE/CM for long term preservation, are the below listed activities.
e       Complete concrete placement of Reactor Building Dome.
It is emphasized that, while undesirable, the Project can fully recover from these delays.
o       Class I backfill and associated mechanical and electrical work.
e Complete concrete placement of Reactor Building Dome.
e       Energization of permanent plant heating and ventilation system (freeze protection).
o Class I backfill and associated mechanical and electrical work.
e       Complete balance of permanent fire protection system.
e Energization of permanent plant heating and ventilation system (freeze protection).
e       Install crane access exterior doors of Fuel Handling Building.
e Complete balance of permanent fire protection system.
e       Complete assembly of HESS structure and store in Reactor Building.
e Install crane access exterior doors of Fuel Handling Building.
e       Install construction access hatch in Reactor Building.
e Complete assembly of HESS structure and store in Reactor Building.
9
e Install construction access hatch in Reactor Building.
9.


  ',                                                                            08/03/83 5.0       ENGINEERING The extended construction delay engineering Management Plan has been structured to fulfill the primary objectives of preserving the engineering design status of WNP-3 Project; to preserve the engineering in consonance with the licensing process; and to immediately support design completion, construction and start-up at the time an assured source of funding for continued construction can be obtained.
08/03/83 5.0 ENGINEERING The extended construction delay engineering Management Plan has been structured to fulfill the primary objectives of preserving the engineering design status of WNP-3 Project; to preserve the engineering in consonance with the licensing process; and to immediately support design completion, construction and start-up at the time an assured source of funding for continued construction can be obtained.
5.1       ENGINEERING PROGRAM OBJECTIVES The primary objectives to be accomplished at Project WNP-3 during the extended construction delay time frame are:
5.1 ENGINEERING PROGRAM OBJECTIVES The primary objectives to be accomplished at Project WNP-3 during the extended construction delay time frame are:
e         Support Licensing activities necessary to preserve all state and federal licensability requirements.
e Support Licensing activities necessary to preserve all state and federal licensability requirements.
e         Finish work currently on the board and not start any new work.
e Finish work currently on the board and not start any new work.
e         Documentation / records will be gathered and vaulted.
e Documentation / records will be gathered and vaulted.
e         Non Conformance Reports (NCRs) will be dispositioned or closed out for the terminated contracts / contractors.
e Non Conformance Reports (NCRs) will be dispositioned or closed out for the terminated contracts / contractors.
e         Vendor equipment qualification activities will be closed out.
e Vendor equipment qualification activities will be closed out.
e         ASME Code requirements will be preserved to permit restart, e         Provisional acceptance activities will be held in abeyance until restart of construction.
e ASME Code requirements will be preserved to permit restart, e
9 5.2       SCOPE OF ENGINEERING ACTIVITIES Specific Engineering activities are required to preserve the design and to enable the project to restart with minimal effort at any time during the period associated with the extended construction delay. During the extended construction delay period, priority will be given to the following activities:
Provisional acceptance activities will be held in abeyance until restart of construction.
03/03/83 e     Engineering activities on WNP-3 will continue et a limited level for those specific identified activities. A documentation / drawing roll-up function will be performed where and when appropriate during this period.
9 5.2 SCOPE OF ENGINEERING ACTIVITIES Specific Engineering activities are required to preserve the design and to enable the project to restart with minimal effort at any time during the period associated with the extended construction delay.
During the extended construction delay period, priority will be given to the following activities:
03/03/83 e
Engineering activities on WNP-3 will continue et a limited level for those specific identified activities.
A documentation / drawing roll-up function will be performed where and when appropriate during this period.
During the extended construction delay period, the following engineering activities have been identified as those that will be continued on a limited basis.
During the extended construction delay period, the following engineering activities have been identified as those that will be continued on a limited basis.
            - Complete Dry Cooling Tower Design
- Complete Dry Cooling Tower Design
            - Resolve Equipment Nozzle Load Discrepancies
- Resolve Equipment Nozzle Load Discrepancies
            - Develop Mechanical Equipment Qualification Plan
- Develop Mechanical Equipment Qualification Plan
            - Track System Review Open Items
- Track System Review Open Items
            - Resolve Equipment Qualification Open Items
- Resolve Equipment Qualification Open Items
            - Resolve Stiff Clamp Concerns
- Resolve Stiff Clamp Concerns
            - Review Engineering Baseline For Completeness
- Review Engineering Baseline For Completeness
            - Maintain Piping & Instrument Diagram Drawir.gs
- Maintain Piping & Instrument Diagram Drawir.gs
            - Continue Change Management Activities
- Continue Change Management Activities
            - Continue System Design Freeze Activities
- Continue System Design Freeze Activities
            - Monitor Chehalis Riverbank Protection in the vicinity of the Ranney Wells
- Monitor Chehalis Riverbank Protection in the vicinity of the Ranney Wells
            - Identify and select records to be gathered and vaulted
- Identify and select records to be gathered and vaulted
            - Complete Actions Items List from System Review Program
- Complete Actions Items List from System Review Program
            - Participate in CE Owner's Group activities in an overview role rather than as an active participant, e     Work will be completed to the extent necessary to satisfy existing ASME Code requirements or to allow bridging of ASME requirements on project restart.
- Participate in CE Owner's Group activities in an overview role rather than as an active participant, e
e     A review of all remaining engineering activities for plant completion will be conducted followed by preparation of a detailed scope of work
Work will be completed to the extent necessary to satisfy existing ASME Code requirements or to allow bridging of ASME requirements on project restart.
          , for plant completion activities.
e A review of all remaining engineering activities for plant completion will be conducted followed by preparation of a detailed scope of work for plant completion activities.
e     Engineering support to the structures and security reviews requested by the NRC will be completed according to the current schedule of October 1, 1983.
e Engineering support to the structures and security reviews requested by the NRC will be completed according to the current schedule of October 1, 1983.,
08/03/83 e       Detailed program plans will be developed for performance of a technical review of ASME design / stress reports to assure Owner's compliance with NA or NCA-3260, and for implementation of an independent design verifi-cation of selected WNP-3 safety related systems.
 
e       Continue to interface with Washington State Regulatory Agencies to preserve Site Certification Agreement, e       Review NRC bulletins for required engineering actions.
08/03/83 e
s'       The Change Management process will continue to exist with all forms of Project Change Proposals (PCPs) available for use. The PCP process will be simplified to the extent practical. Change dispositions of Deferred and Approved / Deferred will be added to the process as many decisions will relate only to concept with actual funding and implementation deferred.
Detailed program plans will be developed for performance of a technical review of ASME design / stress reports to assure Owner's compliance with NA or NCA-3260, and for implementation of an independent design verifi-cation of selected WNP-3 safety related systems.
5.3     ENGINEERING ACTIVITIES DEFERRED During the extended construction delay of WNP3, a number of engineering acti-vities previously identified in the FY84 budget will be deferred or reduced in scope because of limited funding. Examples of these activities are as follows:
e Continue to interface with Washington State Regulatory Agencies to preserve Site Certification Agreement, e
e       Design Change /NCR Council Activities e       TMI Action Items e       Design Verification e       ASME Section XI Programs e       As-Built Program o       Security System Procurement e       Chehalis River Work Completion e    -  Control Room Human Factors Review e       Game Mitigation Plan Design and Implementation e       Certain ASME Owner's Designee Activities l
Review NRC bulletins for required engineering actions.
l 1
s' The Change Management process will continue to exist with all forms of Project Change Proposals (PCPs) available for use.
i 1                           -                  -                                      .      .
The PCP process will be simplified to the extent practical. Change dispositions of Deferred and Approved / Deferred will be added to the process as many decisions will relate only to concept with actual funding and implementation deferred.
5.3 ENGINEERING ACTIVITIES DEFERRED During the extended construction delay of WNP3, a number of engineering acti-vities previously identified in the FY84 budget will be deferred or reduced in scope because of limited funding.
Examples of these activities are as follows:
e Design Change /NCR Council Activities e
TMI Action Items e
Design Verification e
ASME Section XI Programs e
As-Built Program o
Security System Procurement e
Chehalis River Work Completion Control Room Human Factors Review e
e Game Mitigation Plan Design and Implementation e
Certain ASME Owner's Designee Activities l
l 1 i 1


            .                                                                          08/03/83           i
08/03/83 i
          ,    .-                                                                                          1 6.0     0'JALITY ASSURANCE l,
1 6.0 0'JALITY ASSURANCE l
i             The extended construction delay program addresses the following Quality Assurance requirements necessary to preserve assets, plant licensability, and support
i The extended construction delay program addresses the following Quality Assurance requirements necessary to preserve assets, plant licensability, and support subsequent construction completion and plant start-up.
,            subsequent construction completion and plant start-up.
6.1 QUALITY ASSURANCE PROGRAM The Supply System Design and Construction Quality Assurance Requirements and l
6.1     QUALITY ASSURANCE PROGRAM The Supply System Design and Construction Quality Assurance Requirements and Operational Quality Assurance Program Description will continue to be imple-l
Operational Quality Assurance Program Description will continue to be imple-
]             mented during the extended construction delay. Applicability of the programs i
]
will be based on existing organizational structure and responsibilities. The
mented during the extended construction delay. Applicability of the programs i
  ,          Project Quality Assurance organization will continue to be primarily responsible for Project /AE/CM overview while the Plant Quality Assurance organization will j             be responsible for overview of the plant organization.
will be based on existing organizational structure and responsibilities. The Project Quality Assurance organization will continue to be primarily responsible for Project /AE/CM overview while the Plant Quality Assurance organization will j
be responsible for overview of the plant organization.
]
]
,            6.2     PRESERVATION AND STORAGE REQUIREMENTS i
6.2 PRESERVATION AND STORAGE REQUIREMENTS i
1             Installed or warehoused equipment shall be maintained in accordance with manu-facturer's recommendations and/or applicable design requirements and standards,
1 Installed or warehoused equipment shall be maintained in accordance with manu-facturer's recommendations and/or applicable design requirements and standards,
)
)
or Engineering-approved alternatives.
or Engineering-approved alternatives.
Implementation of the asset preservation program by the plant organization for l
l Implementation of the asset preservation program by the plant organization for installed equipment shall be verified by Supply System Quality Assurance through site surveillances/ audits.
;            installed equipment shall be verified by Supply System Quality Assurance through site surveillances/ audits.
Implementation of the asset. preservation program for warehoused equipment and l
>            Implementation of the asset. preservation program for warehoused equipment and l             ASME materials shall be verified by Ebasco Quality Assurance through site audits.
ASME materials shall be verified by Ebasco Quality Assurance through site audits.
6.3     PROCEDURES / INSTRUCTIONS l
6.3 PROCEDURES / INSTRUCTIONS l
Applicable existing procedures will continue to be implemented to assure that
Applicable existing procedures will continue to be implemented to assure that the quality of materials, components and structures, including partially com-pleted structures, is adequately preserved during the period of the construction l.-.
!            the quality of materials, components and structures, including partially com-pleted structures, is adequately preserved during the period of the construction l


08/03/83 delay. Additional procedures will be developed and implemented as necessary to describe turnover of responsibilities for the preservation of assets.
08/03/83 delay. Additional procedures will be developed and implemented as necessary to describe turnover of responsibilities for the preservation of assets.
6.4     RECORDS Documentation for work completed (and partially completed), including main-tenance and qualification records, will be reviewed, accepted, maintained, and stored in a record storage facility to which the Supply System has assured access.
6.4 RECORDS Documentation for work completed (and partially completed), including main-tenance and qualification records, will be reviewed, accepted, maintained, and stored in a record storage facility to which the Supply System has assured access.
The status of construction tests and inspections performed prior to suspension of work will also be documented, reviewed and stored in a records facility accessible to the Supply System.
The status of construction tests and inspections performed prior to suspension of work will also be documented, reviewed and stored in a records facility accessible to the Supply System.
6.5     ASME CODE WORK The Construction Manager's ASME Manual will continue to be in effect.
6.5 ASME CODE WORK The Construction Manager's ASME Manual will continue to be in effect.
6.6     QUALITY ASSURANCE ACTIVITIES DURING TURNDOWN AND PROJECT DELAY The following QA responsibilities will continue during the WNP-3 extended construction delay, with primary focus on preservation of assets and control of quality records. Extended construction delay activities shall be accomplished in accordance with NRC requirements and Supply System connitments.
6.6 QUALITY ASSURANCE ACTIVITIES DURING TURNDOWN AND PROJECT DELAY The following QA responsibilities will continue during the WNP-3 extended construction delay, with primary focus on preservation of assets and control of quality records.
e        Maintain control of notifications, corrective actions and commitments to the NRC.
Extended construction delay activities shall be accomplished in accordance with NRC requirements and Supply System connitments.
                - Verify corrective actions and closecut of NRC items.
Maintain control of notifications, corrective actions and commitments to e
                - Track ongoing commitments to NRC.
the NRC.
                - Status all NRC items from Construction Permit to present to facilitate restart.
- Verify corrective actions and closecut of NRC items.
e       Overview and monitor AE/CM and Contract Quality Assurance activities.
- Track ongoing commitments to NRC.
- Status all NRC items from Construction Permit to present to facilitate restart.
e Overview and monitor AE/CM and Contract Quality Assurance activities. ___


      .                                                                          08/03/83 e   Surveillance of as-built / status of work.
08/03/83 e
            - Participate in development of program for closecut and statusing of construction work.
Surveillance of as-built / status of work.
            - Overview development of ASME partial N-5 data reports.
- Participate in development of program for closecut and statusing of construction work.
e   Overview and audit records turnover, records review and records storage.
- Overview development of ASME partial N-5 data reports.
            - Verify records review and statusing processes are working.
e Overview and audit records turnover, records review and records storage.
            - Verify contractors installing ASME Section III systems implement programs for ' completing partial N-5 data reports.
- Verify records review and statusing processes are working.
            - Verify systems are implemented to confirm records reflect hardware.
- Verify contractors installing ASME Section III systems implement programs for ' completing partial N-5 data reports.
e   Verify proper identification, reporting and disposition of nonconformances.
- Verify systems are implemented to confirm records reflect hardware.
e   Evaluate deficiencies as defined by 10CFR50.55(e) and 10CFR21.
e Verify proper identification, reporting and disposition of nonconformances.
e   Monitor development of WNP-3 asset preservation program and conduct surveillances to verify implementation, e   Close out open audit findings.
e Evaluate deficiencies as defined by 10CFR50.55(e) and 10CFR21.
e   Perform vendor surveillances.
e Monitor development of WNP-3 asset preservation program and conduct surveillances to verify implementation, e
Close out open audit findings.
e Perform vendor surveillances.


08/03/83 7.0     DOCUMENTATION AND RECORDS This section describes the requirements for records and documents needed to preserve the assets of WNP-3 and to assure licensability.
08/03/83 7.0 DOCUMENTATION AND RECORDS This section describes the requirements for records and documents needed to preserve the assets of WNP-3 and to assure licensability.
7.1     RECORDS REQUIREMENTS In order to preserve the assets of the project, all WNP-3 documents 2.nd records must be collected, reviewed, indexed and stored at the Project Site during the extended construction delay. Documents and records in the custody of the Contractors will be collected, processed and stored in a central on-site records facility by the AE/CM. Except as noted in Section 7.2, records and documents presently in the custody of the Supply System will be received, maintained, processed and stored for the Supply System by the AE/CM in a central on-site records fac lity in accordance with existing Supply System procedures and standards, and in accordance with user needs as to form, storage and retrieval requirements.
7.1 RECORDS REQUIREMENTS In order to preserve the assets of the project, all WNP-3 documents 2.nd records must be collected, reviewed, indexed and stored at the Project Site during the extended construction delay. Documents and records in the custody of the Contractors will be collected, processed and stored in a central on-site records facility by the AE/CM.
The consolidation of the records processing activities within one organization at the site will assist in establishing the Records Transition organization to systematically collect, process, store and retrieve documentation to ensure a complete set of documents and records to complete construction, test and start-up and to license, support and operate the plant. Specific requirements by organization are described in the following subsections.
Except as noted in Section 7.2, records and documents presently in the custody of the Supply System will be received, maintained, processed and stored for the Supply System by the AE/CM in a central on-site records fac lity in accordance with existing Supply System procedures and standards, and in accordance with user needs as to form, storage and retrieval requirements.
t    7.1.1   Architect / Engineer and Construction Manager (AE/CM) l
The consolidation of the records processing activities within one organization at the site will assist in establishing the Records Transition organization to systematically collect, process, store and retrieve documentation to ensure a complete set of documents and records to complete construction, test and start-up and to license, support and operate the plant.
(     The AE/CM shall retain all records currently in their custody and shall maintain I     within one records processing facility records currently in the custody of the Supply System except as noted in subsection 7.2.
Specific requirements by organization are described in the following subsections.
7.1.1 Architect / Engineer and Construction Manager (AE/CM) t l
(
The AE/CM shall retain all records currently in their custody and shall maintain I
within one records processing facility records currently in the custody of the Supply System except as noted in subsection 7.2.
i The AE/CM shall identify, collect, review, accept and maintain all contractor I
i The AE/CM shall identify, collect, review, accept and maintain all contractor I
documents and records currently not in AE/CM custody.
documents and records currently not in AE/CM custody.
l The AE/CM shall establish a records receipt, review, indexing, microfilming and data entry function in accordance with established Supply System procedures and l
l The AE/CM shall establish a records receipt, review, indexing, microfilming and data entry function in accordance with established Supply System procedures and l _-
    .                                                                              08/03/83 standards to ensure retrievability of all WNP-3 documents and records to main-tain licensability during the construction slowdown and ensure a complete set of records to complete construction, test and start-up and to support and operate the plant.
 
08/03/83 standards to ensure retrievability of all WNP-3 documents and records to main-tain licensability during the construction slowdown and ensure a complete set of records to complete construction, test and start-up and to support and operate the plant.
The AE/CM shall provide training to Supply System personnel to ensure orderly turnover of documents, records, and record processing systems prior to com-mercial operation.
The AE/CM shall provide training to Supply System personnel to ensure orderly turnover of documents, records, and record processing systems prior to com-mercial operation.
7.1.2     Contractors Contractors will submit their records to the AE/CM as noted in subsection 7.1.1 unless otherwise directed by the Program Director. The Supply System will verify adequacy of records received, reviewed and accepted by tne AE/CM by audit surveillance.
7.1.2 Contractors Contractors will submit their records to the AE/CM as noted in subsection 7.1.1 unless otherwise directed by the Program Director. The Supply System will verify adequacy of records received, reviewed and accepted by tne AE/CM by audit surveillance.
7.1.3     Supply System The Supply System shall identify, locate and collect all WNP-3 records in its custody and except as noted in subsection 7.2, transfer those records to the AE/CM to be stored, maintained, processed, as applicable, within the central on-site record storage facility. The Supply System shall provide overview of this function to ensure compliance with Supply System procedures and standards.
7.1.3 Supply System The Supply System shall identify, locate and collect all WNP-3 records in its custody and except as noted in subsection 7.2, transfer those records to the AE/CM to be stored, maintained, processed, as applicable, within the central on-site record storage facility. The Supply System shall provide overview of this function to ensure compliance with Supply System procedures and standards.
7.2       RECORDS GENERATED DURING CONSTRUCTION DELAY Records generated during construction delay will be processed through the AE/CM central records processing system except as indicated below:
7.2 RECORDS GENERATED DURING CONSTRUCTION DELAY Records generated during construction delay will be processed through the AE/CM central records processing system except as indicated below:
l     e         Security records shall be retained by the Supply System.
l e
7.3       STATUS OF CUST0DY OF DOCUMENTATION PRIOR TO CONSTRUCTION SLOWDOWN i
Security records shall be retained by the Supply System.
e         Design documents and records are in AE/CM and/or contractor custody.
7.3 STATUS OF CUST0DY OF DOCUMENTATION PRIOR TO CONSTRUCTION SLOWDOWN i
l l
e Design documents and records are in AE/CM and/or contractor custody.
l l !


    ,                                                                          08/03/83 e     0 & M manuals are in Supply System custody.
08/03/83 e
e     Generation documents and records are in Supply System custody.
0 & M manuals are in Supply System custody.
e     Procedures are in AE/CM, contractor and Supply System custody.
e Generation documents and records are in Supply System custody.
e     Licensing records are in AE/CM and Supply System custody.
e Procedures are in AE/CM, contractor and Supply System custody.
e     QA program records are in the custody of the Supply System, o     Health Physics Chemistry records are in Supply System custody.
e Licensing records are in AE/CM and Supply System custody.
e     Fuel Program documents and records are in Supply System custody.
e QA program records are in the custody of the Supply System, o
e     Contractor / Vendor Installation and Manufacturing records are in the AE/CM and contractor custody.
Health Physics Chemistry records are in Supply System custody.
e     Construction Test records are in the custody of the CM.
e Fuel Program documents and records are in Supply System custody.
e     Test and Start-Up records are in the custody of the Supply System.
e Contractor / Vendor Installation and Manufacturing records are in the AE/CM and contractor custody.
7.4   REQUIRED ACTION e     Review and approve AE/CM Management Plan for Extended Construction Delay of WNP-3 Records and Documents. (see Detailed Plan).
e Construction Test records are in the custody of the CM.
e     Prepare and obtain approval of detailea WNP-3 Records Management Pro-grams as noted below to facilitate restart of construction.
e Test and Start-Up records are in the custody of the Supply System.
            - Technical Records Program
7.4 REQUIRED ACTION e
            - Non Technical Records Program
Review and approve AE/CM Management Plan for Extended Construction Delay of WNP-3 Records and Documents.
            - Nuclear Operation Program l
(see Detailed Plan).
08/03/83 7.5     ACTIONS TAKEN TO DATE 4
e Prepare and obtain approval of detailea WNP-3 Records Management Pro-grams as noted below to facilitate restart of construction.
              - Transfer of WNP-3 Headquarters files to site initiated (See Detailed Plan, Transfer of WNP-3 Files From Headquarters to Site Transition Plan). Scheduled completion date for this transaction is 11/01/83.
- Technical Records Program
              - Direction given to AE/CM to establish microfilming, encoding and data entry capability, full implementation scheduled for 09/01/83.
- Non Technical Records Program
- Nuclear Operation Program l
08/03/83 7.5 ACTIONS TAKEN TO DATE 4
- Transfer of WNP-3 Headquarters files to site initiated (See Detailed Plan, Transfer of WNP-3 Files From Headquarters to Site Transition Plan). Scheduled completion date for this transaction is 11/01/83.
- Direction given to AE/CM to establish microfilming, encoding and data entry capability, full implementation scheduled for 09/01/83.
E i
E i
4 s
4 s
Line 574: Line 759:
l i
l i


      .                                                                              08/03/83 8.0       COMMERCIAL ACTIONS 8.1       GENERAL The guidance and requirements specified in this section are necessary to ensure proper overall planning, support budget formulation, and facilitate cash flow forecasting and control. It is emphasized that the Project will implement immediately those contractual actions that reduce the continuing commitment of funds to a minimum, while at the same time not foreclosing the options for restart within the next three to nine months. Priority shall be given to the resolution of contractual issues on those contracts which are essential to our restart.
08/03/83 8.0 COMMERCIAL ACTIONS 8.1 GENERAL The guidance and requirements specified in this section are necessary to ensure proper overall planning, support budget formulation, and facilitate cash flow forecasting and control.
8.2     SPECIFIC ACTIONS 8.2.1   Prepurchased Equipment Project Management will make decisions with regard to prepurchased equipment and materials contracts. Contracts will be categorized into three distinct groupings as follows:
It is emphasized that the Project will implement immediately those contractual actions that reduce the continuing commitment of funds to a minimum, while at the same time not foreclosing the options for restart within the next three to nine months.
: 1.       Contracts to be allowed to run to completion.
Priority shall be given to the resolution of contractual issues on those contracts which are essential to our restart.
l         2.       Contracts to be issued partial or total suspension, with the suspension l                 to be lifted when project restart is identified.
8.2 SPECIFIC ACTIONS 8.2.1 Prepurchased Equipment Project Management will make decisions with regard to prepurchased equipment and materials contracts. Contracts will be categorized into three distinct groupings as follows:
l
1.
: 3.       Contracts to be terminated immediately.
Contracts to be allowed to run to completion.
All contracts have been reviewed and suspensions issued for all work not started, except in one case in which current facts dictate other action. Upon approval of the Management Plan, categories will be finalized and appropriate contract action' implemented. Data is currently available which reflects the following:
l 2.
: 1.       Estimate of cost based on category assignment and cost flows through June 1984.
Contracts to be issued partial or total suspension, with the suspension l
08/03/83   i
to be lifted when project restart is identified.
:                                                                                            j
l 3.
: 2.       Intended further action such as total suspension, termination or modifi-l cation of partial suspension.
Contracts to be terminated immediately.
: 3.       Where no action is intended and the work proposed is to run to completion, that has been identified.
All contracts have been reviewed and suspensions issued for all work not started, except in one case in which current facts dictate other action.
: 4.       Appropriate action will be taken when necessary to ensure that all data, material and/or hardware paid for is brought to a point where the resource has value and may be used at a future date for the completion of the plant.
Upon approval of the Management Plan, categories will be finalized and appropriate contract action' implemented. Data is currently available which reflects the following:
1.
Estimate of cost based on category assignment and cost flows through June 1984.
08/03/83 i
j 2.
Intended further action such as total suspension, termination or modifi-cation of partial suspension.
3.
Where no action is intended and the work proposed is to run to completion, that has been identified.
4.
Appropriate action will be taken when necessary to ensure that all data, material and/or hardware paid for is brought to a point where the resource has value and may be used at a future date for the completion of the plant.
Project management will prepare individual contract negotiation plans to support the contract actions referenced above. A continual iterative process beginning with the completion of the negotiation plans will be carried out in order that project cost / cash flow can be updated and adjusted as required. A schedule for negotiations containing a start and a completion date wiii ce prepared and should be available by September 1, 1983. Necessary Project Change Proposals and/or contract documents will be prepared and executed in accordance with established procedures.
Project management will prepare individual contract negotiation plans to support the contract actions referenced above. A continual iterative process beginning with the completion of the negotiation plans will be carried out in order that project cost / cash flow can be updated and adjusted as required. A schedule for negotiations containing a start and a completion date wiii ce prepared and should be available by September 1, 1983. Necessary Project Change Proposals and/or contract documents will be prepared and executed in accordance with established procedures.
8.2.2   Construction Contracts All construction contracts have been reviewed and a preliminary conclusion made as to whether the individual contract should be suspended in whole or in part, terminated in whole or in phrt, or allowed to run to completion. All contractors whose schedule required a site presence prior to May 27, 1983, have been suspended in whole or in part, with the single exception of the site services contractor.
8.2.2 Construction Contracts All construction contracts have been reviewed and a preliminary conclusion made as to whether the individual contract should be suspended in whole or in part, terminated in whole or in phrt, or allowed to run to completion. All contractors whose schedule required a site presence prior to May 27, 1983, have been suspended in whole or in part, with the single exception of the site services contractor.
Project Management has reviewed all contracts and the tentative plan for imple-ment.ing the Board's direction. Current recommendations are that nine contracts be maintained in partial suspension. These nine contracts, together with the site services contractor are considered to be the contracts required to maintain the capability of restart. As the period of construction delay is prolonged, the Project has identified the key dates upon which conscious decisions must be made regarding either termination or continued suspension of these nine con-
Project Management has reviewed all contracts and the tentative plan for imple-ment.ing the Board's direction. Current recommendations are that nine contracts be maintained in partial suspension. These nine contracts, together with the site services contractor are considered to be the contracts required to maintain the capability of restart. As the period of construction delay is prolonged, the Project has identified the key dates upon which conscious decisions must be made regarding either termination or continued suspension of these nine con-
[
[
tractors. All other construction contracts are recommended for termination as l       soon as the plan is approved.
tractors. All other construction contracts are recommended for termination as l
    -      -                                        ,  =--   -,                            -  .
soon as the plan is approved. !
=--


WWA@J     l Project management will prepare individual contract negotiation plans to support the necessary contract changes to implement the approved plan. Based on this approved plan, projected cost / cash flow requirements will be reviewed and adjusted as necessary. An overall negotiation schedule will be prepared and available by September 1, 1983. Negotiations will be carried out in accordance with that schedule. This schedule will include both a start date and a com-pletion date for negotiations. Necessary Project Change Proposals and/or contract documents will be prepared and executed in accordance with established procedures.
WWA@J l
8.2.3     Headquarters Contracting Activities Service and prepurchase contracts that support, or are funded by WNP-3 and are managed by headquarters, are being given the same scrutiny and appropriate reports and cash flows are being prepared. This activity has been accomplished by the Project Business Department, working in close coordination with the headquarters staff, the Project Controller, and the responsible manager who requested the service. Cash forecasts for these items are now stated at minimum required levels.
Project management will prepare individual contract negotiation plans to support the necessary contract changes to implement the approved plan.
8.3     NUCLEAR FUEL The nuclear fuel contracts are under the technical control of the Technical Director. The following actions are to be taken:
Based on this approved plan, projected cost / cash flow requirements will be reviewed and adjusted as necessary. An overall negotiation schedule will be prepared and available by September 1, 1983.
8.3.1     Initial Core - UF Supply, 6
Negotiations will be carried out in accordance with that schedule.
Allied Chemical Contract 3240-2A l
This schedule will include both a start date and a com-pletion date for negotiations.
l This contract supplied 395,780 kg of UF   6 f r the WNP-3 initial core. Storage was provided for through June 1981. Final shipment to DOE in May 1981 concluded l
Necessary Project Change Proposals and/or contract documents will be prepared and executed in accordance with established procedures.
the contract requirements. Closeout is targeted for October 1983.
8.2.3 Headquarters Contracting Activities Service and prepurchase contracts that support, or are funded by WNP-3 and are managed by headquarters, are being given the same scrutiny and appropriate reports and cash flows are being prepared.
l 8.3.2   Enrichment Services, Department of Energy Contract DE-SC05-79UE4666 Under this Adjustable, Fixed-Commitment contract, DOE provides enrichment services for 30 years (through 2009). This covers the initial and reload cores.     Enrichment i
This activity has been accomplished by the Project Business Department, working in close coordination with the headquarters staff, the Project Controller, and the responsible manager who requested the service. Cash forecasts for these items are now stated at minimum required levels.
1 l                                             l
8.3 NUCLEAR FUEL The nuclear fuel contracts are under the technical control of the Technical Director.
The following actions are to be taken:
8.3.1 Initial Core - UF Supply, Allied Chemical Contract 3240-2A 6
l This contract supplied 395,780 kg of UF f r the WNP-3 initial core.
Storage l
6 was provided for through June 1981. Final shipment to DOE in May 1981 concluded l
l the contract requirements. Closeout is targeted for October 1983.
8.3.2 Enrichment Services, Department of Energy Contract DE-SC05-79UE4666 Under this Adjustable, Fixed-Commitment contract, DOE provides enrichment services for 30 years (through 2009). This covers the initial and reload cores.
Enrichment i
1 l l


      .                                                                                  08/03/83 of the WNP-3 initial core was completed in September 1981 and placed in storage at 00E. Full and final payment for the initial core enrichment services was made in October 1981. Notices must be provided to DOE by July I of each year establishing future amounts of enrichment services and delivery requirements of enriched uranium. Further, the Supply System is committed to utilization of enrichment services in FY85 which are in excess of needs. To avoid significant expenditure, these services must be either sold or assigned.
08/03/83 of the WNP-3 initial core was completed in September 1981 and placed in storage at 00E. Full and final payment for the initial core enrichment services was made in October 1981.
8.3.3   Conversion Services, Kerr-McGee Nuclear Contract C-5391 This contract provides for conversion services and storage for two initial cores (WNP-4/5) and reload cores for all five projects through 1986. The contract is based on a fixed commitment for conversion of 5,165,633 kg U to UF6 .         The WNP-3 reload allocation of this amount is 847,985 kg U, all of which is excess to present needs. No conversion services are required for the initial core.
Notices must be provided to DOE by July I of each year establishing future amounts of enrichment services and delivery requirements of enriched uranium. Further, the Supply System is committed to utilization of enrichment services in FY85 which are in excess of needs. To avoid significant expenditure, these services must be either sold or assigned.
Cancellation charges are payable if actual quantities converted are less than the fixed amount. Decision on disposition must be made by December 31, 1984 to avoid significant penalties.
8.3.3 Conversion Services, Kerr-McGee Nuclear Contract C-5391 This contract provides for conversion services and storage for two initial cores (WNP-4/5) and reload cores for all five projects through 1986.
8.3.4   Storage of Enriched UF 6, Department of Energy Contract EY-77-SA-05-5410                 -
The contract is based on a fixed commitment for conversion of 5,165,633 kg U to UF.
l       This contract provides for enriched uranium storage services and storage containers
The WNP-3 6
:      for material enriched for any of the Supply System projects if the Supply System is unable to take delivery and alternative storage cannot be obtained. In September 1981, the enriched UF   6 f r the WNP-3 initial core was placed in storage l       at the DOE enrichment facility at Piketon, Ohio. The material is stored in 19 l       DOE-provided storage cylinders. To ensure the initial core fabrication supply and plant restart capability, storage will be continued.
reload allocation of this amount is 847,985 kg U, all of which is excess to present needs.
8.3.5   Initial Core Fabrication, Combustion Engineering Contract 3240-2 This contract covers both the purchase of the NSSS and the design and fabrication of the initial core. In November 1982, CE was released to complete the final fuel design. An FSAR amendment was submitted for Supply System review based on
No conversion services are required for the initial core.
Cancellation charges are payable if actual quantities converted are less than the fixed amount.
Decision on disposition must be made by December 31, 1984 to avoid significant penalties.
8.3.4 Storage of Enriched UF, Department of Energy Contract EY-77-SA-05-5410 6
l This contract provides for enriched uranium storage services and storage containers for material enriched for any of the Supply System projects if the Supply System is unable to take delivery and alternative storage cannot be obtained.
In September 1981, the enriched UF f r the WNP-3 initial core was placed in storage 6
l at the DOE enrichment facility at Piketon, Ohio.
The material is stored in 19 l
DOE-provided storage cylinders. To ensure the initial core fabrication supply and plant restart capability, storage will be continued.
8.3.5 Initial Core Fabrication, Combustion Engineering Contract 3240-2 This contract covers both the purchase of the NSSS and the design and fabrication of the initial core.
In November 1982, CE was released to complete the final fuel design. An FSAR amendment was submitted for Supply System review based on _


                                                                            ~
~
    .                                                                            08/03/83 the final fuel design;   this review has generated only minor comments. On March 29, 1983, all work on the asymmetric load analysis was suspended. Completion of this analysis is required before fuel fabrication can begin. No further action is planned pending additional funding.
08/03/83 the final fuel design; this review has generated only minor comments.
8.3.6   Reload Fuel, Exxon Nuclear Contract 3240-2B This contract, which provides for WNP-3 reload fuel supply and fabrication, has recently been upheld in the King County Superior Court. Resolution of several issues remain consistent with the Court's ruling. Periodic notices to Exxon establishing delivery requirements, however, continue to be a Supply System obligation.
On March 29, 1983, all work on the asymmetric load analysis was suspended. Completion of this analysis is required before fuel fabrication can begin.
8.3.7   Contract C-13265 This contract covers additional tasks required and related to, but not included in the scope of the 3240-2 contract. Not-to-exceed funding is provided on a task basis. Continuation of fuel related efforts by CE to maintain and ensure plant licensability are anticipated.
No further action is planned pending additional funding.
8.3.8   Additional Enrichment Modification of enrichment levels of the intial core is required to meet plant operating requirements and has been defined. Based on a three-year suspension of WNP-3, actions to contractually implement this additional enrichment must be completed by mid-1986 to support fuel fabrication in 3rd Quarter 1987.
8.3.6 Reload Fuel, Exxon Nuclear Contract 3240-2B This contract, which provides for WNP-3 reload fuel supply and fabrication, has recently been upheld in the King County Superior Court.
Resolution of several issues remain consistent with the Court's ruling.
Periodic notices to Exxon establishing delivery requirements, however, continue to be a Supply System obligation.
8.3.7 Contract C-13265 This contract covers additional tasks required and related to, but not included in the scope of the 3240-2 contract.
Not-to-exceed funding is provided on a task basis. Continuation of fuel related efforts by CE to maintain and ensure plant licensability are anticipated.
8.3.8 Additional Enrichment Modification of enrichment levels of the intial core is required to meet plant operating requirements and has been defined.
Based on a three-year suspension of WNP-3, actions to contractually implement this additional enrichment must be completed by mid-1986 to support fuel fabrication in 3rd Quarter 1987.
4 i
4 i
l I
l I
i                                          
i 08/03/83 9.0 MANAGEMENT OF THE EXTENDED CONSTRUCTION DELAY The principles for management of the construction delay are presented in Section 1.4 of the Level I Executive Summary and will be the basis for implementation by Department Managers.
    .                                                                                08/03/83 9.0       MANAGEMENT OF THE EXTENDED CONSTRUCTION DELAY The principles for management of the construction delay are presented in Section 1.4 of the Level I Executive Summary and will be the basis for implementation by Department Managers.
9.1 DEPARTMENT MANAGEMENT RESPONSIBILITIES Management of the extended construction delay is the direct responsibility of the Department Managers of the Supply System.
9.1       DEPARTMENT MANAGEMENT RESPONSIBILITIES Management of the extended construction delay is the direct responsibility of the Department Managers of the Supply System.       Each Manager will be responsible for accomplishing those activities within his/her area of responsibility on the defined schedule and within budget. The integrity of the overall financial baseline defined in Section 1.0 must be maintained and is the collective respon-sibility of each manager.
Each Manager will be responsible for accomplishing those activities within his/her area of responsibility on the defined schedule and within budget. The integrity of the overall financial baseline defined in Section 1.0 must be maintained and is the collective respon-sibility of each manager.
9.2       PROGRAM RESPONSIBILITIES The Program (i.e., the Program Director and appropriate members of his staff) is to provide assistance to department managers in developing and implementing actions and is to provide a consolidated report and evaluation. The Program Director will continue to report to the Managing Director on all matters related to the extended construction delay. The functions of the Program will be as follows:
9.2 PROGRAM RESPONSIBILITIES The Program (i.e., the Program Director and appropriate members of his staff) is to provide assistance to department managers in developing and implementing actions and is to provide a consolidated report and evaluation. The Program Director will continue to report to the Managing Director on all matters related to the extended construction delay. The functions of the Program will be as follows:
e         Develop and publish a consolidated Monthly Progress Report.
e Develop and publish a consolidated Monthly Progress Report.
e         Identify any requirements or additional initiatives for executing the delay.
e Identify any requirements or additional initiatives for executing the delay.
* Assist managers as required in the implementation of the extended construc-tion delay.
Assist managers as required in the implementation of the extended construc-tion delay.
a       Review the experience of other nuclear utilities in extended delays on their plants.
a Review the experience of other nuclear utilities in extended delays on their plants.
e       Review Supply System performance on accomplishing required tasks.
e Review Supply System performance on accomplishing required tasks. _


08/03/83 s       Review total expenditures versus baseline and funds availability to identify possible variance trends or overruns.
08/03/83 s
e       Identify and analyze potential areas for further savings.
Review total expenditures versus baseline and funds availability to identify possible variance trends or overruns.
e       Process Project Change Proposals e       Update plan as necess6ry.
e Identify and analyze potential areas for further savings.
9.3     ACTIONS & REPORTING GUIDELINES The following reports / input are required:
e Process Project Change Proposals e
e       Financial (Responsibility of S. B. Merlin)
Update plan as necess6ry.
                  - Monthly Rolling Cash Flow Budget Line Item Prepurchased and Construction Detail Variance Analysis Graphic Display
9.3 ACTIONS & REPORTING GUIDELINES The following reports / input are required:
                  - Monthly / Fiscal Year To Date Cash Summary Budget vs. Actual Prepurchased and Ccnstruction Detail Construction and Non Construction Major One Time Activities Variance Analysis
e Financial (Responsibility of S. B. Merlin)
                  - Monthly / Fiscal Year To Date Cost Summary Budget Line Item Budget vs. Actual l
- Monthly Rolling Cash Flow Budget Line Item Prepurchased and Construction Detail Variance Analysis Graphic Display
Prepurchased and Construction Detail Construction and Non Construction Major One Time Cost Variance Analysis
- Monthly / Fiscal Year To Date Cash Summary Budget vs. Actual Prepurchased and Ccnstruction Detail Construction and Non Construction Major One Time Activities Variance Analysis
                  - Monthly / Fiscal Year To Date Project Manpower Budget vs. Actual Contract and Department Detail Construction vs. Non Construction Variance Analysis
- Monthly / Fiscal Year To Date Cost Summary Budget Line Item l
Budget vs. Actual Prepurchased and Construction Detail Construction and Non Construction Major One Time Cost Variance Analysis
- Monthly / Fiscal Year To Date Project Manpower Budget vs. Actual Contract and Department Detail Construction vs. Non Construction Variance Analysis -


08/03/83
08/03/83
          - Monthly Summary Financial Assessment Cost / Cash / Status Performance / Trend Analysis e   Licensing (responsibility of K. W. Cook)
- Monthly Summary Financial Assessment Cost / Cash / Status Performance / Trend Analysis e
          - Status of Draft SER Questions received, response schedule status, open items, etc.
Licensing (responsibility of K. W. Cook)
          - Status of Major Issues
- Status of Draft SER Questions received, response schedule status, open items, etc.
          - Status of Rampdown Activities
- Status of Major Issues
          - Status of Preservation Activities
- Status of Rampdown Activities
          - Status of Operating Experience Review Size of data base, backlog, review status.
- Status of Preservation Activities
          - Status of Nuclear Safety Assurance reporting.
- Status of Operating Experience Review Size of data base, backlog, review status.
e   Documentation & Records (responsibility of M. C. Robb)
- Status of Nuclear Safety Assurance reporting.
          - Status of required records received from Contractors, reviewed and vaulted by AE/CM as measured by completion percentages vs. expectations.
e Documentation & Records (responsibility of M. C. Robb)
          - Status of records transfer from headquarters to site measured by progress towards intermediate milestones.
- Status of required records received from Contractors, reviewed and vaulted by AE/CM as measured by completion percentages vs. expectations.
          - Status of consolidation of on-site records processing functions measured by progress towards intermediate milestones.
- Status of records transfer from headquarters to site measured by progress towards intermediate milestones.
e   Asset Preservation (responsibility of J. W. Wilson)
- Status of consolidation of on-site records processing functions measured by progress towards intermediate milestones.
          - Status of component turnovers to Supply System.
e Asset Preservation (responsibility of J. W. Wilson)
          - Status of Preventative Maintenance.
- Status of component turnovers to Supply System.
          - Status of critical skills staffing.
- Status of Preventative Maintenance.
          - Status of procedures required to operate and maintain systems turnover to Operations.
- Status of critical skills staffing.
          - Status of fragnet development.
- Status of procedures required to operate and maintain systems turnover to Operations.
                                                                          .                    .=.
- Status of fragnet development.  
08/03/83 e         Construction (responsibility of J. J. Peterson)
.=.
                          - Manpower (actual vs budget)
08/03/83 e
                          - Cost / Cash flows (actual vs budget)
Construction (responsibility of J. J. Peterson)
                          - Construction completion in support of rampdown/ preservation.
- Manpower (actual vs budget)
                                      - Monthly Accomplishments
- Cost / Cash flows (actual vs budget)
                          - Documentation Submittals
- Construction completion in support of rampdown/ preservation.
                                      - Number of packages submitted, reviewed and approved.
- Monthly Accomplishments
                          - Materials Management
- Documentation Submittals
                                      - Returned to warehouse status, inventory and store statuses.
- Number of packages submitted, reviewed and approved.
                          - Construction contract closecut status.
- Materials Management
                        - Safety status.
- Returned to warehouse status, inventory and store statuses.
                        - NCR, DDNs and Conditional Releases
- Construction contract closecut status.
                                      - Issued, dispositioned and cleared e         Engineering (responsibility of J. E. Werle)
- Safety status.
                        - Status of FSAR Connittments.
- NCR, DDNs and Conditional Releases
                        - Status of Engineering Key Items:
- Issued, dispositioned and cleared e
Engineering (responsibility of J. E. Werle)
- Status of FSAR Connittments.
- Status of Engineering Key Items:
Stiff Clamps Beam Coping Nozzle Loads (Othersasidentified)
Stiff Clamps Beam Coping Nozzle Loads (Othersasidentified)
                        - Status of Drawing Roll-up
- Status of Drawing Roll-up
                        - Status of NCR Closecut
- Status of NCR Closecut
                        - Status of Start-Up Systems Design Freeze
- Status of Start-Up Systems Design Freeze
                        - Status of DCN, QFPCP Closeout
- Status of DCN, QFPCP Closeout
                        - Status of Equipment Qualification Activities
- Status of Equipment Qualification Activities
                        - Status of Vendor Drawings
- Status of Vendor Drawings
                  .      - Status of System Review Action Items Lists Setpoints
- Status of System Review Action Items Lists Setpoints
                        - A/E Manpower Levels
- A/E Manpower Levels
!                        - Budgeted Cost of Work Scheduled
- Budgeted Cost of Work Scheduled
                        - Bi-Monthly Engineering Review Meetings
- Bi-Monthly Engineering Review Meetings
                        - Bi-Monthly SAIL Meetings
- Bi-Monthly SAIL Meetings


    '                                                                                                                      08/03/83
08/03/83
  ,e     .
,e e
e    Business (responsibilityofR.N. Williams)
Business (responsibilityofR.N. Williams)
              - Status of contract closeout actions by contract.
- Status of contract closeout actions by contract.
              - Status of negotiations implementing partial suspension by contract.
- Status of negotiations implementing partial suspension by contract.
              - Status of negotiations implementing total suspension by contract.
- Status of negotiations implementing total suspension by contract.
              - Status of negotiations implementing termination by contract.
- Status of negotiations implementing termination by contract.
Identification of those pending actions which appear to have significant potential of impacting the estimated cost / cash flow by an amount in excess of $100,000.
Identification of those pending actions which appear to have significant potential of impacting the estimated cost / cash flow by an amount in excess of $100,000.
e     Quality Assurance (responsibility of 0. E. Trapp)
e Quality Assurance (responsibility of 0. E. Trapp)
              - Status of NRC items.
- Status of NRC items.
              - Status of Records turnover and review.
- Status of Records turnover and review.
              - Status of vendor surveillance /VQA.
- Status of vendor surveillance /VQA.
              - Status of Asset Preservation Program / Preventative Maintenance.
- Status of Asset Preservation Program / Preventative Maintenance.
              - Status of closeout and construction work.
- Status of closeout and construction work.
                                                              - . . . .        --        -  . -  - _ . _ _ _ . . . - _ _ . . . - . . . . , _ _ . - _ - _ _ _ . . - -}}
. - _ _... -...., _ _. - _ - _ _ _.. - -}}

Latest revision as of 03:01, 15 December 2024

Mgt Plan for Extended Const Delay of WNP-3,Executive Summary (Level I & Level II)
ML20076C280
Person / Time
Site: Satsop
Issue date: 08/04/1983
From:
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
Shared Package
ML20076C251 List:
References
NUDOCS 8308220300
Download: ML20076C280 (55)


Text

l MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY OF WNP-3 EXECUTIVE

SUMMARY

ILEVEL11 AUGUST 4,1983 l

Washington Public Power Supply System

[888!888Ro!888,8le

08/03/83 PLAN STRUCTURE LEVEL I - EXECUTIVE

SUMMARY

This portion is intended tc provide executive level information relative to the plan,~anagement principles and the most critical aspects of the construction m

delay.

J LEVEL II - DESCRIPTION OF PERFORMANCE Bf FUNCTION This is intended to describe, at the management level, those functions which will or might be performed during the construction delay.

This level II portion together with Level I constitutes middle management's guidelines.

LEVEL III - SUPPORTING DOCUMENTS These documents are all of the supporting procedures, data, budgets, etc., which support the Level II and I.

These are internal documents and are not intended for consolidation or distribution outside the project except as may be required.

a l

08/03/83 MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY OF WNP-3 1.0 EXECUTIVE

SUMMARY

1.1 INTRODUCTION

This Management Plan is a description of the policy and guidelines to be fol-lowed in executing an extended construction delay at WNP-3. The Supply System will use this plan as the basis for management direction relative to the delay period. The delay plan must be executed in strict accordance with the limited funding plan while preserving the assets of WNP-3 during the delay.

1.2 BACKGROUND

The delay of construction of this project is a result of several major events.

These include numerous matters of litigation two of which can be deemed major:

(1) the decision by the \\'ashington State Supreme Court on June 15, 1983 ruling that WNP-4/5 Participants are not bound to make payments to the Supply System, and (2) the question of the authority of certain participants to enter into the WNP-1, 2 and 3 net-billing agreements.

These and other related issues impact the ability of the Supply System to continue financing construction of WNP-3.

As a result of the status of these issues, on May 27, 1983, the Executive Board through Resolution No. 147 directed that the Managing Director slowdown con-struction on WNP-3 for a period not to exceed thirty (30) days in such a manner that, should additional funding be found during that period, work could be resumed with no impact to the 1983 total budget and official schedule. Then, on i

July 8,1983, the Executive Board Resolution No.152 directed the Managing Director to implement an immediate extended construction delay of Project 3 until'an assured source of funding for continued construction can be obtained and to prepare and deliver a detailed implementation plan to the Executive Board.

Tnis Management Plant satisfies the latter direction.

i 1

1 08/03/83 1.3 CRITERIA The criterion upon which this plan are based is at Attachment 1.

The Managing Director must be notified of any requirements and recommendations to change these criteria. Without the Managing Director's approval of such changes, the existing criteria are to be met.

1.4 MANAGEMENT PRINCIPLES 1.4.1 Execution The management of the extended construction delay will be implemented through the site organization with the appropriate assistance from the Richland head-quarters.

In managing the delay, maximum utilization will be made of existing procedures, systems and reports. All actions taken must be with full compliance of the existiag Ownership Agreements, Net-Billing Agreement and the Project Agreement.

1.4.2 Changes To The Plan Changes to this plan will require approval of the Program Director and at his discretion the concurrence of the Managing Director, BPA, the Private Owners, the Participants' Committee and the Executive Board.

1.5 LICENSING A major element of the criteria is preservation of licenses.

Because of the sensitivity of this aspect of the construction delay, a brief description of licenses and associated activities is at Attachment 2.

1.6 -

CASH FLOW Because of the limited funding available and the flow thereof, forecasted ex-penditures of that funding and flow are of executive level interest.

That may be found at Attachment 3. _.

08/03/83 1.7 MANPOWER PROFILE Manpower requirements on the Project are closely related to the level of docu-mentation, rampdown and preservation activities.

These requirements are graphic-ally displayed on the associated manpower profile at Attachments 4 and 5.

1.8 SCHEDULE 1.8.1 Implementation Implementation of the delay plan began immediately after the Board action was taken on July 8, 1983. Concurrently, this Management Plan, as well as detailed plans which support the limited funding and associated manpower levels, were developed. All are consistent with the Board's action and specific guicance provided by the Managing Director.

4 1.8.2 Submittals e

First draft for Program Director's review on July 26, 1983.

e Final " Management Plan For Extended Construction Delay of WNP-3" for Executive Board Committee review on August 11, 1983.

1.9 REPORTING Reporting against this plan will generally follow the monthly report of WNP-1 tailored to WNP-3 as further described in Section 9.0 of the Level II portion of this plan.

4 I

l :

GENERAL CRITERZA ATTACHMENT 1 IINP-3 CONSTRUCTf0N DELAY IMPLEMENTATION PLAN 08/03/83 I. Introduction l

Executive Board Resolution No.152 directed the Supply System to implement an immediate extended construction delay of Project No. 3 until an assured source of funding for continued construction can be obtained, and to pre-pare and deliver a detailed implementation plan to the Executive Board consistent with the foregoing.

II. General Criteria I

A.

As of July 8,1983, continue further rampdown of construction and related activities from the current manpower level to a documentation roll-up and preservation / maintenance staff of approximately 800 by October 1983.

B.

Maintain the documentation roll-up and preservation / maintenance efforts from October 1983 to July 1984 with a manpower level of approximately 800 as of October 1983 gradually declining to a mini-mum preservation staff of approximately 375 as of July 1984.

Man-power reductions to be generally accomplished within the profile shown on Attachment 1.

C.

Maintain construction restart ability through approximately March 1984 by retaining the contractual ability to reactivate the essen-tial construction and prepurchased contracts.

D.

The implementation plan shall cover the period from July 8,1983 through June 30,1985 (FY-1984 and FY-1985).

E.

Preserve all state and federal licensability requirements.

F.

Preserve and control all documentation required for licenses, opera-tion and construction status.

G.

Optimize (to the extent practicable) the retention of the Supply System's resource capabilities over those of the AE/CM and contrac-tors.

H.

Outstanding licensing issues should be resolved to the largest extent possible.

I.

Complete those activities essential to planning for restart of con-struction.

J.

Establish and implement a cost tracking system for construction versus nonconstruction costs.

I l

l

General Criteria 08/03/83 -

UllP-3 Construction Delay Implementation Plan Page 2 of 4 III. Financial Consideration A.

Detailed cost and cash flow estimates shall be consistent with the following:

1.

The estimating guidelines (as applicable) provided by the

" General Criteria Fiscal Year 1984 Financing Planning Process".

2.

Actuals as of June 30, 1983.

3.

On a monthly basis for the period from July 1,1983 through June 30, 1985 (FY-1984 and FY-1985) at 100 percent ownership values.

4.

Summary presentations shall be formatted similar to the rolli.ng cash flow forecast (Attachment 2).

5.'

Supporting cost and cash flow details shall as a minimum be broken down to the following levels:

Major budget line items.

Contract-by-contract.

Construction activities and nonconstruction activities.

One-time costs and on-going costs.

6.

Funding for contract settlements or other costs, which may be rescheduled (due to the above Item II.C requirement) to a later time than planned in the May 1983 Wr1P-3 Alternative Analysis, are not available for other or additional disbursements.

7.

Cash disbursements shall be planned in accordance with the Supply System's fiscal year calendar, which will be the basis for future performance measurement.

8.

Include all applicable construction and fuel costs; i.e.,

escalation, sales tax, nuclear fuel, applicable financing, contingency, etc.

9.

Exclude all potential cost sharing adjustments identified as a result of Supply System management review.

B.

July 1, 1983 through September 30, 1984 financial baseline ($ in millions):

Construction & Fuel Fund as of June 30, 1983 5 74.0 Estimated Investment Income 1.5 Payments by 100's 59.5 Payments by BPA 63.0 Total Disbursements

$3d

08/03/83 General Criteria UNP-3 Construction Delay Implementation Plan Page 3 of 4 C.

Total cash disbursements for the period from July 1,1983 through September 30, 1984 shall not exceed $198 million (above).

Further-more, the total cash disbursements from July 1,1983 through November 30, 1933 shall not exceed 5108 million.

D.

October 1,1984 through September 30, 1985 financial baseline ($ in millions):

1 Payments by 100's

$13. 5 i

Payments by BPA 31.5 I

Total Disbursements

$45.0 IV. Format Utilize the "flanagement Plan for Extended Construction Delay of UNP-1",

dated November 30, 1982, as both a guide and a checklist tailored as 9

j necessary to include UNP-3 considerations.

~

V. Schedule A.

First draft for Managing Director's review on July 26, 1983.

B.

Final "UNP-3 Construction Delay Implementation Plan" for Executive Board Committee review on August 11, 1983.

l 1

' Pag? 4 of 4 08/03/83 UASHIflGTON PUBLIC POWER SUPPLY SYSTEM NUCLEAR PROJECT NO. 3 CONSTRUCTIO:t DELAY I!!PLEMEtiTATI0tt PLAft FISCAL YEAR 1984 AtlD 1985 GEllERAL TOTAL PROJECT 11ANPOWER PROFILE

  • Average Monthly FY-1984 Equivalent fianpower July 1,500 Rampdown August 1,200 Period September 1,000 October 8005 f!ovember 800 December 750 Documentation January 725 and Preservation February 700 )

Effort March 675 April 650 May 550 June 450s Average Monthly FY-1985 Equivalent Manpower July 375' August 375 September 375 October 375 November 375 Preservation and December 375 \\ Maintenance Only January February 375(

375

!! arch 375 April 375 May 375 June 375s

  • Total project manpower includes the following:

Craft Contractor's ilonmanuel Construction Management Architect-Engineer Home Office On-site Supply System On-site Home Office Direct y

Home Office A&G Allocation t

i

y.

e e

ATTACimi 2 WASHINGTON PUSLIC POWER SUPPLY SYSTEM NUCLEAR PROJECT NO. 3 Sheet 1 of 2 CONSTRUCTION FU.'s CASil FLOW t M 10U5 M 5) 1983 1984 0 0tN.

July Aq Sept Oct Ptw Dec

.La Feb Mr Apr Mqr are 11y As Sapt

' 7-1-83 to 9-hot h6girejBalaor Reteipts Irretsut frume PJ)muets ter IW's

}

fit Billirsp lotal Receipts Diprsammts PlsA DesisfvTngiratring EXAMPLE htinsthsud Espipasit Plwit Cuistrution/Capletim Cuistewtlue Cuitra.ts Ca structtui Ka uf.c N ax's Re m tes (d)

Na. lear final Cuitirsysay Ismtus livs Total Di:,tAYstNGts f.'!!"9 S'h'i' O'

(4) Ircitakes prisf sy Ewrapasit, plait garation arsi caprate allocation.

D w

CD w.

l

~

s m

WASHINGT018 PUBLIC POK R SUPPLY SYSTEM ATTACitMENT 2 NULLEAR 8110 JECT NO. 3 Sheet 2 of 2 COIISTRUCTION FUNu CASH FLOW

($ IN TlluuSANDS) 1984 1985

[

Total Total '" * "

Oct Itw Dec Jan Feb Mr Apr My an Ari Asj Sm 10-1-tM to 9-3)E 7-1-tu to 9-2H6,

.@fdI1M dI8" U

bh"ijits Irewstmusit Ircuse l'.rpents ty (W's fot Billitsjs IOld! Rt.Ct'Ipts I)i hs soimts E X A M*P L E l'l.eit Ibigi/Erigineering thiestiwxt 6pignes.t l'I. set Gristrittlui/Gmpletion fiarstrittlui Cuitr.s ts Gerstru.tka Msuff luier's Resoistes (a) tia le.r fuel Leeitlesysicy frustccftzs Mal Dislasumuits

(!!'I *l!$60

.. =::::::..: :: ::

O*

R o

(a) Ira.luks payas avoyet, plait querattui mui corporate allocattat.

R c)

W

08/03/83 ATTACHMENT 2 LICENSE MAINTENANCE

1.0 DESCRIPTION

OF LICENSES 1.1 LICENSE REQllIREMENTS AND WNP-3 LICENSE STATUS The Supply System currently possesses an Nuclear Regulatory Commission (NRC) construction permit for WNP-3. NRC regulations do not require that any phase of construction of a total project be completed on a specific schedule. The only requirement relating to construction schedule is that construction be completed by the latest completion date specified in the construction permit. The latest completion date may be extended by the NRC for " good cause".

The WNP-3 Con-struction Permit (CP) specifies a latest construction completion date of January 1, 1985.

1.2 LICENSE EXTENSIONS It has been typical for NRC licensees to seek construction permit amendments to extend latest completion dates.

Such amendments are usually granted.

" Good cause" for such amendments can be demonstrated by factors beyond the licensee's control such as labor difficulties, changing regulatory requirements, and adverse economic conditions.

However, applications for extension are required to be noticed in the Federal Register and an opportunity given for a public hearing if requested by an intervenor.

It will be necessary to request an extention from the NRC prior to the construction completion date. However, it is not necessary to complete the process and obtain approval before the com-pletion date. Under NRC regulations, the Construction Permit will remain in effect pending NRC action on the request.

The Coalition for Safe Power, the intervenor on the WNP-3 Operating License application can be expected to intervene on the WNP-3 Construction Permit extention application. The Supply System's and the NP.C's legal staffs will be..

i

N/ awl @J required to develop and file briefs in opposition to the petition. A pre-hearing conference would then be required to determine whether the petition would be admitted and a hearing required.

The review of petitions, conduct of the pre-hearing conference, and the conduct of the hearings is accomplished by a board of administrative law judges which constitute the Atomic Safety and Licensing Board.

Should a hearing be necessary, the Supply System's legal staff, licensing staff and the technical staff would be required to support the effort to contest the petition. Failure to support this activity could result in loss of the Con-struction Pemit.

1.3 NRC OVERVIEW 0F DELAY The NRC Inspection and Enforcement staff has a direct interest in the activities associated with preservation of the facility records and hardware. Their concerns were considered during the formulation of plans for deferral of WNP-3 construction, and they will be kept informed of pertinent activites.

While the NRC staff has the authority to require licensees to "show cause" why permits should not be modified, suspended or revoked in view of significant new information, the issuance of a "show cause" order solely because of an extended construction delay on WNP-3 is considered to be unlikely, particularly in view of the state of completion of the project and the likelihood of eventual re-sumption of construction.

In response to a petition filed by the Coalition for Safe Power to have the WNP-4/5 Construction Permits revoked because of the termination of these projects the NRC replied that the project terminations did not pose any hazard to public health and safety and as such the petition was denied.

The NRC has reversed their earlier position that no action would be taken on the Construction Pemit extension request fer WNP-1 until resumption of construc-tien. An extension was granted to June 1,1991 for completion of construction.

Therefore, WNP-3 should be prepared to proceed with the extension process in the event a similar decision is reached on the WNP-3 application.

_2_

08/03/83 As stated above, the NRC response to the Coalition for Safe Power petition to withdraw the construction permits for WNP-4/5 on the basis of their termination was that the terminations do not pose any hazard to public health and safety, and the petition was denied.

The NRC staff is expected to take the same posi-tion with regard to the construction delay of WNP-3.

1.4 SITE CERTIFICATION AGREEMENT As a requirement of State Law, parties desiring to construct energy facilities in excess of 250 megawatts must meet the application and certification require-ments of the Washington Energy Facility Site Evaluations Council (EFSEC). The Supply System has secured the requisite Site Certification Agreements for WNP-3.

Early in 1982, the Supply System briefed EFSEC on the various stages of the termination process for WNP-4 and 5.

On March 11, 1982, the Supply System requested EFSEC to defer any actions that would impact the Site Certification Agreements for WNP-4 and 5, as a facility with a license was definitely more marketable than one without. On April 12, 1982, EFSEC took formal action to concur with the request, and will postpone any consideration of Agreement amendments until later in 1983.

On May 20, 1982, the Supply System submitted a similar request to EFSEC for WNP-3. On June 14, 1982, EFSEC agreed "to continue to treat WNP-1 as a licensed facility and to take no action which would in any way diminish or jeopardize the current Site Certification Agreement for WNP-1."

A similar agreement is ex-pected to be available for WNP-3 after discussions with EFSEC.

t i

WASallNETON diaLIC PotEst SUPPLY SVSIDI AliACMM 3 IRACLEAR PROJECT ND. 3 Sheet 1 of 2 CONSTRUCiloll FMIS CASH FLOW

($ Ill Ill0USAfss) 1984 1985 Total Idil' ' " '

Oct hr Dec Jai feb Mu-W My Ja dal Asg S,

10-1-84 to 9-3}& 7-I-al to 9.n m_

Dtyireil3 alace -o-74000 B

bfD lawe.tmas.t Irroe 1500 P.ounts ty IW's 1631 1140 2303 901 894 951 904 917 1138 907 907 908 13501 12685 t6 t Billings 3805 2659 5375 2101 2087 2220 2108 2138 2655-2117 2117 2117 31499 94815 heal ikreipts

$436 3799 7678 3002 2981 3171' 3012 3055 3793 3024 3024 3025 45000 Jgg fli Jarsousas Piet DesigvErgituring 452 454 457 459 461 464 467 470 473 470 470 470 5567 29211 husethasal Epipest 569 357 1099 219 219 220 219 219 220 220 220 220 4001 50282 l' lait Gsstnttlu&mpletim 6682 68116 Gastnx. tim Cuar.scis 1532 442 594 435 410 593 4e'0 437 498 437 437 437 Sill 29385 Gsstnttim muir 416 418 420 422 421 426 429 432 434 430 430 430 18310 51498 (kaar's Resuates (4) 1465 1465 1465 1165 1465 1465 1465 1495 2165 1465 1465 1465 4668 3704 ina:les fin:1 1

2 3643 2

2 3

2 2

3 2

2 3

1661 10085 (asitir9ny 1000 661 739 h ustee Facs hAal Dislarsemias

$436 3799 1678 3002 2981 3171 3012 3055 3793 30/4 3024 302'.

45ggg 243000 1:$ lies Halmre -C-0- -- j

.n ok o

(al lea:lules pvyaa meafsmst, plant quratim arut aalurele allocatim.

g

.e

t WASHIBGTON PUBLIC PoiKR SUPPLY SYSIEg ATTACHMENT 3 Ml8 CLEAR PROJECT No. 3 Sheet 2 of 2 CiNSTRUCT1081 fuse CASH FLOW (flOklU5hfE35')

1983 1984 101Ai Aly Aug Set Oct br Ibc Jan

. Feb Mar 4r Mer Asie Aly Asg 5+t 71-83 to 9-3tH4 tispelg B.alag 74000 58321 42370 30784 18292 6721 74000 Ihf d.5 i

i Inwestmas4 Innue 500 400 300 200 100 1500 Penasts ty 100's 6891 6%0 5051 5396 4959 4606 4591 3629 2728 2257 3309 2247 2701 2199 1660 59184 tot Billin.js 4126 10811 8475 6366 5267 7720 5244 6301 5132 3874 63316 lotal ihreipts 7391 7360 5351 55 % 5059 8732 15402 12104 9094 7524 11029 7491 9002 7331 5534 124000 D,tgawasA,s, Plar th:si Vtrajirusing 2368 2303 2059 2677 2260 1820 1650 1686 1546 1346 1090 934 789 655 461 23644 f

Pngaatta,al Epipurg 5636 4637 5108 4438 4937 7276 4700 2002 1148 894 1633 997 1836 519 520 46281 PlaA Gmtrts.tia VDmpletim Gsistnttim Quitra.ts 7354 10217 5416 5636 4736 2920 5057 3384 2307 1555 4490 1647 2704 2562 1449 61434 cmt,u; tim Msurpr 1809 1913 1752 3288 2877 1666 1221 1394 1233 1238 1244 1366 1351 1128 794 24274 a,ar's Resentes (a) 5800 4129 2499 1947 1718 1668 2672 2527 1757 1389 1470 1362 1320 1465 1465 33188 h.les ru:)

3 2

3 2

2 3

2 2

3 2

2 3

2 2

3 36 n,4 isayny 1100 1100 1100 1100' 1182 1000 1000 842 8424 Trmtce fit:s 100 110 100 100 100 100 100 9

719 lotal DistiswasAs 23070 23311 16937 18088 16630 15453 15402 12104 9094 7524 11029 7491 9002 7331 5534 198000 fidig Balare 58323 42370 30784 18292 6721 O A

(a) Ircluk:s puy.su aseymmt, pimt operatian ad corprate aWcatim.

Rb r

08/03/83 ATTACHMENT 4 300HNOI1YA83S3Bdl!!,

b ll I

a

/ //

I

~

3

!"/l 5

/

E I l//

G

/

I M

l l

~I 4

/ ll i

~

>-dm d

Il I

~I e-

/

i CD O Z

j l

' h 5$ 05 s

8 EE 8E lg*

)

1 1 I

E e

a os a w l

/

//

I a

/

!R I

E 8

U$

5g

/E i

/E I

5. 8 88 z

e ils

/$/

I g

/ s/

/ g I

o-z 5

Es sI S

E d

l

///$I l

E

//

/ gls; l

g a

/

,/

/

u i

=

/s

/

i"I

/U

/

/

/

E

/

/

g&b"g/

/

/

i 8

/

/

l m

l D

m e

8I

MONTH CONTRACTOR CRAFT CONTRACTOR NONMANl!AL EBASCO CM ERASCO AE SUPPLY SYSTEM

  • TOTAL JULY 250 502 380 280 358 1770 AUGUST 213 357 350 246 280 1446 SEPTEMBER 179 256 300 232 256 1223

~0CTOBER 135 189 250 211 251 1036' NOVEMBER 113 137 250 200 242 942 DECEMBER 92 117 250 187 231 877 JANUARY 60 96 250 158 228 792 FEBRUARY 60 90 250 140 226 766 MARCH 60 71 250 118 222 721 APRIL 60 66 225 97 219 667 MAY 60 54 175 80 214 583 JUNE 60 44 125 72 204 505 1342 1979 3055 2021 2931 11328 PRESERVATION MODE 45 20 80 50 204 399

%?

5! o

  • NOTE: Supply System manpower includes equivalent manpower for indirect overhead and corporate allocation h!,

as an estimated value.

g; e

U1

MANAGEMENT PLAN FOR EXTENDED CONSTRUCTION DELAY 0F WNP-3 ILEVEL 111 AUGUST 4,1983 l

Washington Public Power Supply System

_= _ -_.

s TABLE OF CONTENTS SECTION PAGE PLAN STRUCTURE i

1.0 FINANCIAL 1

2.0 LICENSING 4

3.0 ASSET PRESERVATION 8

4.0 CONSTRUCTION ACTIVITIES 12 5.0 ENGINEERING 15 6.0 QUALITY ASSURANCE 18 7.0 DOCUMENTATION AND RECORDS 21 8.0 COMMERCIAL ACTIONS 25 9.0 MANAGEMENT OF EXTENDED CONSTRUCTION DELAY 30 2

l s

1 I

I

08/03/83 PLAN STRUCTURE LEVEL I - EXECUTIVE

SUMMARY

This portion is intended to provide executive level information relative to the plan, management principles and the most critical aspects of the construction delay.

LEVEL II - DESCRIPTION OF PERFORMANCE BY FUNCTION This is intended to describe, at the management level, those functions which will or might be performed during the construction delay.

This level II portion together with Level I constitutes middle management's guidelines.

LEVEL III - SUPPORTING DOCUMENTS These documents are all of the supporting procedures, data, budgets, etc., which support the Level II and I.

These are internal documents and are not intended for consolidation or distribution outside the project except as may be required.

t l

l l

l I

i l

i a.

e t

TABLE I WASHilIETGIl PUBLIC PotER SUPPLY SYS1[N InsCLEAR PROJCCT IIG. 3 Sheet I of 2 COIISTRUCT1001 fille CA531 FLOW

- IfIlnliolfSAlms) 1983 1984 10fn Aly Aq Set att hr Dec Jai Feb Mar Apr Mer Ase Aly Ag 5:14 7-1-al to 94 34 tt3 mint alate 74000 58321 42370 30784 18292 6721 a. 3_ 74000 6

D i

NSli5 i

Y lemenst latime 500 400 300 200 100 1500 P.yassts ty lau's 6891 6960 5051 5396 4959 4606 4591 3629 2728 2257 3309 2247 2701 2199 1660 59184 fu Billitys 4126 10811 8475 6366 5267 7720 5244 6301 5132 3874 63316 lotal ikteipts 7391-7360 5351 55 % 5059 8732 15402 12104 9094 7524 11029 7491 9002 7331 5534 124000 DiJanssasits Pl.m.t Desigi/Lrvjiruring 2368 2303 2059 2677 2260 1820 1650 1686 1546 1346 1090 9 34 789 655 461 23644 Iwpattael Erpalpiest 5636 4637 5108 4438 4937 7276 4700 2002 1148 894 1633 997 1836 519 520 46281 Plait Os6tna. tim /Qmgeletim Gsstnattim Gastracts 7354 10217 5416 5636 4736 2920 5057 3384 2307 1555 4490 1647 2704 2562 1449 61434 n.,structim Niayr 1809 1913 1752 3288 2877 1666 1221 1394 1233 1238 1244 1366 1351 1128 794 24274 asa r's inesamtes (a) 5800 4129 2499 1947 1718 1668 2672 2527 1757 1389 1470 1362 1320 1465 1465 33188 terlearFia:1 3

2 3

2 2

3 2

  • 2 3

2 2

3 2

2 3

36 nadirmj sty 1100 1100 1100 1100' 1182 1000 1000 842 8424 Trustee tws 100 110 100 100 100 100 100 9

719 Total Dislaswasats 23070 23311 16937 18088 16630 15453 15402 12104 9094 7524 11029 7491 9002 7331 5534 198000 Irshrg ibt.mm e 58321 42370 30784 18292 6721

- O'- I s

8 i - b c

(a) Incitales proyau asiagtment, plat geratim ard corporate ellacottm.

R-B 9

~

08/03/83 1.0 FINANCIAL 1.1 GENERAL Funding of the WNP-3 extended construction delay is limited to approximately

$243 million for the period July 1, 1983 through September 30, 1985 (this coincides with BPA's fiscal years).

Scurces of funding are as follows:

07/01/83 - 09/30/84 Construction & Fuel Fund Balance as of 6/30/83 74.0 M Estimated Investment Income 1.5 M Payments by 100's 59.5 M Payments by BPA 63.0 M

$ 198.0 M 10/01/84 - 09/30/85 Payments by 100's 13.5 M Payments by BPA 31.5 M 45.0 M Planned expenditures for the period January 1983 through September 30, 1985, must not exceed the cumulative BPA contribution profile.

Table I summarizes the estimated cash expenditures through September 30, 1985.

1.2 BUDGET AND CASH FLOW REQUIREMENTS See Attachment 1 to Executive Summary (Level I) of this Management Plan.

e _ _ _ _ _ _ _ _ _.. _.. _

.J

vu i

(

i WASHINGTON PUBLIC P0lfR 541PPLY SYSIEN TABLE I lefCLEAR PROJECT ND. 3 COIESTRUCTICII FUIS CASH FLOW Sheet 2 of 2

($Ill1HOUSAlmS) 1984 1985 Total lutal ' ~

Oct kw Dec Jm Feb Mr 4r Mar Asi dal Asj Sep 10-1-Bi to 9-3&E 7-1-ni to 9 3) tt, Ikyi33 alare -o-74000 1 8 Sldd.5

.W Irwestmard httme l'. spuds ty IGPs 1631 1140.

1500 2303 901 894 951 904 917 1838 907 907 908 13501 72685 ftt Dillisajs 3805 2659 5315

-2101 2087 2220 2108 2138 2655 2117 2117 2117 31499 94815 Total Rareipts 5436 3799 7678 3CO2 2981 3171 3012 3055 3793 3024 3024 3025 45000

. j69000 Iqslas sesuas l't.eit D stydigiarring 452 454 457 459 461 464 467 470 473 470 470 470 5567 29211 liqisdesal Dpi suit 569 357 1099 219 219 220 219 219 220 220 220 220 4001 50282 l

l'I.e.t Gsistrutiud4mpletim 668?

68116 6mtru.tlui ContrdLis 1531 442 594 435 4l0 593 410 437 498 437 437 437 Sill 29385 Osritna.tia; Mosfr 416 418 420 422 421 426 429 432 434 430 4 30 430 18310 51493 insar's Resmates (a) 1465 1465 1465 1165 1465 1465 1465 1495 2165 1465 1465 1465 1668 3704 ris.les finel i

2 3643 2

2 3

2 2

3 2

2 3

1661 10085 i es Ainupsty 1000 661 h ustm fws I19 lutal DivarsemuAs

$436 3799 7678 3002 2981 3171 3012 3055 3791 30J4 3024 3025 -

45.000 243000 0.hesj 1141mce -c-..::::..

s

~ -.. -

'a'Q (a) ha-Itals lirT;spissiinsL*ymit. [1144 pdian mal wate Olixdial.

8N m

08/03/83 2.0 LICENSING 2.1 NOTIFICATIONS The NRC was formally advised of the 30 day construction delay decision by the Executive Board and the decision of July 8,1983 to implement an immediately construction delay until an assured source of funds becomes available to con-tinue construction. These notifications were made to both Nuclear Reactor Regulation (NRR-Bethesda) and Inspection and Enforcement (I&E - Region V) by formal letters.

No other formal submittals are considered necessary at this time to maintain the WNP-3 Construction Permit or to satisfy normal practices of keeping the NRC informed of significant activities.

A meeting with NRC staff (Bethesda)washeldonJuly 19, 1983 to review the Supply System's planning in regards to completion of the responses to NRC round one questions, completion of the environmental review and submittal of the construction delay implementation plan to the NRC staff. Additional meetings with the NRR and I&E staffs will be scheduled if it appears necessary to keep them informed of WNP-3 implementation plans.

Infonnal discussions were held with the Washington State Energy Facility Site Evaluation Council (EFSEC) officials on June 6, 1983, at which time the ac-tivities planned for the delay period were discussed.

Formal notification to EFSEC of the extended construction delay was provided on August 1,1983.

2.2 LICENSING APPLICATIONS The operating license application for WNP-3 was docketed on August 22, 1983.

The Supply System responses to the NRC Safety and Environmental review questions l

and issues will be limited due to the construction delay and funding limitations.

j Emphasis will be placed on completing efforts in areas where closcout of issues l

appears feasible without major expenditures or where changes in technology are not expected to invalidate current efforts if a prolonged extended delay occurs.

l The NRC Safety and Environmental reviews have proceeded to the point where:

i e

The environmental questions have been received and responses provided to the NRC staff.

The NRC staff is prepared to generate a craf t invironhental statement.

e The completion is expected by Septembe,r.1983.

i

~

e A series of six submittals of safety review questions (approximately 300) have been received.

Three branches have not provided questions to.

date. A significant fraction (approximately 2/3) are~ scheduled to'be completed and responses provided to the NRC staff.

s.

TheNRCstaffhasagreedtocompleteapartialdraft)afetyEvaluation e

Report (SER) based upon the state of completion of question responses.

1 2.3 OPERATING EXPERIENCE REVIEW WNP-3 nill continue to screen and review operating experience documents generated by NRC (Bulletins, Circulars, information notices), INPO (Operating Experience Reports - OERs), and Combustion Engineering (CE Infobulletins). Commitments 4.

made regarding design or operation which result frem.the reviews will be tracked for implementation later. WNP-3 will continue to respond to NRC Bullatins, as,

necessary. The size of the operating experience documents backlog will be

~

monitored and a plan will be generated during the construction delay perio'd to

~ '

~

s ensure that the backlog can be worked off prior to fuel load.

2.4 CURRENT ISSUES REVIEW As part of the ongoing efforts, the WNP-3 staff will continue participation in l

the Combustion Engineering'0wner's Group and Generic Issues Industry Groups as'

-well as monitor generic licensing issues with the NRC and licensing activities on other Combustion Engineering plants.

i 2.5 REQUIRED ACTION l

2.5.1' Licensing Actions s

During the extended construction delay, Project Licensing will:

l l

e Complete review and approval of a portion of the NRC Round One questions.,

, ~, 4 m

l x

e Support Partial Draft SER from NRC e

Resolve Stiff Clamp Issue with NRC Y

Complete;subcoppartment pressurization analytical tasks in response to e

NRC' questions

-~.s

~

e Complete NRC requested Structural Audit & Site Visit u

o Schedule and Conduct Security Site Visit Participate in Licensing' Board Pre-hearing conference to resolve issue e

of which contentions will require litigation, e'

Complete CESSAR-F FDA Activities.

L-o Complete Documentation of Licensing Commitments into General Tracking System (GTS).

,e Review commitment dates and develop basis for revision of dates to reflect slowdown.

,e Develop and submit FSAR/ER Amendments in support of Draft Environmental Statement (DES) and Draft Safety Evaluation Report (DSER).

e Initiate application for Extention of Construction Permit (Expires 1/1/85) e Prepare Plans and Licensing Strategies on major issues.

Gather documentation and review critical files for completeness, e

e Maintain involvement in CE Owners Group on shared basis with Project Engineering.

e Maintain membership and participation in industry groups associated with generic issues.

1 l L

08/03/83 I

e Monitor licensing meetings / hearings on other CE plants, o

Monitor NRC meetings / hearings /rulemakings on generic licensing issues and unresolved safety issues.

e Continue interface with NRC and other regulatory agencies.

2.5.2 Nuclear Safety Assurance Actions e

Complete establishment of the Operating Experience Review (0ER) data bas.e (tracking list),

e Screen Operating Experience Review (0ER) backlog.

e Screen, track and coordinate reviews of new incoming OER information.

o Evaluate OER information and prepare recommendations for appropriate management.

Review procedures for Plant Operations Committee (P0C) meetings.

e Participate in resolution of remaining issues of field design change and e

NCR review council.

Finalize development of the onsite Nuclear Safety Assessment Program o

Plan.

e Complete procedures for Operating Experience Reviews.

Establish plans for nuclear safety assessment activities and procedures e

as necessary. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

08/03/83 3.0 ASSET PRESERVATION 3.1 PURPOSE To provide the methods to be utilized to preserve WNP-3 assets and the capacity for a rapid restart while optimizing Supply System financial and personnel resources.

3.2 OBJECTIVES / REQUIREMENTS 3.2.1 Preservation of Installed WNP-3 Assets Systems, components and structures must be preserved and maintained in the most cost effective manner possible to satisfy commercial, regulatory, and code requirements.

Preservation considerations must ensure licensability of the plant and provide the capability for efficient and expedient resumption of start-up activities and operation of the plant. To satisfy these goals the following actions are to be taken:

Maintain a cold iron watch with the following responsibilities:

e

- Operate temporary and permanent plant systems which are necessary to preserve the plant such as HVAC, Electrical Distribution, Lighting, and Dewatering, etc.

- Continuous security of plant island.

- Provide control room functions for canmunications, maintenance activities and surveillances, etc.

- Operation of fire protection systam.

- Operate other plant systems necessary to facilitate extended plant construction delay such as construction water, sewage treatment, etc.

l 4.

08/03/83

- Maintain records of above activities to satisfy licensing and in-surance requirements.

e Maintain a Maintenance and Technical force with the following responsi-bilities:

- Evaluate, determine and implement required preservation activities.

- Evaluate, determine and implement required long term preventive maintenance and preservation activities in the event of a prolonged construction delay.

- Correct deficiencies identified during preventive maintenance.

- Maintain temporary and permanent plant systems which are necessary to preserve the plant such as HVAC, Electrical Distribution, lighting, and Dewatering, etc.

- Maintain plant systems necessary to facilitate extended plant con-struction ' delay such as construction water, sewage treatment, etc.

- Preserve and maintain existing Operational Spare Parts.

Procure, receive, store and issue parts and supplies necessary for plant preservation.

- Maintain all permanent plant activities to satisfy licensing and insurance requirements.

3.3 PRESERVATION OF RESTART / START-UP AND OPERATIONS CAPABILITIES WNP-3, at the time of construction delay, was at the point of Provisional Acceptance and Start de testing of several major plant systems.

The permanent plant staff and the s. art-Up contractor conduct the start-up activities at WNP-3.

The folicwing joint actions must be taken to preserve the ability to maintain the presently scheduled sequence between construction completion, start-up and operation of the plant: '

1

N I

e Complete fragnet development to support cold hydro testing.

e Maintain presently existing programs and procedures.

e Develop the procedures to start up those systems necessary to preserve the plant.

e Maintain the inventory of plant components / systems to support both preservation, construction completion and start-up of the plant.

- Material Equipment List (MEL)/ Construction Commodity Control Systems (CCCS) completion, integration and upgrading.

- Field verification and identification of installed equipment to support preservation and permanent plant documentation, e

Review the start-up schedule through commercial operation, develop detailed fragnets, levelize system acceptance dates and integrate into the master construction schedule.

- Maintain records of above activities to satisfy licensing and in-l surance requirements.

l 3.4 BENEFITS i

e Performance of the above actions will result in the following:

- Minimize the financial loss to the Supply System by retaining those highly technical personnel recruited and trained at great expense.

I

- Retention of the personnel necessary to ensure licensability, start-up and operation of the plant.

l

- Ensures the most cost effective and highest quality maintenance and preservation of the plant....- - _..

senmin n s

Provides maximum opportunity for owner involvem:nt throughout the extended delay and resumption of start-up activities.

Provides maximum opportunity for permanent plant personnels' familiar-ization with plant systems and components which will enhance the cost effectiveness of subsequent start-up and operations.

- Provides the minimum required capacity for restart capability.

+

l 1

t 1._ -,, _

4.0 CONSTRUCTION ACTIVITIES 4.1 Construction Objectives The primary Construction objectives to support the extended delay are:

e Bring work to a logical and reasonable stopping point.

e Support the turnover of documentation through the clearing of Non Confor-mance Reports (NCRs), Document Deficiency Notices (DDNs), Conditional Releases and completion of in-process work.

Implement cost effective plans to complete work required to preserve e

assets and ensure capability of construction restart.

4.2 CONSTRUCTION PLAN Construction activities have been reviewed in detail for each construction contract.

The activities identified below represent the minimum effort required to provide a controlled rampdown and prepare the project for an extended con-struction delay. The asset preservation program reflects the local atmospheric conditions (i.e., high humidity) and the associated detrimental effects on equipment.

Inherent in the construction plan is preparation and implementation of long tenn preservation of assets, securing quality assurance documentation, inventorying and assuming custody of all permanent material and equipment.

The proposed plan provides the following types of work:

o Complete in-process welds and associated Non Destructive Examination (NDE) work.

e Complete fire protection pumps and tanks and energize completed portions of permanent system.

e Complete mechanical and electrical work at makeup water wells.

(Necessary to provide ability to cycle pumps.)

l 08/03/83 l

e Complete certain identified terminations, and pull pre-cut cable.

(Facilitates equipment closure.)

e Install cathodic protection necessary for long term layup.

(Engineering requirement regardless of term of layup.)

e Perform touch up painting and coating, as specified, such as external steel surface areas of the containment vessel.

(Required to remain withindesigncorrosionallowance.)

e Complete weatherizing of administration building and site access facility.

(Requirement for preservation of permanent assets located and stored within these facilities.)

e Continue care and maintenance on equipment as identified by the Con-struction Manager; start turnover of asset preservation responsibilities to Owner.

Install Reactor Vessel (RV) head and layup Nuclear Steam Supply System e

(NSSS) system.

e Inventory and assure custody of Owner and Contractor furnished permanent plant materials and equipment.

e Review, disposition, and closecut as appropriate NCRs, DDNs and Con-ditional Releases.

e Carry out drawing roll-up and documentation turnover on all completed work.

Bring documentation to current state on all partially completed work and e

turnover to the Construction Manager.

e Perform walkdown of plant and enter status in Construction Commodity Control System (CCCS) and support design verification program as directed by the Construction Manager.. _ -.

08/03/83 e

Energization of the 230 KV line.

(Cable manufacturer recommendation for long term preservation.)

It has been determined all activities recommended are essential to preservation of assets.

4.3 ADDITIONAL CONSTRUCTION RECOMMENDATIONS Excluded from the plan due to financial constraints but recommended by the AE/CM for long term preservation, are the below listed activities.

It is emphasized that, while undesirable, the Project can fully recover from these delays.

e Complete concrete placement of Reactor Building Dome.

o Class I backfill and associated mechanical and electrical work.

e Energization of permanent plant heating and ventilation system (freeze protection).

e Complete balance of permanent fire protection system.

e Install crane access exterior doors of Fuel Handling Building.

e Complete assembly of HESS structure and store in Reactor Building.

e Install construction access hatch in Reactor Building.

9.

08/03/83 5.0 ENGINEERING The extended construction delay engineering Management Plan has been structured to fulfill the primary objectives of preserving the engineering design status of WNP-3 Project; to preserve the engineering in consonance with the licensing process; and to immediately support design completion, construction and start-up at the time an assured source of funding for continued construction can be obtained.

5.1 ENGINEERING PROGRAM OBJECTIVES The primary objectives to be accomplished at Project WNP-3 during the extended construction delay time frame are:

e Support Licensing activities necessary to preserve all state and federal licensability requirements.

e Finish work currently on the board and not start any new work.

e Documentation / records will be gathered and vaulted.

e Non Conformance Reports (NCRs) will be dispositioned or closed out for the terminated contracts / contractors.

e Vendor equipment qualification activities will be closed out.

e ASME Code requirements will be preserved to permit restart, e

Provisional acceptance activities will be held in abeyance until restart of construction.

9 5.2 SCOPE OF ENGINEERING ACTIVITIES Specific Engineering activities are required to preserve the design and to enable the project to restart with minimal effort at any time during the period associated with the extended construction delay.

During the extended construction delay period, priority will be given to the following activities:

03/03/83 e

Engineering activities on WNP-3 will continue et a limited level for those specific identified activities.

A documentation / drawing roll-up function will be performed where and when appropriate during this period.

During the extended construction delay period, the following engineering activities have been identified as those that will be continued on a limited basis.

- Complete Dry Cooling Tower Design

- Resolve Equipment Nozzle Load Discrepancies

- Develop Mechanical Equipment Qualification Plan

- Track System Review Open Items

- Resolve Equipment Qualification Open Items

- Resolve Stiff Clamp Concerns

- Review Engineering Baseline For Completeness

- Maintain Piping & Instrument Diagram Drawir.gs

- Continue Change Management Activities

- Continue System Design Freeze Activities

- Monitor Chehalis Riverbank Protection in the vicinity of the Ranney Wells

- Identify and select records to be gathered and vaulted

- Complete Actions Items List from System Review Program

- Participate in CE Owner's Group activities in an overview role rather than as an active participant, e

Work will be completed to the extent necessary to satisfy existing ASME Code requirements or to allow bridging of ASME requirements on project restart.

e A review of all remaining engineering activities for plant completion will be conducted followed by preparation of a detailed scope of work for plant completion activities.

e Engineering support to the structures and security reviews requested by the NRC will be completed according to the current schedule of October 1, 1983.,

08/03/83 e

Detailed program plans will be developed for performance of a technical review of ASME design / stress reports to assure Owner's compliance with NA or NCA-3260, and for implementation of an independent design verifi-cation of selected WNP-3 safety related systems.

e Continue to interface with Washington State Regulatory Agencies to preserve Site Certification Agreement, e

Review NRC bulletins for required engineering actions.

s' The Change Management process will continue to exist with all forms of Project Change Proposals (PCPs) available for use.

The PCP process will be simplified to the extent practical. Change dispositions of Deferred and Approved / Deferred will be added to the process as many decisions will relate only to concept with actual funding and implementation deferred.

5.3 ENGINEERING ACTIVITIES DEFERRED During the extended construction delay of WNP3, a number of engineering acti-vities previously identified in the FY84 budget will be deferred or reduced in scope because of limited funding.

Examples of these activities are as follows:

e Design Change /NCR Council Activities e

TMI Action Items e

Design Verification e

ASME Section XI Programs e

As-Built Program o

Security System Procurement e

Chehalis River Work Completion Control Room Human Factors Review e

e Game Mitigation Plan Design and Implementation e

Certain ASME Owner's Designee Activities l

l 1 i 1

08/03/83 i

1 6.0 0'JALITY ASSURANCE l

i The extended construction delay program addresses the following Quality Assurance requirements necessary to preserve assets, plant licensability, and support subsequent construction completion and plant start-up.

6.1 QUALITY ASSURANCE PROGRAM The Supply System Design and Construction Quality Assurance Requirements and l

Operational Quality Assurance Program Description will continue to be imple-

]

mented during the extended construction delay. Applicability of the programs i

will be based on existing organizational structure and responsibilities. The Project Quality Assurance organization will continue to be primarily responsible for Project /AE/CM overview while the Plant Quality Assurance organization will j

be responsible for overview of the plant organization.

]

6.2 PRESERVATION AND STORAGE REQUIREMENTS i

1 Installed or warehoused equipment shall be maintained in accordance with manu-facturer's recommendations and/or applicable design requirements and standards,

)

or Engineering-approved alternatives.

l Implementation of the asset preservation program by the plant organization for installed equipment shall be verified by Supply System Quality Assurance through site surveillances/ audits.

Implementation of the asset. preservation program for warehoused equipment and l

ASME materials shall be verified by Ebasco Quality Assurance through site audits.

6.3 PROCEDURES / INSTRUCTIONS l

Applicable existing procedures will continue to be implemented to assure that the quality of materials, components and structures, including partially com-pleted structures, is adequately preserved during the period of the construction l.-.

08/03/83 delay. Additional procedures will be developed and implemented as necessary to describe turnover of responsibilities for the preservation of assets.

6.4 RECORDS Documentation for work completed (and partially completed), including main-tenance and qualification records, will be reviewed, accepted, maintained, and stored in a record storage facility to which the Supply System has assured access.

The status of construction tests and inspections performed prior to suspension of work will also be documented, reviewed and stored in a records facility accessible to the Supply System.

6.5 ASME CODE WORK The Construction Manager's ASME Manual will continue to be in effect.

6.6 QUALITY ASSURANCE ACTIVITIES DURING TURNDOWN AND PROJECT DELAY The following QA responsibilities will continue during the WNP-3 extended construction delay, with primary focus on preservation of assets and control of quality records.

Extended construction delay activities shall be accomplished in accordance with NRC requirements and Supply System connitments.

Maintain control of notifications, corrective actions and commitments to e

the NRC.

- Verify corrective actions and closecut of NRC items.

- Track ongoing commitments to NRC.

- Status all NRC items from Construction Permit to present to facilitate restart.

e Overview and monitor AE/CM and Contract Quality Assurance activities. ___

08/03/83 e

Surveillance of as-built / status of work.

- Participate in development of program for closecut and statusing of construction work.

- Overview development of ASME partial N-5 data reports.

e Overview and audit records turnover, records review and records storage.

- Verify records review and statusing processes are working.

- Verify contractors installing ASME Section III systems implement programs for ' completing partial N-5 data reports.

- Verify systems are implemented to confirm records reflect hardware.

e Verify proper identification, reporting and disposition of nonconformances.

e Evaluate deficiencies as defined by 10CFR50.55(e) and 10CFR21.

e Monitor development of WNP-3 asset preservation program and conduct surveillances to verify implementation, e

Close out open audit findings.

e Perform vendor surveillances.

08/03/83 7.0 DOCUMENTATION AND RECORDS This section describes the requirements for records and documents needed to preserve the assets of WNP-3 and to assure licensability.

7.1 RECORDS REQUIREMENTS In order to preserve the assets of the project, all WNP-3 documents 2.nd records must be collected, reviewed, indexed and stored at the Project Site during the extended construction delay. Documents and records in the custody of the Contractors will be collected, processed and stored in a central on-site records facility by the AE/CM.

Except as noted in Section 7.2, records and documents presently in the custody of the Supply System will be received, maintained, processed and stored for the Supply System by the AE/CM in a central on-site records fac lity in accordance with existing Supply System procedures and standards, and in accordance with user needs as to form, storage and retrieval requirements.

The consolidation of the records processing activities within one organization at the site will assist in establishing the Records Transition organization to systematically collect, process, store and retrieve documentation to ensure a complete set of documents and records to complete construction, test and start-up and to license, support and operate the plant.

Specific requirements by organization are described in the following subsections.

7.1.1 Architect / Engineer and Construction Manager (AE/CM) t l

(

The AE/CM shall retain all records currently in their custody and shall maintain I

within one records processing facility records currently in the custody of the Supply System except as noted in subsection 7.2.

i The AE/CM shall identify, collect, review, accept and maintain all contractor I

documents and records currently not in AE/CM custody.

l The AE/CM shall establish a records receipt, review, indexing, microfilming and data entry function in accordance with established Supply System procedures and l _-

08/03/83 standards to ensure retrievability of all WNP-3 documents and records to main-tain licensability during the construction slowdown and ensure a complete set of records to complete construction, test and start-up and to support and operate the plant.

The AE/CM shall provide training to Supply System personnel to ensure orderly turnover of documents, records, and record processing systems prior to com-mercial operation.

7.1.2 Contractors Contractors will submit their records to the AE/CM as noted in subsection 7.1.1 unless otherwise directed by the Program Director. The Supply System will verify adequacy of records received, reviewed and accepted by tne AE/CM by audit surveillance.

7.1.3 Supply System The Supply System shall identify, locate and collect all WNP-3 records in its custody and except as noted in subsection 7.2, transfer those records to the AE/CM to be stored, maintained, processed, as applicable, within the central on-site record storage facility. The Supply System shall provide overview of this function to ensure compliance with Supply System procedures and standards.

7.2 RECORDS GENERATED DURING CONSTRUCTION DELAY Records generated during construction delay will be processed through the AE/CM central records processing system except as indicated below:

l e

Security records shall be retained by the Supply System.

7.3 STATUS OF CUST0DY OF DOCUMENTATION PRIOR TO CONSTRUCTION SLOWDOWN i

e Design documents and records are in AE/CM and/or contractor custody.

l l !

08/03/83 e

0 & M manuals are in Supply System custody.

e Generation documents and records are in Supply System custody.

e Procedures are in AE/CM, contractor and Supply System custody.

e Licensing records are in AE/CM and Supply System custody.

e QA program records are in the custody of the Supply System, o

Health Physics Chemistry records are in Supply System custody.

e Fuel Program documents and records are in Supply System custody.

e Contractor / Vendor Installation and Manufacturing records are in the AE/CM and contractor custody.

e Construction Test records are in the custody of the CM.

e Test and Start-Up records are in the custody of the Supply System.

7.4 REQUIRED ACTION e

Review and approve AE/CM Management Plan for Extended Construction Delay of WNP-3 Records and Documents.

(see Detailed Plan).

e Prepare and obtain approval of detailea WNP-3 Records Management Pro-grams as noted below to facilitate restart of construction.

- Technical Records Program

- Non Technical Records Program

- Nuclear Operation Program l

08/03/83 7.5 ACTIONS TAKEN TO DATE 4

- Transfer of WNP-3 Headquarters files to site initiated (See Detailed Plan, Transfer of WNP-3 Files From Headquarters to Site Transition Plan). Scheduled completion date for this transaction is 11/01/83.

- Direction given to AE/CM to establish microfilming, encoding and data entry capability, full implementation scheduled for 09/01/83.

E i

4 s

4 l

l i

08/03/83 8.0 COMMERCIAL ACTIONS 8.1 GENERAL The guidance and requirements specified in this section are necessary to ensure proper overall planning, support budget formulation, and facilitate cash flow forecasting and control.

It is emphasized that the Project will implement immediately those contractual actions that reduce the continuing commitment of funds to a minimum, while at the same time not foreclosing the options for restart within the next three to nine months.

Priority shall be given to the resolution of contractual issues on those contracts which are essential to our restart.

8.2 SPECIFIC ACTIONS 8.2.1 Prepurchased Equipment Project Management will make decisions with regard to prepurchased equipment and materials contracts. Contracts will be categorized into three distinct groupings as follows:

1.

Contracts to be allowed to run to completion.

l 2.

Contracts to be issued partial or total suspension, with the suspension l

to be lifted when project restart is identified.

l 3.

Contracts to be terminated immediately.

All contracts have been reviewed and suspensions issued for all work not started, except in one case in which current facts dictate other action.

Upon approval of the Management Plan, categories will be finalized and appropriate contract action' implemented. Data is currently available which reflects the following:

1.

Estimate of cost based on category assignment and cost flows through June 1984.

08/03/83 i

j 2.

Intended further action such as total suspension, termination or modifi-cation of partial suspension.

3.

Where no action is intended and the work proposed is to run to completion, that has been identified.

4.

Appropriate action will be taken when necessary to ensure that all data, material and/or hardware paid for is brought to a point where the resource has value and may be used at a future date for the completion of the plant.

Project management will prepare individual contract negotiation plans to support the contract actions referenced above. A continual iterative process beginning with the completion of the negotiation plans will be carried out in order that project cost / cash flow can be updated and adjusted as required. A schedule for negotiations containing a start and a completion date wiii ce prepared and should be available by September 1, 1983. Necessary Project Change Proposals and/or contract documents will be prepared and executed in accordance with established procedures.

8.2.2 Construction Contracts All construction contracts have been reviewed and a preliminary conclusion made as to whether the individual contract should be suspended in whole or in part, terminated in whole or in phrt, or allowed to run to completion. All contractors whose schedule required a site presence prior to May 27, 1983, have been suspended in whole or in part, with the single exception of the site services contractor.

Project Management has reviewed all contracts and the tentative plan for imple-ment.ing the Board's direction. Current recommendations are that nine contracts be maintained in partial suspension. These nine contracts, together with the site services contractor are considered to be the contracts required to maintain the capability of restart. As the period of construction delay is prolonged, the Project has identified the key dates upon which conscious decisions must be made regarding either termination or continued suspension of these nine con-

[

tractors. All other construction contracts are recommended for termination as l

soon as the plan is approved. !

=--

WWA@J l

Project management will prepare individual contract negotiation plans to support the necessary contract changes to implement the approved plan.

Based on this approved plan, projected cost / cash flow requirements will be reviewed and adjusted as necessary. An overall negotiation schedule will be prepared and available by September 1, 1983.

Negotiations will be carried out in accordance with that schedule.

This schedule will include both a start date and a com-pletion date for negotiations.

Necessary Project Change Proposals and/or contract documents will be prepared and executed in accordance with established procedures.

8.2.3 Headquarters Contracting Activities Service and prepurchase contracts that support, or are funded by WNP-3 and are managed by headquarters, are being given the same scrutiny and appropriate reports and cash flows are being prepared.

This activity has been accomplished by the Project Business Department, working in close coordination with the headquarters staff, the Project Controller, and the responsible manager who requested the service. Cash forecasts for these items are now stated at minimum required levels.

8.3 NUCLEAR FUEL The nuclear fuel contracts are under the technical control of the Technical Director.

The following actions are to be taken:

8.3.1 Initial Core - UF Supply, Allied Chemical Contract 3240-2A 6

l This contract supplied 395,780 kg of UF f r the WNP-3 initial core.

Storage l

6 was provided for through June 1981. Final shipment to DOE in May 1981 concluded l

l the contract requirements. Closeout is targeted for October 1983.

8.3.2 Enrichment Services, Department of Energy Contract DE-SC05-79UE4666 Under this Adjustable, Fixed-Commitment contract, DOE provides enrichment services for 30 years (through 2009). This covers the initial and reload cores.

Enrichment i

1 l l

08/03/83 of the WNP-3 initial core was completed in September 1981 and placed in storage at 00E. Full and final payment for the initial core enrichment services was made in October 1981.

Notices must be provided to DOE by July I of each year establishing future amounts of enrichment services and delivery requirements of enriched uranium. Further, the Supply System is committed to utilization of enrichment services in FY85 which are in excess of needs. To avoid significant expenditure, these services must be either sold or assigned.

8.3.3 Conversion Services, Kerr-McGee Nuclear Contract C-5391 This contract provides for conversion services and storage for two initial cores (WNP-4/5) and reload cores for all five projects through 1986.

The contract is based on a fixed commitment for conversion of 5,165,633 kg U to UF.

The WNP-3 6

reload allocation of this amount is 847,985 kg U, all of which is excess to present needs.

No conversion services are required for the initial core.

Cancellation charges are payable if actual quantities converted are less than the fixed amount.

Decision on disposition must be made by December 31, 1984 to avoid significant penalties.

8.3.4 Storage of Enriched UF, Department of Energy Contract EY-77-SA-05-5410 6

l This contract provides for enriched uranium storage services and storage containers for material enriched for any of the Supply System projects if the Supply System is unable to take delivery and alternative storage cannot be obtained.

In September 1981, the enriched UF f r the WNP-3 initial core was placed in storage 6

l at the DOE enrichment facility at Piketon, Ohio.

The material is stored in 19 l

DOE-provided storage cylinders. To ensure the initial core fabrication supply and plant restart capability, storage will be continued.

8.3.5 Initial Core Fabrication, Combustion Engineering Contract 3240-2 This contract covers both the purchase of the NSSS and the design and fabrication of the initial core.

In November 1982, CE was released to complete the final fuel design. An FSAR amendment was submitted for Supply System review based on _

~

08/03/83 the final fuel design; this review has generated only minor comments.

On March 29, 1983, all work on the asymmetric load analysis was suspended. Completion of this analysis is required before fuel fabrication can begin.

No further action is planned pending additional funding.

8.3.6 Reload Fuel, Exxon Nuclear Contract 3240-2B This contract, which provides for WNP-3 reload fuel supply and fabrication, has recently been upheld in the King County Superior Court.

Resolution of several issues remain consistent with the Court's ruling.

Periodic notices to Exxon establishing delivery requirements, however, continue to be a Supply System obligation.

8.3.7 Contract C-13265 This contract covers additional tasks required and related to, but not included in the scope of the 3240-2 contract.

Not-to-exceed funding is provided on a task basis. Continuation of fuel related efforts by CE to maintain and ensure plant licensability are anticipated.

8.3.8 Additional Enrichment Modification of enrichment levels of the intial core is required to meet plant operating requirements and has been defined.

Based on a three-year suspension of WNP-3, actions to contractually implement this additional enrichment must be completed by mid-1986 to support fuel fabrication in 3rd Quarter 1987.

4 i

l I

i 08/03/83 9.0 MANAGEMENT OF THE EXTENDED CONSTRUCTION DELAY The principles for management of the construction delay are presented in Section 1.4 of the Level I Executive Summary and will be the basis for implementation by Department Managers.

9.1 DEPARTMENT MANAGEMENT RESPONSIBILITIES Management of the extended construction delay is the direct responsibility of the Department Managers of the Supply System.

Each Manager will be responsible for accomplishing those activities within his/her area of responsibility on the defined schedule and within budget. The integrity of the overall financial baseline defined in Section 1.0 must be maintained and is the collective respon-sibility of each manager.

9.2 PROGRAM RESPONSIBILITIES The Program (i.e., the Program Director and appropriate members of his staff) is to provide assistance to department managers in developing and implementing actions and is to provide a consolidated report and evaluation. The Program Director will continue to report to the Managing Director on all matters related to the extended construction delay. The functions of the Program will be as follows:

e Develop and publish a consolidated Monthly Progress Report.

e Identify any requirements or additional initiatives for executing the delay.

Assist managers as required in the implementation of the extended construc-tion delay.

a Review the experience of other nuclear utilities in extended delays on their plants.

e Review Supply System performance on accomplishing required tasks. _

08/03/83 s

Review total expenditures versus baseline and funds availability to identify possible variance trends or overruns.

e Identify and analyze potential areas for further savings.

e Process Project Change Proposals e

Update plan as necess6ry.

9.3 ACTIONS & REPORTING GUIDELINES The following reports / input are required:

e Financial (Responsibility of S. B. Merlin)

- Monthly Rolling Cash Flow Budget Line Item Prepurchased and Construction Detail Variance Analysis Graphic Display

- Monthly / Fiscal Year To Date Cash Summary Budget vs. Actual Prepurchased and Ccnstruction Detail Construction and Non Construction Major One Time Activities Variance Analysis

- Monthly / Fiscal Year To Date Cost Summary Budget Line Item l

Budget vs. Actual Prepurchased and Construction Detail Construction and Non Construction Major One Time Cost Variance Analysis

- Monthly / Fiscal Year To Date Project Manpower Budget vs. Actual Contract and Department Detail Construction vs. Non Construction Variance Analysis -

08/03/83

- Monthly Summary Financial Assessment Cost / Cash / Status Performance / Trend Analysis e

Licensing (responsibility of K. W. Cook)

- Status of Draft SER Questions received, response schedule status, open items, etc.

- Status of Major Issues

- Status of Rampdown Activities

- Status of Preservation Activities

- Status of Operating Experience Review Size of data base, backlog, review status.

- Status of Nuclear Safety Assurance reporting.

e Documentation & Records (responsibility of M. C. Robb)

- Status of required records received from Contractors, reviewed and vaulted by AE/CM as measured by completion percentages vs. expectations.

- Status of records transfer from headquarters to site measured by progress towards intermediate milestones.

- Status of consolidation of on-site records processing functions measured by progress towards intermediate milestones.

e Asset Preservation (responsibility of J. W. Wilson)

- Status of component turnovers to Supply System.

- Status of Preventative Maintenance.

- Status of critical skills staffing.

- Status of procedures required to operate and maintain systems turnover to Operations.

- Status of fragnet development.

.=.

08/03/83 e

Construction (responsibility of J. J. Peterson)

- Manpower (actual vs budget)

- Cost / Cash flows (actual vs budget)

- Construction completion in support of rampdown/ preservation.

- Monthly Accomplishments

- Documentation Submittals

- Number of packages submitted, reviewed and approved.

- Materials Management

- Returned to warehouse status, inventory and store statuses.

- Construction contract closecut status.

- Safety status.

- NCR, DDNs and Conditional Releases

- Issued, dispositioned and cleared e

Engineering (responsibility of J. E. Werle)

- Status of FSAR Connittments.

- Status of Engineering Key Items:

Stiff Clamps Beam Coping Nozzle Loads (Othersasidentified)

- Status of Drawing Roll-up

- Status of NCR Closecut

- Status of Start-Up Systems Design Freeze

- Status of DCN, QFPCP Closeout

- Status of Equipment Qualification Activities

- Status of Vendor Drawings

- Status of System Review Action Items Lists Setpoints

- A/E Manpower Levels

- Budgeted Cost of Work Scheduled

- Bi-Monthly Engineering Review Meetings

- Bi-Monthly SAIL Meetings

08/03/83

,e e

Business (responsibilityofR.N. Williams)

- Status of contract closeout actions by contract.

- Status of negotiations implementing partial suspension by contract.

- Status of negotiations implementing total suspension by contract.

- Status of negotiations implementing termination by contract.

Identification of those pending actions which appear to have significant potential of impacting the estimated cost / cash flow by an amount in excess of $100,000.

e Quality Assurance (responsibility of 0. E. Trapp)

- Status of NRC items.

- Status of Records turnover and review.

- Status of vendor surveillance /VQA.

- Status of Asset Preservation Program / Preventative Maintenance.

- Status of closeout and construction work.

. - _ _... -...., _ _. - _ - _ _ _.. - -