2CAN028316, Responds to Re Schedule for Core Protection Computer Mods to Correct Low Power Density Penalty Factor.Correction Will Be Provided During Next Software Update.Schedule Should Be Available by 830530: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:_ _ - . _ _ _ _
{{#Wiki_filter:,
ARKANSAS FOWER & LtGHT COMPANY POST OFFICE box 551 UTTLE ROCK. ARKANSAS 72203 (501)371-4000 February 25, 1983 1
ARKANSAS FOWER & LtGHT COMPANY POST OFFICE box 551 UTTLE ROCK. ARKANSAS 72203 (501)371-4000 February 25, 1983 1
2CAN028316 Director of Nuclear Reactor Regulation ATTN: Mr. Robert A. Clark, Chief Operating Reactors Branch #3 Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555
2CAN028316 Director of Nuclear Reactor Regulation ATTN: Mr. Robert A. Clark, Chief Operating Reactors Branch #3 Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555
Line 24: Line 24:
Arkansas Nuclear One - Unit 2 Docket No. 50-368 License No. NPF-6 CPC Software Discrepancy Gentlemen:
Arkansas Nuclear One - Unit 2 Docket No. 50-368 License No. NPF-6 CPC Software Discrepancy Gentlemen:
Your {{letter dated|date=February 6, 1983|text=letter dated February 6, 1983}}, (2CNA028302) requested we provide you, within 30 days from receipt, a schedule for the CPC modifications to correct the Low Power Density (LPD) penality factor.
Your {{letter dated|date=February 6, 1983|text=letter dated February 6, 1983}}, (2CNA028302) requested we provide you, within 30 days from receipt, a schedule for the CPC modifications to correct the Low Power Density (LPD) penality factor.
As we have previously informed you, we intend to provide this correction at the next CPC software update. Currently, we have meetings scheduled with Combustion Engineering (our NSSS vendor) to discuss future CPC software modifications. Following these meetings, we will be in a position to provide you a more specific schedule for these modifications.
As we have previously informed you, we intend to provide this correction at the next CPC software update.
Currently, we have meetings scheduled with Combustion Engineering (our NSSS vendor) to discuss future CPC software modifications.
Following these meetings, we will be in a position to provide you a more specific schedule for these modifications.
We expect to be able to provide this schedule on or about May 30, 1983.
We expect to be able to provide this schedule on or about May 30, 1983.
This information and schedule was discussed with your Mr. Oliver Lynch on February 25, 1983. Mr. Lynch concurred in this schedule.
This information and schedule was discussed with your Mr. Oliver Lynch on February 25, 1983.
Mr. Lynch concurred in this schedule.
Very truly yours,
Very truly yours,
                                                                                    ~
~
John R. Marshall Manager, Licensing JRM:JTE:s1
John R. Marshall Manager, Licensing JRM:JTE:s1
                                                                                                            / ol     o 0303040333 830225                                                                                                 L PDR ADOCK 05000368 p                 PDR MEMBEFI MIDOLE SOUTH UTILITIES SYSTEM
/ ol o
_ _ _ _ _ _ _ _ _ _ _ _ _ . . _ _ _ _}}
0303040333 830225 L
PDR ADOCK 05000368 p
PDR MEMBEFI MIDOLE SOUTH UTILITIES SYSTEM
_ _ _ _ _ _ _ _ _ _ _ _ _.. _ _ _ _}}

Latest revision as of 23:00, 14 December 2024

Responds to Re Schedule for Core Protection Computer Mods to Correct Low Power Density Penalty Factor.Correction Will Be Provided During Next Software Update.Schedule Should Be Available by 830530
ML20079N578
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 02/25/1983
From: John Marshall
ARKANSAS POWER & LIGHT CO.
To: Clark R
Office of Nuclear Reactor Regulation
References
2CAN028316, 2CAN28316, NUDOCS 8303040333
Download: ML20079N578 (1)


Text

,

ARKANSAS FOWER & LtGHT COMPANY POST OFFICE box 551 UTTLE ROCK. ARKANSAS 72203 (501)371-4000 February 25, 1983 1

2CAN028316 Director of Nuclear Reactor Regulation ATTN: Mr. Robert A. Clark, Chief Operating Reactors Branch #3 Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555

SUBJECT:

Arkansas Nuclear One - Unit 2 Docket No. 50-368 License No. NPF-6 CPC Software Discrepancy Gentlemen:

Your letter dated February 6, 1983, (2CNA028302) requested we provide you, within 30 days from receipt, a schedule for the CPC modifications to correct the Low Power Density (LPD) penality factor.

As we have previously informed you, we intend to provide this correction at the next CPC software update.

Currently, we have meetings scheduled with Combustion Engineering (our NSSS vendor) to discuss future CPC software modifications.

Following these meetings, we will be in a position to provide you a more specific schedule for these modifications.

We expect to be able to provide this schedule on or about May 30, 1983.

This information and schedule was discussed with your Mr. Oliver Lynch on February 25, 1983.

Mr. Lynch concurred in this schedule.

Very truly yours,

~

John R. Marshall Manager, Licensing JRM:JTE:s1