ML20095C168: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot insert
 
StriderTol Bot change
 
Line 17: Line 17:
=Text=
=Text=
{{#Wiki_filter:j
{{#Wiki_filter:j
+e Tennessee Valley Authority, Post Offce Box 2000, Soddy-Daisy, Temessee 37379-2000 1
+e Tennessee Valley Authority, Post Offce Box 2000, Soddy-Daisy, Temessee 37379-2000 1
December 1, 1995 U.S. Nuclear Regulatory Commission ATTN     Document Control Desk Washington, D.C. 20555 Gentlemen In the Matter of                                         )                         Docket Nos. 50-327               ,
December 1, 1995 U.S. Nuclear Regulatory Commission ATTN Document Control Desk Washington, D.C. 20555 Gentlemen In the Matter of
          ' Tennessee Valley Authority                             )                                       50-328             l SEQUOYAH NUCLEAR PLANT (SQN) - FIRE PROTECTION IMPROVEMENT PLAN PERIODIC                                           l STATUS REPORT A working meeting between TVA and NRC was held at SQN on August 19, 1991,                                           f to discuss the self-identified problems in SQN's Fire Protection Program and the improvement plan efforts initiated by TVA.                             As a result of this meeting, TVA agreed to submit periodic status reports to inform NRC on the progress of efforts made in conjunction with the improvement plan.
)
l The most recent status report identifying progress achieved and areas                                               i I
Docket Nos. 50-327
' Tennessee Valley Authority
)
50-328 SEQUOYAH NUCLEAR PLANT (SQN) - FIRE PROTECTION IMPROVEMENT PLAN PERIODIC l
STATUS REPORT A working meeting between TVA and NRC was held at SQN on August 19, 1991, f
to discuss the self-identified problems in SQN's Fire Protection Program and the improvement plan efforts initiated by TVA.
As a result of this meeting, TVA agreed to submit periodic status reports to inform NRC on the progress of efforts made in conjunction with the improvement plan.
The most recent status report identifying progress achieved and areas i
needing further action is included in the enclosure.
needing further action is included in the enclosure.
The original targeted completion date for activities specified in the Fire Protection Improvement Plan was set for December 1, 1994. This was later revised to December 1, 1995 as a result of the impact of a two-unit outage involving erosion and corrosion problems and the associated engineering evaluations.
The original targeted completion date for activities specified in the Fire Protection Improvement Plan was set for December 1, 1994. This was later revised to December 1, 1995 as a result of the impact of a two-unit outage involving erosion and corrosion problems and the associated engineering evaluations.
Significant progress has been made toward completion of the four phases of the Fire Protection Improvement Plan. As reflected in the enclosure, Phases 1, 2, and 3 are complete, and the only Phase 4 item that is not complete is the SQN Fire Protection Report. The design for a potable water fire protection supply system was issued in June 1995, and the installation is underway. Due to the complexity of the system and the                                               i significant financial resources required to complete this modification,                                             l it is not anticipated that the system will be operable until late 1997.                                             l The potable water system was anticipated to be the primary system used as                                           l the basis for the Fire Protection Report.                                                                     ,    l l
Significant progress has been made toward completion of the four phases of the Fire Protection Improvement Plan. As reflected in the enclosure, Phases 1, 2, and 3 are complete, and the only Phase 4 item that is not complete is the SQN Fire Protection Report. The design for a potable water fire protection supply system was issued in June 1995, and the installation is underway. Due to the complexity of the system and the i
l 94 n 9512110393 951201 PDR AD
significant financial resources required to complete this modification, it is not anticipated that the system will be operable until late 1997.
                                                                                                                    ,Q     i t
The potable water system was anticipated to be the primary system used as the basis for the Fire Protection Report.
        .- E . ,.OCK~ .05000327  _   _PDR
l l
9512110393 951201
,Q 94 n t
PDR AD i
.- E.
,.OCK 05000327
_PDR
~. _


    %    A- .
A-
      '$r                                                                                           p l
'$r p
U.S. Nuclear Regulatory Commission                                             .t
l
                ,Page 2 December 1, 1995 However, due to the potential for the operability of the potable water
.t U.S. Nuclear Regulatory Commission
                . system being extended until late 1997, the report will include provisions for the current rav water system. 'Also, SQN has been closely following
,Page 2 December 1, 1995 However, due to the potential for the operability of the potable water
                -the NRC review /approvkl of the Fire Protection Report for Watts Bar Nuclear Plant (f /BN) . SCW will utilize a format similar to the WBN report and will incoryorate lesscus learned during the NRC review of WBN's l report.. Final comments wer6 received and resolved for WBN in October this year. Therefore, SQN is .* vising the commitment date to complete           !
. system being extended until late 1997, the report will include provisions for the current rav water system. 'Also, SQN has been closely following
Phase 4 of tha Fire Protection Impr9vement Plan to August 30, 1996.             ,
-the NRC review /approvkl of the Fire Protection Report for Watts Bar Nuclear Plant (f /BN). SCW will utilize a format similar to the WBN report and will incoryorate lesscus learned during the NRC review of WBN's l report.. Final comments wer6 received and resolved for WBN in October this year. Therefore, SQN is.* vising the commitment date to complete Phase 4 of tha Fire Protection Impr9vement Plan to August 30, 1996.
Since there is now only one outstanding item, and no significant status changes are expected for this item until'it is completed, periodic status reports in the interim would not convey any new information. Therefore,
Since there is now only one outstanding item, and no significant status changes are expected for this item until'it is completed, periodic status reports in the interim would not convey any new information. Therefore, this report will be the last periodic status report on the Fire Protection Improvement Plan. TVA will notify NRC when the remaining open
* this report will be the last periodic status report on the Fire Protection Improvement Plan. TVA will notify NRC when the remaining open
-item is complete. NRC will also be notified if there are any changes to the existing schedule for completion.
                -item is complete. NRC will also be notified if there are any changes to the existing schedule for completion.
If you have any questions concerning this submittal, please telephone S. D. Gilley at (423) 843-7427.
If you have any questions concerning this submittal, please telephone S. D. Gilley at (423) 843-7427.
t sincerely, b h . ,A     l/                                                                 c R. H. Shell Manager SQN Site Licensing i
t sincerely, b h.,A l/
c R. H. Shell Manager SQN Site Licensing i
Enclosure cc (Enclosure):
Enclosure cc (Enclosure):
Mr. D. E. LaBarge, Project Manager U.S. Nuclear Regulatory Commission one White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 NRC Resident Inspector                                                     ]
Mr. D. E. LaBarge, Project Manager U.S. Nuclear Regulatory Commission one White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 NRC Resident Inspector
Sequoyah Nuclear Plant                                                     ]
]
                        -2600 Igou Ferry Road Soddy-Daisy, Tennessee 37379-3624 l
Sequoyah Nuclear Plant
Regional Administrator U.S. Nuclear Regulatory Commission E                       Region II
]
[                       .101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323-2711 l
-2600 Igou Ferry Road Soddy-Daisy, Tennessee 37379-3624 l
1 i
Regional Administrator U.S. Nuclear Regulatory Commission E
 
Region II
:*2   fi ..
[
                ?.
.101 Marietta Street, NW, Suite 2900 l
e-
Atlanta, Georgia 30323-2711 1
                  ''                                                ENCLOSURE'
i
                      ' FIRE PROTECTION IMPROVEMENT PLAN - STATUS FOR PERIOD ENDING.
:*2 fi..
NOVEMBER- 30,-1995' Phane'I - Phase I is'ca= alate Phmae II - Phase II is Camalate p
?.
Phman III - Phmae III is Complete Phase IV - Taracted ea-alation Data Auaust 30, 1996 4-1           Perform an independent fire protection assessment to ensure that     .:
e-ENCLOSURE'
the actions taken in Phase III are properly Laplemented and           l effective.- This-item is complete.                                     j
' FIRE PROTECTION IMPROVEMENT PLAN - STATUS FOR PERIOD ENDING.
                        '4-2           Complete an evaluation of the mechanical and electrical fire           :
NOVEMBER-30,-1995' Phane'I - Phase I is'ca= alate Phmae II - Phase II is Camalate p
barrier penetration seals in accordance with the guidelines in         l Information Notice No. 88-04. This item was rescheduled and           i
Phman III - Phmae III is Complete Phase IV - Taracted ea-alation Data Auaust 30, 1996 4-1 Perform an independent fire protection assessment to ensure that the actions taken in Phase III are properly Laplemented and l
                                      . completed during Phase III as Item 3-8.                             l l
effective.- This-item is complete.
4-3           Issue the remaining updated design documentation to support the     'l final compilation into the SQN Fire Protection Report and establish a process to maintain the documenb Ton current.
j
I                                       Status     Work required for the submittal of the Fire Protection Report is approximately 10 percent complete. The Fire Protection. Report is expected to be submitted by 1                                                 August 30, 1996.
'4-2 Complete an evaluation of the mechanical and electrical fire barrier penetration seals in accordance with the guidelines in l
j 4-4           Issue a design package for Project Control No. (PCN) 607.
Information Notice No. 88-04.
                                      -Status: The design package for this item was issued in June 1995.
This item was rescheduled and i
: j.                                                 This item is complete.
. completed during Phase III as Item 3-8.
1The final design for the new fire protection pumping system being installed at SQN involves an extensive
l l
,                                                  redesign of the system. The final design involves the following features:     (1) replacement of the existing
4-3 Issue the remaining updated design documentation to support the
                                                  . pumping. system; (2) abandonment of the current pressure control system; (3) pigging and replacement, when
'l final compilation into the SQN Fire Protection Report and establish a process to maintain the documenb Ton current.
                                                  'necessary, to remove flow inhibiting corrosion and degraded piping; and (4) performance of a full system hydrostatic test prior to declaring the new system           !
I Status Work required for the submittal of the Fire Protection Report is approximately 10 percent complete. The Fire Protection. Report is expected to be submitted by 1
operational. .The new design establishes a more reliable
August 30, 1996.
                                                  . fire protection system. Detailed life cycle analysis of the existing fire protection system was not warranted
j 4-4 Issue a design package for Project Control No. (PCN) 607.
.                                                  because.of the extensive nature of the system redesign.     ,
-Status: The design package for this item was issued in June 1995.
l
j.
      .-_                . _ . . . _        _2          - -        - -              --
This item is complete.
1The final design for the new fire protection pumping system being installed at SQN involves an extensive redesign of the system. The final design involves the following features:
(1) replacement of the existing
. pumping. system; (2) abandonment of the current pressure control system; (3) pigging and replacement, when
'necessary, to remove flow inhibiting corrosion and degraded piping; and (4) performance of a full system hydrostatic test prior to declaring the new system operational..The new design establishes a more reliable
. fire protection system. Detailed life cycle analysis of the existing fire protection system was not warranted because.of the extensive nature of the system redesign.
l 2


.e.  ,.
.e.
e.
e.
4'-5 ' Ferform a life-cycle analysis on high-pressure fire protection components and provide replacement-recommendations.
4'-5 ' Ferform a life-cycle analysis on high-pressure fire protection components and provide replacement-recommendations.
status: This item will be accomplished in conjunction with the
status: This item will be accomplished in conjunction with the
                          , upgrade to the fire protection system within the scope of-
, upgrade to the fire protection system within the scope of-
                          . PCN 607. This item should be considered an integral part of Item 4-4.
. PCN 607. This item should be considered an integral part of Item 4-4.
a l
a l
1 l
l i
                                                    .                                  i
...}}
                      .      .                        . ..}}

Latest revision as of 08:47, 13 December 2024

Submits Periodic Status Rept for Fire Protection Improvement Plan for Period Ending 951130
ML20095C168
Person / Time
Site: Sequoyah  
Issue date: 12/01/1995
From: Shell R
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9512110393
Download: ML20095C168 (4)


Text

j

+e Tennessee Valley Authority, Post Offce Box 2000, Soddy-Daisy, Temessee 37379-2000 1

December 1, 1995 U.S. Nuclear Regulatory Commission ATTN Document Control Desk Washington, D.C. 20555 Gentlemen In the Matter of

)

Docket Nos. 50-327

' Tennessee Valley Authority

)

50-328 SEQUOYAH NUCLEAR PLANT (SQN) - FIRE PROTECTION IMPROVEMENT PLAN PERIODIC l

STATUS REPORT A working meeting between TVA and NRC was held at SQN on August 19, 1991, f

to discuss the self-identified problems in SQN's Fire Protection Program and the improvement plan efforts initiated by TVA.

As a result of this meeting, TVA agreed to submit periodic status reports to inform NRC on the progress of efforts made in conjunction with the improvement plan.

The most recent status report identifying progress achieved and areas i

needing further action is included in the enclosure.

The original targeted completion date for activities specified in the Fire Protection Improvement Plan was set for December 1, 1994. This was later revised to December 1, 1995 as a result of the impact of a two-unit outage involving erosion and corrosion problems and the associated engineering evaluations.

Significant progress has been made toward completion of the four phases of the Fire Protection Improvement Plan. As reflected in the enclosure, Phases 1, 2, and 3 are complete, and the only Phase 4 item that is not complete is the SQN Fire Protection Report. The design for a potable water fire protection supply system was issued in June 1995, and the installation is underway. Due to the complexity of the system and the i

significant financial resources required to complete this modification, it is not anticipated that the system will be operable until late 1997.

The potable water system was anticipated to be the primary system used as the basis for the Fire Protection Report.

l l

9512110393 951201

,Q 94 n t

PDR AD i

.- E.

,.OCK 05000327

_PDR

~. _

A-

'$r p

l

.t U.S. Nuclear Regulatory Commission

,Page 2 December 1, 1995 However, due to the potential for the operability of the potable water

. system being extended until late 1997, the report will include provisions for the current rav water system. 'Also, SQN has been closely following

-the NRC review /approvkl of the Fire Protection Report for Watts Bar Nuclear Plant (f /BN). SCW will utilize a format similar to the WBN report and will incoryorate lesscus learned during the NRC review of WBN's l report.. Final comments wer6 received and resolved for WBN in October this year. Therefore, SQN is.* vising the commitment date to complete Phase 4 of tha Fire Protection Impr9vement Plan to August 30, 1996.

Since there is now only one outstanding item, and no significant status changes are expected for this item until'it is completed, periodic status reports in the interim would not convey any new information. Therefore, this report will be the last periodic status report on the Fire Protection Improvement Plan. TVA will notify NRC when the remaining open

-item is complete. NRC will also be notified if there are any changes to the existing schedule for completion.

If you have any questions concerning this submittal, please telephone S. D. Gilley at (423) 843-7427.

t sincerely, b h.,A l/

c R. H. Shell Manager SQN Site Licensing i

Enclosure cc (Enclosure):

Mr. D. E. LaBarge, Project Manager U.S. Nuclear Regulatory Commission one White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 NRC Resident Inspector

]

Sequoyah Nuclear Plant

]

-2600 Igou Ferry Road Soddy-Daisy, Tennessee 37379-3624 l

Regional Administrator U.S. Nuclear Regulatory Commission E

Region II

[

.101 Marietta Street, NW, Suite 2900 l

Atlanta, Georgia 30323-2711 1

i

  • 2 fi..

?.

e-ENCLOSURE'

' FIRE PROTECTION IMPROVEMENT PLAN - STATUS FOR PERIOD ENDING.

NOVEMBER-30,-1995' Phane'I - Phase I is'ca= alate Phmae II - Phase II is Camalate p

Phman III - Phmae III is Complete Phase IV - Taracted ea-alation Data Auaust 30, 1996 4-1 Perform an independent fire protection assessment to ensure that the actions taken in Phase III are properly Laplemented and l

effective.- This-item is complete.

j

'4-2 Complete an evaluation of the mechanical and electrical fire barrier penetration seals in accordance with the guidelines in l

Information Notice No. 88-04.

This item was rescheduled and i

. completed during Phase III as Item 3-8.

l l

4-3 Issue the remaining updated design documentation to support the

'l final compilation into the SQN Fire Protection Report and establish a process to maintain the documenb Ton current.

I Status Work required for the submittal of the Fire Protection Report is approximately 10 percent complete. The Fire Protection. Report is expected to be submitted by 1

August 30, 1996.

j 4-4 Issue a design package for Project Control No. (PCN) 607.

-Status: The design package for this item was issued in June 1995.

j.

This item is complete.

1The final design for the new fire protection pumping system being installed at SQN involves an extensive redesign of the system. The final design involves the following features:

(1) replacement of the existing

. pumping. system; (2) abandonment of the current pressure control system; (3) pigging and replacement, when

'necessary, to remove flow inhibiting corrosion and degraded piping; and (4) performance of a full system hydrostatic test prior to declaring the new system operational..The new design establishes a more reliable

. fire protection system. Detailed life cycle analysis of the existing fire protection system was not warranted because.of the extensive nature of the system redesign.

l 2

.e.

e.

4'-5 ' Ferform a life-cycle analysis on high-pressure fire protection components and provide replacement-recommendations.

status: This item will be accomplished in conjunction with the

, upgrade to the fire protection system within the scope of-

. PCN 607. This item should be considered an integral part of Item 4-4.

a l

l i

...