#REDIRECT [[W3P84-1254, Amends Schedule for Submittal of Detailed Control Room Design Review Program Plan Per Suppl 1 to NUREG-0737 to 841001 & Summary Rept to 850301,per Request.Summary Rept Schedule Tentative Based on NRC Review of Program Plan]]
| number = ML20084J774
| issue date = 05/07/1984
| title = Amends Schedule for Submittal of Detailed Control Room Design Review Program Plan Per Suppl 1 to NUREG-0737 to 841001 & Summary Rept to 850301,per Request.Summary Rept Schedule Tentative Based on NRC Review of Program Plan
| author name = Cook K
| author affiliation = LOUISIANA POWER & LIGHT CO.
| addressee name = Knighton G
| addressee affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR)
| docket = 05000382
| license number =
| contact person =
| case reference number = RTR-NUREG-0737, RTR-NUREG-737
| document report number = W3P84-1254, NUDOCS 8405100063
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
| page count = 2
}}
 
=Text=
{{#Wiki_filter:_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
o LOUISIANA            242 ouanONoe sineer POWER & LIGHT        P O. BOX 6008
* NEW OnLEANS. LOUISIANA 70174 + (504) 366-2345
      $EONEsSEU May 7, 1984 W3P84-1254 3-A1.01.04 3-H1 Director of Nuclear Reactor Regulation Attention: Mr. G.W. Knighton, Chief Licensing Branch No. 3 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555
 
==SUBJECT:==
Waterford SES Unit 3 Docket No. 50-382 Detailed Control Room Design Review (DCRDR)
 
==REFERENCE:==
W3P84-1005 dated April 10, 1984
 
==Dear Sir:==
 
In the referenced letter LP&L committed to providing the DCRDR program plan and summary report in one submittal scheduled for January 31, 1985.
However, at the request of your staff, we are amending our schedule to allow for a two-fold submittal as follows:
Submittal Report                                Date Program Plan                        October 1, 1984 Summary Report                      March 1, 1985 1
Due to this change some qualifying remarks are in order. The Program Plan                                                            l will not necessarily be a listing of intended actions but rather a descrip-                                                          '
tion of what has been completed. As you know, most was completed prior to issuance of the NUREC 0737 Su(DCRDR  pplement  work at Waterford I requirement                                              l for submittal of a Program Plan', Additionally, the Summary Report schedule is tentative, dependent upon the timely review by your staff of the Program Plan and the extent of comments received that must be addressed in the Summary Report.
8405100063 840507 PINT ADOCK 05000tM32 F                  pm                                                                                                        3
                                                                                                                                      ) ()
 
      . =.                                --.              _ _ _
o Should you require additional information on this matter please feel free l to contact Mike Meisner at (504) 363-8938.
Yours very truly, K.W. Cook Nuclear Support & Licensing Manager KWC/MJM/pco cc:  E.L.-Blake, W.M. Stevenson, J.T. Collins, D.M. Crutchfield, J. Wilson, G.L. Constable, D. Tondi 4