#REDIRECT [[TXX-6850, Interim Deficiency Rept CP-87-100 Re Three Containment Isolation Penetrations That May Lack Relief Protection. Initially Reported on 870910.Evaluation Continuing.Next Rept Will Be Submitted by 871211]]
| number = ML20235U663
| issue date = 10/08/1987
| title = Interim Deficiency Rept CP-87-100 Re Three Containment Isolation Penetrations That May Lack Relief Protection. Initially Reported on 870910.Evaluation Continuing.Next Rept Will Be Submitted by 871211
| author name = Counsil W, Marshall J
| author affiliation = TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
| addressee name =
| addressee affiliation = NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
| docket = 05000445, 05000446
| license number =
| contact person =
| document report number = CP-87-100, TXX-6850, NUDOCS 8710140189
| document type = DEFICIENCY REPORTS (PER 10CFR50.55E & PART 21), TEXT-SAFETY REPORT
| page count = 1
}}
 
=Text=
{{#Wiki_filter:_ ___
                                                              ,    E.--                  Log # TXX-6850 Fi1e:# 10110
                                                              =      =                            906.2 7t/ ELECTRIC                  Ref # 10CFR50.55(e)
[
                                                                                          -October 8,1987 .
William G. Counsil Esecutive Vice President U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555
 
==SUBJECT:==
- COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445~AND 50-446                                                        .
CONTAINMENT PENETRATION OVERPRESSURE                                                j PROTECTION
                              .SDAR: CP-87-100(INTERIMREPORT)
Gentlemen:
On September 10, 1987, we verbally notified yc ~ Mr. I. Barnes of a deficiency involving three containment isolation penetrations that may lack relief protectiori . Specifically, the design validation process has revealed that one Safety Injection System containment penetration and two Primary Sampling System containment penetrations, which are water solid and isolable, may lack overpressure protection. This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e).
We are continuing our evaluation and anticipated submitting our next report by December 11, 1987.
Very truly yours, (d C. Couns A W. G. Counsil By /                4  4 (J. S. Marshall              j Supervisor,                J Generic, Licensing        )
CBC/grr c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) 8710140189 871000                                                                                          (