ML20138D168: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 1: Line 1:
{{Adams
#REDIRECT [[U-600334, Provides Quarterly Update on Const schedule.Full-scale Emergency Preparedness Exercise Dress Rehearsal & Nrc/Fema Observed Emergency Preparedness Exercise Conducted on 851119 & 851204,respectively]]
| number = ML20138D168
| issue date = 12/11/1985
| title = Provides Quarterly Update on Const schedule.Full-scale Emergency Preparedness Exercise Dress Rehearsal & Nrc/Fema Observed Emergency Preparedness Exercise Conducted on 851119 & 851204,respectively
| author name = Hall D
| author affiliation = ILLINOIS POWER CO.
| addressee name = Denton H
| addressee affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR)
| docket = 05000461
| license number =
| contact person =
| document report number = U-600334, NUDOCS 8512130162
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
| page count = 2
}}
 
=Text=
{{#Wiki_filter:N U-600334 C30-85 (12 - 11)-L 1A.120 ILLINDIS POWER 00MPANY CLINTON POWER STATION P.O. BOX 678. CLINTON. ILLINOIS 61727 December 11, 1985 Docket No. 50-461 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555
 
==Subject:==
Clinton Power Station Construction Schedule Update
 
==Dear Mr. Denton:==
 
The USNRC letter dated May 29, 1981, from H. R. Denton to W. J. Kelley requested Illinois Power Company provide quarterly updates concerning the Clinton I construction schedule.
The September analysis of the project schedule indicated that the limiting critical path was the preparation of a preoperational test procedure for the Fire Protection System, which was fifty-six days behind. The latest analysis (October) indicated that delays to the Fire Protection System now result in a sixty-one day delay to Fuel load. Management emphasis is dedicated to recover as much of the delay as possible.
Two milestones have been achieved since September.                                                                                                                              The Full-Scale (on and off site) Emergency Preparedness Exercise Dress Rehearsal and the NRC/ FEMA observed Emergency Preparedness Exercise were conducted on November 19, 1985, and December 4, 1985,.respectively.                                                                                                                                                  Both events were conducted successfully on schedule.
On November 27, 1985, the company announced that construction at the Clinton Power Plant will be essentially complete at the end of December 1985, by which time all systems will be turned over to Illinois Power for testing.
Because of the delay in completing systems for testing, the company now anticipates that fuel loading will occur between late February and late March _1986.
non - vac'. neu somat 8512130162 851211                                                                                                                                                                  Na      * *)              '  #
PDR  ADOCK 05000461
?                F                                                                                    pyg                                                                                                  go 8C8"(5""g'"^"I
[
AD - G. RAINAS (1.tr enly) i
___.____.__m        _________._.,_______.___.________________._.__,.____________.______m___..___,___.____________.__________.___________,__,__________,,_,_,__m,_,_.__._.,.,______._____.,___m
 
F:
U-600334 C30-85 (12 -11 )-L 1A.120 We will continue to submit quarterly updates of the
: Clinton Power Station construction schedule.
Sincerely yours,
                                              .  . Hall Vice President CDS/ckc cc:  Mr. B. Siegel, NRC Clinton Project Manager NRC Resident Office Illinois Dept. of Nuclear Safety Regional Administrator, Region III, USNRC e
i
  ~
  'I
!-                                                                                j}}

Latest revision as of 03:43, 13 December 2021